Earth work in foundation trenches up to 1.5 m depth and maximum 10 m lead including protecting and maintaining the trench: Very stiff (hard) claye soil / rubbish ( 100 cft )
Material
quantity
Unit
Rate
Amount
Masson (Civil)
0.10
person
770.00
77.00
Ordinary Labour
1.00
person
638.00
638.00
Skill Labour (civil)
0.25
person
660.00
165.00
Miscellaneous (taka)
20.00
LS
1.14
22.80
Total amount
902.80