| Profit | Sub - Total 10.00% 3.50% | = = = | Tk. | 14,578.25 1,457.83 510.24 |
Total | = | Tk. | 16,546.32 | ||
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 1,056.15 |
|
| Grand Total | = | Tk. | 17,602.47 |
|
| Rate per cft | = | Tk. | 17.60 |
|
| Rate per cum | = | Tk. | 621.54 |
Say, Tk. | 622 | .00 per cum |
|
|
|
|
|
|
|
|
|
Item No.- 02.15.2 |
|
|
|
|
|
Earth filling in foundation trenches with carted earth carried by truck or any other means |
|
|
|
|
|
Considering 1000 cft of work in/c compacting, dressing and local carriage |
|
|
|
|
|
For Chittagong / Sylhet/ Narayanganj Area |
|
|
|
|
|
Loose earth required in/c 15% shrinkage = | 1,150.00 | cft |
|
|
|
1. Royalty for earth 1150 cft @ Tk. | 1,715.00 | per % 0 cft | = | Tk. | 1,972.25 |
2 Truck hire charge including cost of labour for 6 Trips @ Tk. loading and unloading 3 Lbour for loca crriage, levelling & compacting etc. complete:
| 1,200.00 320.00 | per trip | = = | Tk. Tk. | 7,200.00 1,920.00 |
| 390.00 | per day | = | Tk. | 390.00 |
4 Sundries, T & P etc. |
| LS | = |
| 172.23 |
|
| Sub - Total | = | Tk. | 11,654.48 |
| Profit | 10.00% | = | Tk. | 1,165.45 |
| Overhead | 3.50% | = | Tk. | 407.91 |
|
| Total | = | Tk. | 13,227.84 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 844.33 |
|
| Grand Total | = | Tk. | 14,072.17 |
|
| Rate per cft | = | Tk. | 14.07 |
|
| Rate per cum | = | Tk. | 496.88 |
Say, Tk. | 497 | .00 per cum |
|
|
|
|
|
|
|
|
|
Item No.- 02.15.3 |
|
|
|
|
|
Earth filling in foundation trenches with carted earth carried by truck or any other means |
|
|
|
|
|
Considering 1000 cft of work in/c conmpacting, dressing and local carriage |
|
|
|
|
|
For Rajshahi / Barisal / Khulna metropolitan area |
|
|
|
|
|
Loose earth required in/c 15% shrinkage = | 1,150.00 | cft |
|
|
|
1. Royalty for earth 1150 cft @ Tk. | 1,715.00 | per % 0 cft | = | Tk. | 1,972.25 |
3. Truck hire charge including cost of labour for loading and unloading 6 Trips @ Tk. | 950.00 | per trips | = | Tk. | 5,700.00 |
4. Labour for local carriage, levelling & compacting etc. complete: |
|
|
|
|
|
| 320.00 | per day | = | Tk. | 1,920.00 |
| 390.00 | per day | = | Tk. | 390.00 |
5. Sundries, T & P etc. |
| LS | = |
| 149.73 |
|
| Sub - Total | = | Tk. | 10,131.98 |
| Profit | 10.00% | = | Tk. | 1,013.20 |
| Overhead | 3.50% | = | Tk. | 354.62 |
|
| Total | = | Tk. | 11,499.80 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 734.03 |
|
| Grand Total | = | Tk. | 12,233.83 |
|
| Rate per cft | = | Tk. | 12.23 |
|
| Rate per cum | = | Tk. | 431.90 |
Say, Tk. | 432 | .00 per cum |
|
|
|
|
|
|
|
|
|
Item No.- 02.15.4 |
|
|
|
|
|
Earth filling in foundation trenches with carted earth carried by truck or any other means |
|
|
|
|
|
Considering 1000 cft of work in/c compacting, dressing and local carriage |
|
|
|
|
|
(d) For other than Dhaka, Ctg., Sylhet, Rajshahi, Barisal, Khulna metropolitan area and N'ganj district |
|
|
| ||
Loose earth required in/c 15% shrinkage = 1,150.00 cft |
|
|
| ||