Item No.- 28.9.2

 

 

 

 

Supplying & fitting-fixing 25 mm N.D. ball valve Ball class 150 R.F. 1" dia. Considering 1 No.

  1. 25 mm ND dia ball valve

class 150 R.F. 1 no @ Tk. 5,221.92

each

=

Tk.

5,221.92

  1. 25 mm dia flange W/N 150 R.F. 2 nos @ Tk. 385.83

each

=

Tk.

771.66

  1. 25 mm dia gaskit (asbestos) 2 nos @ Tk. 45.62

each

=

Tk.

91.24

  1. 1/2" x 2.5" nut-bolt 8 nos @ Tk. 33.75

each

=

Tk.

270.00

  1. Labour for fitting-fixing, necessary welding in/c transportation

LS

=

Tk.

3,200.00

 

Sub - Total

=

Tk.

9,554.82

Incidental charges

10.00%

=

Tk.

955.48

Profit

10.00%

=

Tk.

955.48

Overhead

3.50%

=

Tk.

33.44

 

Total

=

Tk.

11,499.22

Add VAT with adjustment factor 1.06383

6.00%

=

Tk.

733.99

 

Grand Total

=

Tk.

12,233.21

Say, Tk. 12,233 .00 each

 

 

 

 

 

 

 

 

Item No.- 28.10

 

 

 

 

Cutting and permanent re-installment of pucca road (rigid & flexible)

 

 

 

 

28.10.1 Bitumenous road:

 

 

 

 

Considering 100 sft

(I) Cutting & permanent re-installment of road

LS

=

Tk.

5,488.00

Incidental charges

10.00%

=

Tk.

548.80

Profit

10.00%

=

Tk.

548.80

Overhead

3.50%

=

Tk.

19.21

 

Total

=

Tk.

6,604.81

Add VAT with adjustment factor 1.06383

6.00%

=

Tk.

421.58

 

Grand Total

=

Tk.

7,026.39

 

Rate per sft

=

Tk.

70.26

 

Rate per sqm

=

Tk.

756.28

Say, Tk. 756 .00 per sqm

 

 

 

28.10.2 R.C.C. Road:

 

 

 

 

Considering 100 sft

(i) Cutting & permanent re-installment of road

LS

=

Tk.

8,208.00

Incidental charges

10.00%

=

Tk.

820.80

Profit

10.00%

=

Tk.

820.80

Overhead

3.50%

=

Tk.

28.73

 

Total

=

Tk.

9,878.33

Add VAT with adjustment factor 1.06383

6.00%

=

Tk.

630.53

 

Grand Total

=

Tk.

10,508.86

 

Rate per sft

=

Tk.

105.09

 

Rate per sqm

=

Tk.

1,131.19

Say, Tk. 1,131 .00 per sqm

 

 

 

Part - B (Domestic & Commercial line)

 

 

 

 

Item No.- 28.11.1

 

 

 

 

Installation of commercial and domestic house line

 

 

 

 

3/4" dia G.I. pipe line

 

 

 

 

Considering 1 rft of work

  1. G.I. pipe 1 rft @ Tk. 41.70

per rft

=

Tk.

41.70

  1. Fittings

LS

=

Tk.

6.36

  1. Labour:

LS

=

Tk.

10.40

 

Sub - Total

=

Tk.

58.46

Incidental charges

10.00%

=

Tk.

5.85

Profit

10.00%

=

Tk.

5.85

Overhead

3.50%

=

Tk.

0.20