Concrete (1:3:6) work using BRICK CHIPS and sand of F.M. 1.2 ( 100 cft )
MaterialquantityUnitRateAmount
Bricks 765.00 Nos 14.17 10,840.05
Breaking chips including screening 90.00 cft 0.00
Sand 1.2 FM 45.00 cft 53.55 2,409.75
Cement 13.00 bag 603.75 7,848.75
Miscellaneous (taka) 1,000.00 LS 1.14 1,140.00
Total amount 22,238.55