Item No.- 28.9.2 |
|
|
|
|
Supplying & fitting-fixing 25 mm N.D. ball valve Ball class 150 R.F. 1" dia. Considering 1 No.
class 150 R.F. 1 no @ Tk. 5,221.92 | each | = | Tk. | 5,221.92 |
| each | = | Tk. | 771.66 |
| each | = | Tk. | 91.24 |
| each | = | Tk. | 270.00 |
| LS | = | Tk. | 3,200.00 |
| Sub - Total | = | Tk. | 9,554.82 |
Incidental charges | 10.00% | = | Tk. | 955.48 |
Profit | 10.00% | = | Tk. | 955.48 |
Overhead | 3.50% | = | Tk. | 33.44 |
| Total | = | Tk. | 11,499.22 |
Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 733.99 |
| Grand Total | = | Tk. | 12,233.21 |
Say, Tk. 12,233 .00 each |
|
|
| |
|
|
|
|
|
Item No.- 28.10 |
|
|
|
|
Cutting and permanent re-installment of pucca road (rigid & flexible) |
|
|
|
|
28.10.1 Bitumenous road: |
|
|
|
|
Considering 100 sft (I) Cutting & permanent re-installment of road | LS | = | Tk. | 5,488.00 |
Incidental charges | 10.00% | = | Tk. | 548.80 |
Profit | 10.00% | = | Tk. | 548.80 |
Overhead | 3.50% | = | Tk. | 19.21 |
| Total | = | Tk. | 6,604.81 |
Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 421.58 |
| Grand Total | = | Tk. | 7,026.39 |
| Rate per sft | = | Tk. | 70.26 |
| Rate per sqm | = | Tk. | 756.28 |
Say, Tk. 756 .00 per sqm |
|
|
| |
28.10.2 R.C.C. Road: |
|
|
|
|
Considering 100 sft (i) Cutting & permanent re-installment of road | LS | = | Tk. | 8,208.00 |
Incidental charges | 10.00% | = | Tk. | 820.80 |
Profit | 10.00% | = | Tk. | 820.80 |
Overhead | 3.50% | = | Tk. | 28.73 |
| Total | = | Tk. | 9,878.33 |
Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 630.53 |
| Grand Total | = | Tk. | 10,508.86 |
| Rate per sft | = | Tk. | 105.09 |
| Rate per sqm | = | Tk. | 1,131.19 |
Say, Tk. 1,131 .00 per sqm |
|
|
| |
Part - B (Domestic & Commercial line) |
|
|
|
|
Item No.- 28.11.1 |
|
|
|
|
Installation of commercial and domestic house line |
|
|
|
|
3/4" dia G.I. pipe line |
|
|
|
|
Considering 1 rft of work
| per rft | = | Tk. | 41.70 |
| LS | = | Tk. | 6.36 |
| LS | = | Tk. | 10.40 |
| Sub - Total | = | Tk. | 58.46 |
Incidental charges | 10.00% | = | Tk. | 5.85 |
Profit | 10.00% | = | Tk. | 5.85 |
Overhead | 3.50% | = | Tk. | 0.20 |