(iii) Ordinary labour 3 nos @ Tk. 320.00 per day = Tk. 960.00 |
Sub - Total = Tk. 178,787.87 Profit 10.00% = Tk. 17,878.79 Overhead 3.50% = Tk. 6,257.58 |
Total = Tk. 202,924.24 Add VAT with adjustment factor 1.06383 6.00% = Tk. 12,952.61 |
Grand Total = Tk. 215,876.85 Rate per ft = Tk. 10,793.84 Rate per m = Tk. 35,414.59 |
Say, Tk. 35,415 .00 per meter |
26.32.1.10 Supplying, laying, fitting , fixing 900 mm/38" outer diameter PE-100, PN-6 , HDPE Soil, Waste & Ventilation Pipe |
Considering 20 ft. long HDPE one pipe (a) 900 mm dia 20'-0" long pipe: 20 ft. @ Tk. 11,110.00 per ft = Tk. 222,200.00 (b) Fittings:
(c) Jointing & fixing Materials Butt fusion welding joint 1 Tk. 600.00 each = Tk. 600.00 (d) Excavation (underground) 112.5 cft @ Tk. 2,958.33 per % cft = Tk. 3,328.12 (e) Bedding by sand (FM 0.8) (underground) 77.5 cft @ Tk. 1,400.00 per % cft = Tk. 1,085.00 (d) Labour:
|
Sub - Total = Tk. 286,804.12 Profit 10.00% = Tk. 28,680.41 Overhead 3.50% = Tk. 10,038.14 |
Total = Tk. 325,522.67 Add VAT with adjustment factor 1.06383 6.00% = Tk. 20,778.05 |
Grand Total = Tk. 346,300.72 Rate per ft = Tk. 17,315.04 Rate per m = Tk. 56,810.65 |
Say, Tk. 56,811 .00 per meter |
26.32.2 [ For in House System ] 26.32.2.1 Supplying, laying, fitting , fixing 110 mm/4" outside diameter PE-100, PN-6 , SDR 26 HDPE Soil, Waste & Ventilation Pipe |
Considering 20 ft. long HDPE one pipe (a) 110 mm dia 20'-0" long pipe: 20 ft. @ Tk. 167.00 per ft = Tk. 3,340.00 (b) Fittings:
(c) Jointing & fixing Materials Electro fusion welding joint 1.0 no @ Tk. 350.00 each = Tk. 350.00 (d) Labour:
|
Sub - Total = Tk. 7,723.60 Profit 10.00% = Tk. 772.36 Overhead 3.50% = Tk. 270.33 |
Total = Tk. 8,766.29 Add VAT with adjustment factor 1.06383 6.00% = Tk. 559.55 |
Grand Total = Tk. 9,325.84 Rate per Foot = Tk. 466.29 Rate per m = Tk. 1,529.90 |
Say, Tk. 1,530 .00 per meter |