Profit Overhead | per day | = = | Tk. Tk. | 975.00 133.33 |
Sub - Total 10.00% 3.50% | = = = | Tk. | 4,433.33 443.33 155.17 | |
Total | = | Tk. | 5,031.83 | |
Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 321.18 |
| Grand Total | = | Tk. | 5,353.01 |
| Rate per cft | = | Tk. | 5.35 |
| Rate per cum | = | Tk. | 188.94 |
Say, Tk. 189 | .00 per cum |
|
|
|
|
|
|
|
|
Item No.- 02.1.5 |
|
|
|
|
Earth work in foundation trenches up to 1.5 m depth and maximum 10 m lead including protecting and maintaining the trench: very soft / saturated / organic claye soil/ soil of semi-liquid state |
|
|
|
|
Considering 1000 cft work
| per day | = | Tk. | 125.00 |
| per day | = | Tk. | 3,520.00 |
| per day | = | Tk. | 1,170.00 |
| LS | = | Tk. | 266.67 |
| Sub - Total | = | Tk. | 5,081.67 |
Profit | 10.00% | = | Tk. | 508.17 |
Overhead | 3.50% | = | Tk. | 177.86 |
| Total | = | Tk. | 5,767.70 |
Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 368.15 |
| Grand Total | = | Tk. | 6,135.85 |
| Rate per cft | = | Tk. | 6.14 |
| Rate per cum | = | Tk. | 216.83 |
Say, Tk. 217 | .00 per cum |
|
|
|
|
|
|
|
|
Item No.- 02.1.6 |
|
|
|
|
Extra rate for each additional 0.5 meter depth exceeding 1.5 meter |
|
|
|
|
Considering 1000 cft work 1. Ordinary labour 1.50 nos @ Tk. 320.00 | per day | = | Tk. | 480.00 |
| Sub - Total | = | Tk. | 480.00 |
Profit | 10.00% | = | Tk. | 48.00 |
Overhead | 3.50% | = | Tk. | 16.80 |
| Total | = | Tk. | 544.80 |
Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 34.77 |
| Grand Total | = | Tk. | 579.57 |
| Rate per cft | = | Tk. | 0.58 |
| Rate per cum | = | Tk. | 20.48 |
Say, Tk. 20 | .00 per cum |
|
|
|
|
|
|
|
|
Item No.- 02.1.7 |
|
|
|
|
Extra rate for each 1 m additional lead beyond 10 m |
|
|
|
|
Considering 1000 cft work 1. Ordinary labour 0.20 no @ Tk. 320.00 | per day | = | Tk. | 64.00 |
| Sub - Total | = | Tk. | 64.00 |
Profit | 10.00% | = | Tk. | 6.40 |
Overhead | 3.50% | = | Tk. | 2.24 |
| Total | = | Tk. | 72.64 |
Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 4.64 |
| Grand Total | = | Tk. | 77.28 |
| Rate per cft | = | Tk. | 0.08 |
| Rate per cum | = | Tk. | 2.83 |
Say, Tk. 3 | .00 per cum |
|
|
|