Item No. 32.76.8 |
|
|
|
|
Supplying timber (unfinished) for repairing in wood works: Chapalish Considering 1 cft unfinished wood (Chapalish) |
|
|
|
|
Cost of unfinished wood 1.00 cft @ Tk. 2,390.00 | per cft | = | Tk. | 2,390.00 |
Contractor's profit | 10% | = | Tk. | 239.00 |
Overhead expenses | 3.50% | = | Tk. | 83.65 |
| Total | = | Tk. | 2,712.65 |
VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 173.15 |
| Grand Total | = | Tk. | 2,885.80 |
| Rate per cum | = | Tk. | 101,912.03 |
Say, Tk. 101,912 .00 cum |
|
|
| |
|
|
|
|
|
Item No. 32.76.9 |
|
|
|
|
Supplying timber (unfinished) for repairing in wood works: Loha/Pyiankado |
|
|
|
|
Considering 1 cft unfinished wood (Loha/Pyiankado) |
|
|
|
|
Cost of unfinished wood 1.00 cft @ Tk. 2,600.00 | per cft | = | Tk. | 2,600.00 |
Contractor's profit | 10% | = | Tk. | 260.00 |
Overhead expenses | 3.50% | = | Tk. | 91.00 |
| Total | = | Tk. | 2,951.00 |
VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 188.36 |
| Grand Total | = | Tk. | 3,139.36 |
| Rate per cum | = | Tk. | 110,866.50 |
Say, Tk. 110,867 .00 cum |
|
|
| |
|
|
|
|
|
Item No. 32.76.10 |
|
|
|
|
Supplying timber (unfinished) for repairing in wood works: Burma teak |
|
|
|
|
Considering 1 cft unfinished wood (Burma teak) |
|
|
|
|
Cost of unfinished wood 1.00 cft @ Tk. 6,500.00 | per cft | = | Tk. | 6,500.00 |
Contractor's profit | 10% | = | Tk. | 650.00 |
Overhead expenses | 3.50% | = | Tk. | 227.50 |
| Total | = | Tk. | 7,377.50 |
VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 470.90 |
| Grand Total | = | Tk. | 7,848.40 |
| Rate per cum | = | Tk. | 277,166.25 |
Say, Tk. 277,166 .00 cum |
|
|
| |
|
|
|
|
|
Item No. 32.76.11 |
|
|
|
|
Supplying timber (unfinished) for repairing in wood works: Ordinary timber |
|
|
|
|
Considering 1 cft unfinished wood Ordinary timber (Mehgani) |
|
|
|
|
Cost of unfinished wood 1.00 cft @ Tk. 1,800.00 | per cft | = | Tk. | 1,800.00 |
Contractor's profit | 10% | = | Tk. | 180.00 |
Overhead expenses | 3.50% | = | Tk. | 63.00 |
| Total | = | Tk. | 2,043.00 |
VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 130.40 |
| Grand Total | = | Tk. | 2,173.40 |
| Rate per cum | = | Tk. | 76,753.62 |
Say, Tk. 76,754 .00 cum |
|
|
| |
|
|
|
|
|
Item No. 32.77 |
|
|
|
|
Cleaning, washing, brooming, taking away from work place and stacking of debris from all heights at a place beyond plinth area of the the site during execution of repair works as per direction of the engineer-in-charge |
|
|
|
|
Considering 1 cum debris |
|
|
|
|