| = = | Tk. Tk. | 160.00 160.00 |
SubTotal Contractor's profit 10% Overhead expenses 3.50% | = = = | Tk. | 1,123.40 112.34 39.32 |
Total | = | Tk. | 1,275.06 |
VAT with adjustment factor 1.06383 6.00% | = | Tk. | 81.39 |
Grand Total | = | Tk. | 1,356.45 |
Rate per meter | = | Tk. | 452.15 |
Say, Tk. 452 .00 per meter |
|
|
|
|
|
|
|
Item No. 32.10 |
|
|
|
Taking out and relaying old brick soling including replacement of 10% brick |
|
|
|
[Cost of fine sand required for attaining level to be paid by P.W.D. SoR 2018 Item No. 2.10.1 |
|
|
|
Considering 10 sqm of work
| = | Tk. | 125.00 |
| = | Tk. | 320.00 |
| = | Tk. | 44.45 |
| = | Tk. | 261.00 |
| = | Tk. | 96.00 |
| = | Tk. | 32.00 |
SubTotal | = | Tk. | 878.45 |
Contractor's profit 10% | = | Tk. | 87.85 |
Overhead expenses 3.50% | = | Tk. | 30.75 |
Total | = | Tk. | 997.05 |
VAT with adjustment factor 1.06383 6.00% | = | Tk. | 63.64 |
Grand Total | = | Tk. | 1,060.69 |
Rate per sqm | = | Tk. | 106.07 |
Say, Tk. 106 .00 per sqm |
|
|
|
|
|
|
|
Item No. 32.11 |
|
|
|
Taking out and relaying brick soling after redressing the surfaces |
|
|
|
[Cost of fine sand required for attaining level to be paid by P.W.D. SoR 2018 Item No. 2.10.1 |
|
|
|
Considering 10 sqm of work
| = | Tk. | 100.00 |
| = | Tk. | 320.00 |
| = | Tk. | 15.88 |
| = | Tk. | 96.00 |
| = | Tk. | 32.00 |
SubTotal | = | Tk. | 563.88 |
Contractor's profit 10% | = | Tk. | 56.39 |
Overhead expenses 3.50% | = | Tk. | 19.74 |
Total | = | Tk. | 640.01 |
VAT with adjustment factor 1.06383 6.00% | = | Tk. | 40.85 |
Grand Total | = | Tk. | 680.86 |
Rate per sqm | = | Tk. | 68.09 |
Say, Tk. 68 .00 per sqm |
|
|
|
|
|
|
|
Item No. 32.12.1 |
|
|
|
Taking out old brick on edge pavement and resetting (Herring bone bond) including replacement of 10% brick |
|
|
|
[Cost of fine sand required for attaining level to be paid by P.W.D. SoR 2018 Item No. 2.10.1 |
|
|
|
Considering 10 sqm of work |
|
|
|