Add VAT with adjustment factor |
| 1.06383 | Total 6.00% | = = | Tk. Tk. | 3,933.24 251.06 |
Grand Total Rate per rm | = = | Tk. Tk. | 4,184.30 4,184.30 | |||
Say, | Tk. | 4,184 | .00 per meter |
| ||
|
|
|
|
|
|
|
Item No.- 27.71.6 |
|
|
|
|
|
|
Supplying 200 mm dia 6 mm thick M.S. housing pipe (Seamless) |
|
|
|
|
|
|
Considering 1 meter
thick M.S. housing pipe 1 meter @ | Tk. | 3,637.63 | per meter | = | Tk. | 3,637.63 |
|
|
| LS | = | Tk. | 160.00 |
|
|
| Sub - Total | = | Tk. | 3,797.63 |
|
| Profit | 10.00% | = | Tk. | 379.76 |
|
| Overhead | 3.50% | = | Tk. | 132.92 |
|
|
| Total | = | Tk. | 4,310.31 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 275.13 |
|
|
| Grand Total | = | Tk. | 4,585.44 |
|
|
| Rate per rm | = | Tk. | 4,585.44 |
Say, | Tk. | 4,585 | .00 per meter |
|
|
|
Item No.- 27.71.7 |
|
|
|
|
|
|
Supplying centralizer made with 12 mm dia M.S. rod of approved design |
|
|
|
|
|
|
Considering 1 No.
|
|
|
|
|
|
|
10 mm dia M.S. rod |
|
|
|
|
|
|
4 x 3'-0"=12'-0" 4.512 Ibs @ | Tk. | 27.44 | per meter | = | Tk. | 123.81 |
|
|
| LS | = | Tk. | 64.00 |
|
|
| Sub - Total | = | Tk. | 187.81 |
|
| Profit | 10.00% | = | Tk. | 18.78 |
|
| Overhead | 3.50% | = | Tk. | 6.57 |
|
|
| Total | = | Tk. | 213.16 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 13.61 |
|
|
| Grand Total | = | Tk. | 226.77 |
|
|
| Rate each. | = | Tk. | 226.77 |
Say, | Tk. | 227 .00 each |
|
|
| |
|
|
|
|
|
|
|
Item No.- 27.71.8 |
|
|
|
|
|
|
Supplying 200 mm dia M.S. cap of 6 mm thick. |
|
|
|
|
|
|
Considering 1 No.
| Tk. | 1,421.27 | each | = | Tk. | 1,421.27 |
|
|
| LS | = | Tk. | 500.00 |
|
|
| Sub - Total | = | Tk. | 1,921.27 |
|
| Profit | 10.00% | = | Tk. | 192.13 |
|
| Overhead | 3.50% | = | Tk. | 67.24 |
|
|
| Total | = | Tk. | 2,180.64 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 139.19 |
|
|
| Grand Total | = | Tk. | 2,319.83 |
|
|
| Rate each. | = | Tk. | 2,319.83 |
Say, | Tk. | 2,320 .00 each |
|
|
| |
|
|
|
|
|
|
|
Item No.- 27.72 |
|
|
|
|
|
|
Complete installation of tube well fixtures |
|
|
|
|
|
|
Considering 107 meter of 1 No. tube-well: |
|
|
|
|
|
|
pipe in/c coverage of risk 107 meter @ | Tk. | 128.00 | LS per meter | = = | Tk. Tk. | 2,133.33 13,696.00 |
| Tk. | 1,920.00 | Per time | = | Tk. | 3,840.00 |