Item No.- 02.2

 

 

 

 

 

 

 

 

Bailing out water during earthwork in excavation for foundation Break-up for 4 hours use of pump in one day to discharge water

 

 

 

 

 

 

 

 

  1. Hire charge of pump 1.00

day

@

Tk.

600.00

per day

=

Tk.

600.00

  1. Fuel for 4 hours 3.00

litre

@

Tk.

68.00

per day

=

Tk.

204.00

  1. Pump operator 1.00

no

@

Tk.

600.00

per day

=

Tk.

600.00

 

 

 

 

 

Sub - Total

=

Tk.

1,404.00

 

 

 

 

Profit

10.00%

=

Tk.

140.40

 

 

 

 

Overhead

3.50%

=

Tk.

49.14

 

 

 

 

 

Total

=

Tk.

1,593.54

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

101.72

 

 

 

 

 

Grand Total

=

Tk.

1,695.26

 

 

 

 

 

Rate per hour

=

Tk.

423.82

 

 

Say,

Tk.

424

.00 per hour

 

 

 

 

 

 

 

 

 

 

 

 

Item No.- 02.3

 

 

 

 

 

 

 

 

Supplying and driving of borrack bamboo post minimum 3" dia

 

 

 

 

 

 

 

 

Consider 1 No. bamboo of 8 rft long

 

 

 

 

 

 

 

 

  1. Cost of bamboo min 3" dia 8

rft

@

Tk.

15.00

per rft

=

Tk.

120.00

  1. Driving cost

@ 4'-0" below G.L. 4

rft

@

Tk.

8.00

per rft

=

Tk.

32.00

  1. Local carriage and sundries

 

 

 

 

LS

=

Tk.

9.60

 

 

 

 

 

Sub - Total

=

Tk.

161.60

 

 

 

 

Profit

10.00%

=

Tk.

16.16

 

 

 

 

Overhead

3.50%

=

Tk.

5.66

 

 

 

 

 

Total

=

Tk.

183.42

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

11.71

 

 

 

 

 

Grand Total

=

Tk.

195.13

 

 

 

 

 

Rate per rft

=

Tk.

24.39

 

 

 

 

 

Rate per rm

=

Tk.

80.02

 

 

Say,

Tk.

80

.00 per meter

 

 

 

 

 

 

 

 

 

 

 

 

Item No.- 02.4

 

 

 

 

 

 

 

 

Supplying and driving wooden ballah in Palisading

 

 

 

 

 

 

 

 

Considering 20 rft of work

(a) Cost of ballah in/c carriage 20

(b) Labour for driving

  1. Skilled labour 1

rft
no

@

@

Tk. Tk.

70.00

390.00

per rft
per day

=

=

Tk. Tk.

1,400.00

390.00

  1. Ordinary labour 3

(c) Sundries, removing of skin, sizing and coaltaring in/c hire
charge of monkey with driving arranement.

nos

@

Tk.

320.00

per day
LS

=

=

Tk. Tk.

960.00

240.00

 

 

 

 

 

Sub - Total

=

Tk.

2,990.00

 

 

 

 

Profit

10.00%

=

Tk.

299.00

 

 

 

 

Overhead

3.50%

=

Tk.

104.65

 

 

 

 

 

Total

=

Tk.

3,393.65

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

216.62

 

 

 

 

 

Grand Total

=

Tk.

3,610.27

 

 

 

 

 

Rate per rft

=

Tk.

180.51

 

 

 

 

 

Rate per rm

=

Tk.

592.25

 

 

Say,

Tk.

592

.00 per meter

 

 

 

 

 

 

 

 

 

 

 

 

Item No.- 02.5

 

 

 

 

 

 

 

 

Palisading work with drum sheet excluding cost of vertical post

 

 

 

 

 

 

 

 

Considering 30'-0" x 5'-0"= 150 sft of work

 

 

 

 

 

 

 

 

  1. Half split borrak bamboo runner @ maximum 1'-6" c/c horizontally, minimum 4 nos

 

 

 

 

 

 

 

 

0.50 x 4.00 x 30.00= 60

rft

@

Tk.

15.00

per rft

=

Tk.

900.00

  1. Bitumen drum sheet: '@ 3.14 x 2 x 3

=18.84 sft per drum 12

nos

@

Tk.

200.00

each

=

Tk.

2,400.00