Item No. 32.76.8

 

 

 

 

Supplying timber (unfinished) for repairing in wood works: Chapalish Considering 1 cft unfinished wood (Chapalish)

 

 

 

 

Cost of unfinished wood 1.00 cft @ Tk. 2,390.00

per cft

=

Tk.

2,390.00

Contractor's profit

10%

=

Tk.

239.00

Overhead expenses

3.50%

=

Tk.

83.65

 

Total

=

Tk.

2,712.65

VAT with adjustment factor 1.06383

6.00%

=

Tk.

173.15

 

Grand Total

=

Tk.

2,885.80

 

Rate per cum

=

Tk.

101,912.03

Say, Tk. 101,912 .00 cum

 

 

 

 

 

 

 

 

Item No. 32.76.9

 

 

 

 

Supplying timber (unfinished) for repairing in wood works: Loha/Pyiankado

 

 

 

 

Considering 1 cft unfinished wood (Loha/Pyiankado)

 

 

 

 

Cost of unfinished wood 1.00 cft @ Tk. 2,600.00

per cft

=

Tk.

2,600.00

Contractor's profit

10%

=

Tk.

260.00

Overhead expenses

3.50%

=

Tk.

91.00

 

Total

=

Tk.

2,951.00

VAT with adjustment factor 1.06383

6.00%

=

Tk.

188.36

 

Grand Total

=

Tk.

3,139.36

 

Rate per cum

=

Tk.

110,866.50

Say, Tk. 110,867 .00 cum

 

 

 

 

 

 

 

 

Item No. 32.76.10

 

 

 

 

Supplying timber (unfinished) for repairing in wood works: Burma teak

 

 

 

 

Considering 1 cft unfinished wood (Burma teak)

 

 

 

 

Cost of unfinished wood 1.00 cft @ Tk. 6,500.00

per cft

=

Tk.

6,500.00

Contractor's profit

10%

=

Tk.

650.00

Overhead expenses

3.50%

=

Tk.

227.50

 

Total

=

Tk.

7,377.50

VAT with adjustment factor 1.06383

6.00%

=

Tk.

470.90

 

Grand Total

=

Tk.

7,848.40

 

Rate per cum

=

Tk.

277,166.25

Say, Tk. 277,166 .00 cum

 

 

 

 

 

 

 

 

Item No. 32.76.11

 

 

 

 

Supplying timber (unfinished) for repairing in wood works: Ordinary timber

 

 

 

 

Considering 1 cft unfinished wood Ordinary timber (Mehgani)

 

 

 

 

Cost of unfinished wood 1.00 cft @ Tk. 1,800.00

per cft

=

Tk.

1,800.00

Contractor's profit

10%

=

Tk.

180.00

Overhead expenses

3.50%

=

Tk.

63.00

 

Total

=

Tk.

2,043.00

VAT with adjustment factor 1.06383

6.00%

=

Tk.

130.40

 

Grand Total

=

Tk.

2,173.40

 

Rate per cum

=

Tk.

76,753.62

Say, Tk. 76,754 .00 cum

 

 

 

 

 

 

 

 

Item No. 32.77

 

 

 

 

Cleaning, washing, brooming, taking away from work place and stacking of debris from all heights at a place beyond plinth area of the the site during execution of repair works as per direction of the engineer-in-charge

 

 

 

 

Considering 1 cum debris