(a) 100 mm dia 20'-0" long pipe: 20 ft. @ Tk. 79.00 per ft =

(b) Fittings:

  1. Bend/45O bend/off-set/cowel 1 no @ Tk. 146.00 each =
  2. Tee/T-Y/Y 1 no @ Tk. 179.00 each =

(c) Jointing & fixing materials

  1. Solvent cement 30 ml @ Tk. 0.70 per ml =
  2. Clamp 8 nos @ Tk. 50.00 each =
  3. Rowel plug & screw 16 nos @ Tk. 13.00 each =
  4. Scaffolding 20 ft. @ Tk. 3.00 per ft =

(d) Labour:

Tk.

Tk. Tk.

Tk. Tk. Tk. Tk.

1,580.00

146.00

179.00

21.00 400.00 208.00 60.00

  1. Plumber 0.5 no @ Tk. 600.00 each =

Tk.

300.00

  1. Skilled labour 1 no @ Tk. 390.00 each =

Tk.

390.00

  1. Ordinary labour 0.8 no @ Tk. 320.00 each =

Tk.

256.00

Sub - Total =

Tk.

3,540.00

Profit 10.00% =

Tk.

354.00

Overhead 3.50% =

Tk.

123.90

Total =

Tk.

4,017.90

Add VAT with adjustment factor 1.06383 6.00% =

Tk.

256.46

Grand Total =

Tk.

4,274.36

Rate per ft =

Tk.

213.72

Rate per m =

Tk.

701.22

Say, Tk. 701 .00 per meter

 

 

 

 

 

Item No.- 26.32

 

 

26.32.1 [ For Underground Work ]

 

 

26.32.1.1 Supplying, laying, fitting , fixing 110 mm/4" outer diameter PE-100, PN-6 , HDPE Soil, Waste & Ventilation Pipe

 

 

Considering 20 ft. long HDPE one pipe

(a) 110 mm dia 20'-0" long pipe: 20 ft. @ Tk. 167.00 per ft =

(b) Fittings:

Tk.

3,340.00

  1. 110 mm HDPE Plain Tee/T-Y 0.25 no @ Tk. 646.00 each =

Tk.

161.50

  1. 110 mm HDPE Plain Bend 0.5 no @ Tk. 465.00 each =

(c) Jointing & fixing Materials

Tk.

232.50

Butt fusion welding joint 1 @ Tk. 350.00 per gm =

Tk.

350.00

(d) Excavation (underground) 62.5 cft @ Tk. 2,958.33 per % cft =

Tk.

184.90

(e) Bedding by sand (FM 0.8) (underground) 38.8 cft @ Tk. 1,400.00 per %0 cft =

(d) Labour:

Tk.

543.20

  1. Plumber 0.5 no @ Tk. 600.00 each =

Tk.

300.00

  1. Skilled labour 0.5 no @ Tk. 390.00 each =

Tk.

195.00

  1. Ordinary labour 0.8 no @ Tk. 320.00 each =

Tk.

256.00

Sub - Total =

Tk.

5,563.10

Profit 10.00% =

Tk.

556.31

Overhead 3.50% =

Tk.

194.71

Total =

Tk.

6,314.12

Add VAT with adjustment factor 1.06383 6.00% =

Tk.

403.03

Grand Total =

Tk.

6,717.15

Rate per ft =

Tk.

335.86

Rate per m =

Tk.

1,101.96

Say, Tk. 1,102 .00 per meter

 

 

26.32.1.2 Supplying, laying, fitting , fixing 160 mm/6" outer diameter PE-100, PN-6 , HDPE Soil, Waste & Ventilation Pipe

 

 

Considering 20 ft. long HDPE one pipe

(a) 160 mm dia 20'-0" long pipe: 20 ft. @ Tk. 307.00 per ft =

(b) Fittings:

Tk.

6,140.00

  1. 160 mm HDPE Plain Tee/T-Y 0.25 no @ Tk. 916.00 each =

Tk.

229.00

  1. 160 mm HDPE Plain Bend 0.5 no @ Tk. 802.00 each =

(c) Jointing & fixing Materials

Tk.

401.00

Butt fusion welding joint 1 Tk. 350.00 each =

Tk.

350.00

(d) Excavation (underground) 62.5 cft @ Tk. 2,958.33 per % cft =

Tk.

184.90

(e) Bedding by sand (FM 0.8) (underground) 38.8 cft @ Tk. 1,400.00 per % cft =

Tk.

543.20