Brick work with first class bricks in superstructure (1:6) ( 100 cft )
Material | quantity | Unit | Rate | Amount |
Scaffolding |
25.00 |
sft |
|
0.00 |
Ordinary Labour |
2.25 |
person |
638.00 |
1,435.50 |
Bricks |
1,100.00 |
Nos |
14.17 |
15,587.00 |
Sand 1.2 FM |
36.00 |
cft |
53.55 |
1,927.80 |
Cement |
4.00 |
bag |
603.75 |
2,415.00 |
Head Masson (Civil) |
0.10 |
person |
920.00 |
92.00 |
Skill Masson (Civil) |
1.00 |
person |
787.50 |
787.50 |
Skill Labour (civil) |
2.50 |
person |
660.00 |
1,650.00 |
Total amount |
23,894.80 |