125 mm brick work with first class bricks (1:6) in superstructure ( 100 sft )
MaterialquantityUnitRateAmount
Bricks 480.00 Nos 14.17 6,801.60
Sand 1.2 FM 18.00 cft 53.55 963.90
Cement 1.75 bag 603.75 1,056.56
Head Masson (Civil) 0.10 person 920.00 92.00
Skill Masson (Civil) 0.75 person 787.50 590.63
Ordinary Labour 3.00 person 638.00 1,914.00
Skill Labour (civil) 0.50 person 660.00 330.00
Scaffolding 25.00 sft 0.00
Total amount 11,748.69