Prev Next


 

Profit
Overhead

10.00%

3.50%

=

=

Tk. Tk.

1,156.41

404.74

Total

=

Tk.

13,125.28

Add VAT with adjustment factor

1.06383

6.00%

=

Tk.

837.78

 

 

Grand Total

=

Tk.

13,963.06

 

 

Rate per cft

=

Tk.

139.63

 

 

Rate per cum

=

Tk.

4,931.03

Say, Tk.

4,931

.00 per cum

 

 

 

 

 

 

 

 

 

Item No.- 02.13

 

 

 

 

 

Earth filling in foundation trenches and plinth (earth available at site)

 

 

 

 

 

Considering 1000 cft of work

1. Labour for filling

including local carriage 8 nos @ Tk.

320.00

per day

=

Tk.

2,560.00

  1. Skilled labour for dressing

& consolidation 2 nos @ Tk.

390.00

per day

=

Tk.

780.00

  1. Sundries, T & P etc.

 

LS

=

Tk.

160.00

 

 

Sub - Total

=

Tk.

3,500.00

 

Profit

10.00%

=

Tk.

350.00

 

Overhead

3.50%

=

Tk.

122.50

 

 

Total

=

Tk.

3,972.50

Add VAT with adjustment factor

1.06383

6.00%

=

Tk.

253.56

 

 

Grand Total

=

Tk.

4,226.06

 

 

Rate per cft

=

Tk.

4.23

 

 

Rate per cum

=

Tk.

149.38

Say, Tk.

149

.00 per cum

 

 

 

 

 

 

 

 

 

Item No.- 02.14

 

 

 

 

 

Carriage of excavated earth from the construction site by truck or any other means to the selected government land within metropolitan area

 

 

 

 

 

Break-up for 1000 cft = 1150 cft loose earth

  1. Ordinary labour for cutting,

loading and unloading 7 nos @ Tk.

320.00

per day

=

Tk.

2,240.00

  1. Skilled labour 1.5 nos @ Tk.

390.00

per day

=

Tk.

585.00

  1. Truck fare 6 trips @ Tk.

1,700.00

trip

=

Tk.

10,200.00

  1. Ordinary labour for local carriage,

leveling and dressing etc. 3 nos @ Tk.

320.00

per day

=

Tk.

960.00

  1. Tools and plant, sundries etc.

 

LS

=

Tk.

80.00

deduction for royality of earh 60.55665 per cum

 

Sub - Total

=

Tk.

14,065.00

 

Profit

10.00%

=

Tk.

1,406.50

 

Overhead

3.50%

=

Tk.

492.28

 

 

Total

=

Tk.

15,963.78

Add VAT with adjustment factor

1.06383

6.00%

=

Tk.

1,018.96

 

 

Grand Total

=

Tk.

16,982.74

 

 

Rate per cft

=

Tk.

16.98

 

 

Rate per cum

=

Tk.

599.65

Say Tk.

539

.00 per cum

 

 

 

 

 

 

 

 

 

Item No.- 02.15.1

 

 

 

 

 

Earth filling in foundation trenches with carted earth carried by truck or any other means

 

 

 

 

 

Considering 1000 cft of work in/c compacting, dressing and local carriage

 

 

 

 

 

For Dhaka Metropolitan Area

 

 

 

 

 

Loose earth required in/c 15% shrinkage =

1,150.00

cft

 

 

 

1. Royalty for earth 1150 cft @ Tk.

1,715.00

per % 0 cft

=

Tk.

1,972.25

2 Truck hire charge including cost of labour for 6 trucks @ Tk.

loading and unloading

3 Lbour for loca crriage, levelling & compacting etc.

  1. Ordinary labour 6 nos @ Tk.

1,700.00

320.00

per truck
per day

=

=

Tk. Tk.

10,200.00

1,920.00

  1. Skilled labour 1 no @ Tk.

390.00

per day

=

Tk.

390.00

4 Sundries, T & P etc.

 

LS

=

Tk.

96.00