26.32.1.5 | Rate per ft = Rate per m = | Tk. Tk. | 1,469.81 4,822.45 |
Say, Tk. 4,822 .00 per meter | |||
Supplying, laying, fitting , fixing 280 mm/11" outer diameter PE-100, PN-6 , HDPE Soil, Waste & Ventilation Pipe | |||
| Considering 20 ft. long HDPE one pipe |
|
|
(a) | 280 mm dia 20'-0" long pipe: 20 ft. @ Tk. 1,072.00 per ft = | Tk. | 21,440.00 |
(b) | Fittings: |
|
|
280 mm HDPE Plain Tee/T-Y 0.25 no @ Tk. 5,465.00 each = | Tk. | 1,366.25 | |
280 mm HDPE Plain Bend 0.5 no @ Tk. 3,960.00 each = | Tk. | 1,980.00 | |
(c) | Jointing & fixing Materials |
|
|
| Butt fusion welding joint 1 Tk. 350.00 each = | Tk. | 350.00 |
(d) | Excavation (underground) 87.5 cft @ Tk. 2,958.33 per % cft = | Tk. | 2,588.54 |
(e) | Bedding by sand (FM 0.8) (underground) 52.5 cft @ Tk. 1,400.00 per % cft = | Tk. | 735.00 |
(d) | Labour: |
|
|
Plumber 0.5 no @ Tk. 600.00 per day = | Tk. | 300.00 | |
Skilled labour 1 no @ Tk. 390.00 per day = | Tk. | 390.00 | |
Ordinary labour 1 no @ Tk. 320.00 per day = | Tk. | 320.00 | |
| Sub - Total = | Tk. | 29,469.79 |
| Profit 10.00% = | Tk. | 2,946.98 |
| Overhead 3.50% = | Tk. | 1,031.44 |
| Total = | Tk. | 33,448.21 |
| Add VAT with adjustment factor 1.06383 6.00% = | Tk. | 2,134.99 |
| Grand Total = | Tk. | 35,583.20 |
| Rate per ft = | Tk. | 1,779.16 |
| Rate per m = | Tk. | 5,837.42 |
| Say, Tk. 5,837 .00 per meter |
|
|
26.32.1.6 | Supplying, laying, fitting , fixing 315 mm/13" outer diameter PE-100, PN-6 , HDPE Soil, Waste & Ventilation Pipe |
|
|
| Considering 20 ft. long HDPE one pipe |
|
|
(a) | 315 mm dia 20'-0" long pipe: 20 ft. @ Tk. 1,367.00 per ft = | Tk. | 27,340.00 |
(b) | Fittings: |
|
|
315 mm HDPE Plain Tee/T-Y 0.25 no @ Tk. 7,320.00 each = | Tk. | 1,830.00 | |
315 mm HDPE Plain Bend 0.5 no @ Tk. 5,402.00 each = | Tk. | 2,701.00 | |
(c) | Jointing & fixing Materials |
|
|
| Butt fusion welding joint 1 Tk. 350.00 each = | Tk. | 350.00 |
(d) | Excavation (underground) 87.5 cft @ Tk. 2,958.33 per % cft = | Tk. | 2,588.54 |
(e) | Bedding by sand (FM 0.8) (underground) 52.5 cft @ Tk. 1,400.00 per % cft = | Tk. | 735.00 |
(d) | Labour: |
|
|
Plumber 0.5 no @ Tk. 600.00 per day = | Tk. | 300.00 | |
Skilled labour 1 no @ Tk. 390.00 per day = | Tk. | 390.00 | |
Ordinary labour 1 no @ Tk. 320.00 per day = | Tk. | 320.00 | |
| Sub - Total = | Tk. | 36,554.54 |
| Profit 10.00% = | Tk. | 3,655.45 |
| Overhead 3.50% = | Tk. | 1,279.41 |
| Total = | Tk. | 41,489.40 |
| Add VAT with adjustment factor 1.06383 6.00% = | Tk. | 2,648.26 |
| Grand Total = | Tk. | 44,137.66 |
| Rate per ft = | Tk. | 2,206.88 |
| Rate per m = | Tk. | 7,240.77 |
| Say, Tk. 7,241 .00 per meter |
|
|
26.32.1.7 | Supplying, laying, fitting , fixing 400 mm/16" outer diameter PE-100, PN-6 , HDPE Soil, Waste & Ventilation Pipe |
|
|
| Considering 20 ft. long HDPE one pipe |
|
|
(a) | 400 mm dia 20'-0" long pipe: 20 ft. @ Tk. 2,190.00 per ft = | Tk. | 43,800.00 |