SL | Items | Rate | Unit |
1 | MARK-UPS |
|
|
1 | Contractor's Profit | 10.00% |
|
2 | Contractor's Overhead Expenses | 3.50% |
|
3 | VAT | 6.00% |
|
4 | Additional Incidental Expenses for Gas Line Installation Works | 10.00% |
|
C1 | LABOUR & MAN-POWER: PER DAY |
|
|
1 | Head mason / Mosaic head mistry | Tk. 600.00 | per day |
2 | Mason | Tk. 500.00 | per day |
3 | Skilled labour | Tk. 390.00 | per day |
4 | Ordinary labour | Tk. 320.00 | per day |
5 | Field Engineer (minimum BSc in Eng. with 3yrs exp or Diploma in Eng. with 8yrs exp) | Tk. 1,800.00 | per day |
6 | Skilled technician | Tk. 1,000.00 | per day |
7 | Semi skilled technician | Tk. 600.00 | per day |
8 | Foreman/Supervisor | Tk. 800.00 | per day |
9 | Electrician | Tk. 600.00 | per day |
10 | Assistant Electrician | Tk. 500.00 | per day |
11 | Rod binder | Tk. 500.00 | per day |
12 | Mosaic mistry | Tk. 500.00 | per day |
13 | Plumber | Tk. 600.00 | per day |
14 | Painter | Tk. 600.00 | per day |
15 | Carpenter | Tk. 600.00 | per day |
16 | Welder | Tk. 600.00 | per day |
17 | Polish mistry | Tk. 600.00 | per day |
18 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator | Tk. 390.00 | per day |
19 | Machine operator | Tk. 600.00 | per day |
20 | Pile rig operator | Tk. 600.00 | per day |
21 | Diesel hammer mounted rig operator | Tk. 800.00 | per day |