Prev Next
īģŋ

Analysis of PWD SoR 2018 for Civil Works 621

 

 

 

 

Item No.- 27.76

 

 

 

 

Filling the bore hole around the well from top to the shrouding to G.L. as per specification Considering 100 meter

 

 

 

 

  1. Foreman 1 no @ Tk. 800.00

each

=

Tk.

800.00

  1. Skilled labour 6 nos @ Tk. 390.00

each

=

Tk.

2,340.00

  1. Local carriage, T & P

LS

=

Tk.

400.00

 

Sub - Total

=

Tk.

3,540.00

Profit

10.00%

=

Tk.

354.00

Overhead

3.50%

=

Tk.

123.90

 

Total

=

Tk.

4,017.90

Add VAT with adjustment factor 1.06383

6.00%

=

Tk.

256.46

 

Grand Total

=

Tk.

4,274.36

 

Rate per rm

=

Tk.

42.74

Say, Tk. 43

.00 per meter

 

 

 

 

 

 

 

 

ANALYSIS FOR INSTALLATION OF 40 MM DIA P.V.C. HAND TUBE WEL

 

 

 

 

 

 

 

 

 

Item No.- 27.77.1

 

 

 

 

Supplying, fitting & fixing 40 mm dia "D" uPVC pipe having wall thickness 2.5 mm to 3.00 mm including sinking

 

 

 

 

Up to 60 m depth

 

 

 

 

Considering 1 rft

  1. 40 mm dia uPVC pipe 1 rft @ Tk. 35.12

per rft

=

Tk.

14.00

  1. Labour for sinking and other costs

LS

=

Tk.

32.00

 

Sub - Total

=

Tk.

46.00

Profit

10.00%

=

Tk.

4.60

Overhead

3.50%

=

Tk.

1.61

 

Total

=

Tk.

52.21

Add VAT with adjustment factor 1.06383

6.00%

=

Tk.

3.33

 

Grand Total

=

Tk.

55.54

 

Rate per rm

=

Tk.

182.23

Say, Tk. 182

.00 per meter

 

 

 

 

 

 

 

 

Item No.- 27.77.2

 

 

 

 

Beyond 60 m depth

 

 

 

 

Considering 1 rft

  1. Cost of 40 mm dia uPVC pipe 1 rft @ Tk. 35.12

per rft

=

Tk.

35.12

  1. Labour cost for sinking and other costs

LS

=

Tk.

48.00

 

Sub - Total

=

Tk.

83.12

Profit

10.00%

=

Tk.

8.31

Overhead

3.50%

=

Tk.

2.91

 

Total

=

Tk.

94.34

Add VAT with adjustment factor 1.06383

6.00%

=

Tk.

6.02

 

Grand Total

=

Tk.

100.36

 

Rate per rm

=

Tk.

329.28

Say, Tk. 329

.00 per meter

 

 

 

 

 

 

 

 

Item No.- 27.78

 

 

 

 

Supplying and sinking Five Star / equivalent brand PVC strainer 3 m long

 

 

 

 

Considering 3 m long 1 No. strainer

  1. Cost of 40 mm dia strainer 1 no @ Tk. 314.39
  2. Labour cost for sinking and other costs

each
LS

=

=

Tk. Tk.

314.39

100.00

 

Sub - Total

=

Tk.

414.39

Profit

10.00%

=

Tk.

41.44