Item No.- 02.2 |
|
|
|
|
|
|
|
|
Bailing out water during earthwork in excavation for foundation Break-up for 4 hours use of pump in one day to discharge water |
|
|
|
|
|
|
|
|
| day | @ | Tk. | 600.00 | per day | = | Tk. | 600.00 |
| litre | @ | Tk. | 68.00 | per day | = | Tk. | 204.00 |
| no | @ | Tk. | 600.00 | per day | = | Tk. | 600.00 |
|
|
|
|
| Sub - Total | = | Tk. | 1,404.00 |
|
|
|
| Profit | 10.00% | = | Tk. | 140.40 |
|
|
|
| Overhead | 3.50% | = | Tk. | 49.14 |
|
|
|
|
| Total | = | Tk. | 1,593.54 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 101.72 | ||
|
|
|
|
| Grand Total | = | Tk. | 1,695.26 |
|
|
|
|
| Rate per hour | = | Tk. | 423.82 |
|
| Say, | Tk. | 424 | .00 per hour |
|
|
|
|
|
|
|
|
|
|
|
|
Item No.- 02.3 |
|
|
|
|
|
|
|
|
Supplying and driving of borrack bamboo post minimum 3" dia |
|
|
|
|
|
|
|
|
Consider 1 No. bamboo of 8 rft long |
|
|
|
|
|
|
|
|
| rft | @ | Tk. | 15.00 | per rft | = | Tk. | 120.00 |
@ 4'-0" below G.L. 4 | rft | @ | Tk. | 8.00 | per rft | = | Tk. | 32.00 |
|
|
|
|
| LS | = | Tk. | 9.60 |
|
|
|
|
| Sub - Total | = | Tk. | 161.60 |
|
|
|
| Profit | 10.00% | = | Tk. | 16.16 |
|
|
|
| Overhead | 3.50% | = | Tk. | 5.66 |
|
|
|
|
| Total | = | Tk. | 183.42 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 11.71 | ||
|
|
|
|
| Grand Total | = | Tk. | 195.13 |
|
|
|
|
| Rate per rft | = | Tk. | 24.39 |
|
|
|
|
| Rate per rm | = | Tk. | 80.02 |
|
| Say, | Tk. | 80 | .00 per meter |
|
|
|
|
|
|
|
|
|
|
|
|
Item No.- 02.4 |
|
|
|
|
|
|
|
|
Supplying and driving wooden ballah in Palisading |
|
|
|
|
|
|
|
|
Considering 20 rft of work (a) Cost of ballah in/c carriage 20 (b) Labour for driving
| rft | @ @ | Tk. Tk. | 70.00 390.00 | per rft | = = | Tk. Tk. | 1,400.00 390.00 |
(c) Sundries, removing of skin, sizing and coaltaring in/c hire | nos | @ | Tk. | 320.00 | per day | = = | Tk. Tk. | 960.00 240.00 |
|
|
|
|
| Sub - Total | = | Tk. | 2,990.00 |
|
|
|
| Profit | 10.00% | = | Tk. | 299.00 |
|
|
|
| Overhead | 3.50% | = | Tk. | 104.65 |
|
|
|
|
| Total | = | Tk. | 3,393.65 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 216.62 | ||
|
|
|
|
| Grand Total | = | Tk. | 3,610.27 |
|
|
|
|
| Rate per rft | = | Tk. | 180.51 |
|
|
|
|
| Rate per rm | = | Tk. | 592.25 |
|
| Say, | Tk. | 592 | .00 per meter |
|
|
|
|
|
|
|
|
|
|
|
|
Item No.- 02.5 |
|
|
|
|
|
|
|
|
Palisading work with drum sheet excluding cost of vertical post |
|
|
|
|
|
|
|
|
Considering 30'-0" x 5'-0"= 150 sft of work |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
0.50 x 4.00 x 30.00= 60 | rft | @ | Tk. | 15.00 | per rft | = | Tk. | 900.00 |
=18.84 sft per drum 12 | nos | @ | Tk. | 200.00 | each | = | Tk. | 2,400.00 |