VAT with adjustment factor | Contractor's profit 10% = Overhead expenses 3.50% = | Tk. Tk. | 17.92 6.27 |
Total = 1.06383 6.00% = | Tk. Tk. | 203.39 12.98 | |
Grand Total = Rate per meter = | Tk. Tk. | 216.37 7.21 | |
Say, | Tk. 7 .00 per meter |
|
|
|
|
|
|
Item No. 32.66 |
|
|
|
Labour charge for refitting barbed wire fencing |
|
|
|
Considering 30 m work
| Tk. 390.00 each = | Tk. | 292.50 |
| LS = | Tk. | 112.00 |
| SubTotal | Tk. | 404.50 |
| Contractor's profit 10% = | Tk. | 40.45 |
| Overhead expenses 3.50% = | Tk. | 14.16 |
| Total = | Tk. | 459.11 |
VAT with adjustment factor | 1.06383 6.00% = | Tk. | 29.30 |
| Grand Total = | Tk. | 488.41 |
| Rate per meter = | Tk. | 16.28 |
Say, | Tk. 16 .00 per meter |
|
|
|
|
|
|
Item No. 32.67 |
|
|
|
Labour charge for tightening of old loose barbed wire fencing |
|
|
|
Considering 30 m work
| Tk. 390.00 each = | Tk. | 39.00 |
| LS = | Tk. | 19.20 |
| SubTotal | Tk. | 58.20 |
| Contractor's profit 10% = | Tk. | 5.82 |
| Overhead expenses 3.50% = | Tk. | 2.04 |
| Total = | Tk. | 66.06 |
VAT with adjustment factor | 1.06383 6.00% = | Tk. | 4.22 |
| Grand Total = | Tk. | 70.28 |
| Rate per meter = | Tk. | 2.34 |
Say, | Tk. 2 .00 per meter |
|
|
|
|
|
|
Item No. 32.68 |
|
|
|
Renewing, supplying and fitting-fixing 300 mm long F.I. Clamp in CC (1:2:4) |
|
|
|
Considering 1 No. clamp
| Tk. 22.00 each = | Tk. | 22.00 |
| Tk. 6,267.01 per cum = | Tk. | 35.10 |
| LS = | Tk. | 22.40 |
| SubTotal = | Tk. | 79.50 |
| Contractor's profit 10% = | Tk. | 7.95 |
| Overhead expenses 3.50% = | Tk. | 2.78 |
| Total = | Tk. | 90.23 |
VAT with adjustment factor | 1.06383 6.00% = | Tk. | 5.76 |
| Grand Total = | Tk. | 95.99 |
| Rate per No. = | Tk. | 95.99 |
Say, | Tk. 96 .00 each |
|
|
|
|
|
|
Item No. 32.69 |
|
|
|
Replacing, supplying and fitting-fixing 150 mm long F.I. Clamp in CC (1:2:4) |
|
|
|
Considering 1 No. clamp
| Tk. 12.00 each = | Tk. | 12.00 |
| Tk. 6,267.01 per cum = | Tk. | 17.55 |