125 mm brick work with 10 hole machine made ceramic bricks (1:4) in superstructure ( 100 sft )
Material | quantity | Unit | Rate | Amount |
Bricks |
480.00 |
Nos |
14.17 |
6,801.60 |
Sand 1.2 FM |
18.00 |
cft |
53.55 |
963.90 |
Cement |
2.80 |
bag |
603.75 |
1,690.50 |
Head Masson (Civil) |
0.10 |
person |
920.00 |
92.00 |
Masson (Civil) |
1.00 |
person |
770.00 |
770.00 |
Ordinary Labour |
1.00 |
person |
638.00 |
638.00 |
Unskilled Labour |
2.00 |
person |
472.50 |
945.00 |
Skill Labour (civil) |
0.50 |
person |
660.00 |
330.00 |
Scaffolding |
25.00 |
sft |
|
0.00 |
Miscellaneous (taka) |
300.00 |
LS |
1.14 |
342.00 |
Total amount |
12,573.00 |