3. Nails, gozzal & wire etc. 5.00 kg @ Tk. 4. Labour for cutting and straightening drum sheet, placing and fixing
5. Local carriage | 65.00 per kg 390.00 per day 320.00 per day LS | = = = = | Tk. Tk. Tk. Tk. | 325.00 780.00 960.00 640.00 |
Sub - Total Profit 10.00% Overhead 3.50% | = = = | Tk. | 6,005.00 600.50 210.18 | |
Total | = | Tk. | 6,815.68 | |
Add VAT with adjustment factor | 1.06383 6.00% | = | Tk. | 435.04 |
| Grand Total | = | Tk. | 7,250.72 |
| Rate per sft | = | Tk. | 48.34 |
| Rate per sqm | = | Tk. | 520.33 |
Say, Tk. | 520 .00 per sqm |
|
|
|
|
|
|
|
|
Item No.- 02.6 |
|
|
|
|
Supplying and fitting-fixing horizontal bracing in Palisading with 1/2 split wooden ballah. |
|
|
|
|
Considering 20 rft of work (a) Cost for 1/2 split ballah in/c carriage 20 rft @ Tk. (b) Labour for fitting-fixing including spliting
| 35.00 per rft 390.00 per day | = = | Tk. Tk. | 700.00 97.50 |
| 320.00 per day | = | Tk. | 80.00 |
(c) Gajals, Nails and wires etc. | LS | = | Tk. | 29.37 |
| Sub - Total | = | Tk. | 906.87 |
| Profit 10.00% | = | Tk. | 90.69 |
| Overhead 3.50% | = | Tk. | 31.74 |
| Total | = | Tk. | 1,029.30 |
Add VAT with adjustment factor | 1.06383 6.00% | = | Tk. | 65.70 |
| Grand Total | = | Tk. | 1,095.00 |
| Rate per rft | = | Tk. | 54.75 |
| Rate per rm | = | Tk. | 179.63 |
Say, Tk. | 180 .00 per meter |
|
|
|
|
|
|
|
|
Item No.- 02.7.1 |
|
|
|
|
Shore protection during earthwork in excavation for foundation: depth up to 1.5 m depth. considering 2 x 22'-0" x 5'-0"= 220.00 sft 2 x 12'-0" x 5'-0"= 120.00 sft | 40.03 per sft | = | Tk. | 13,610.20 |
340.00 sft area of palisading
| ||||
2 x 5 x 8'-0"= 80.00 rft 2 x 1 x 8'-0"= 16.00 rft | 20.20 per rft | = | Tk. | 1,939.20 |
96.00 rft @ Tk. | ||||
|
|
|
|
|
2 x 2 x 5 x 7'-0"= 140.00 rft 2 x 2 x 1 x 7'-0"= 28.00 rft | 120.00 per kg | = | Tk. | 385.20 |
168.00 rft = 3.21 kg @ Tk. | ||||
| Sub - Total | = | Tk. | 15,934.60 |
| Profit 10.00% | = | Tk. | 1,593.46 |
| Overhead 3.50% | = | Tk. | 557.71 |
| Total | = | Tk. | 18,085.77 |
Add VAT with adjustment factor | 1.06383 6.00% | = | Tk. | 1,154.41 |
| Grand Total | = | Tk. | 19,240.18 |
| Rate per sft | = | Tk. | 56.59 |
| Rate per sqm | = | Tk. | 609.13 |
Say, Tk. | 609 .00 per sqm |
|
|
|