| Rate per cum | = | Tk. | 185.40 |
2.18.2 | Say, | Tk. | 185 | .00 per cum |
|
|
|
For each additional lift of one foot beyond 5'-0" and upto 10'-0" |
|
|
|
| |||
| Considering 1000 cft of excavation work |
|
|
|
|
|
|
(i) | Extra labour 1/2 no @ | Tk. | 320.00 | per day | = | Tk. | 160.00 |
|
|
| Profit | 10.00% | = | Tk. | 16.00 |
|
|
| Overhead | 3.50% | = | Tk. | 5.60 |
|
|
|
| Total | = | Tk. | 181.60 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 11.59 |
|
|
|
| Grand Total | = | Tk. | 193.19 |
|
|
|
| Rate per cft | = | Tk. | 0.19 |
|
|
|
| Rate per cum | = | Tk. | 6.71 |
| Say | Tk. | 7 | .00 per cum |
|
|
|
2.18.3 | For each additional lift of one foot beyond 10'-0" and upto 15'-0" |
|
|
|
|
|
|
| Considering 1000 cft of excavation work |
|
|
|
|
|
|
(i) | Extra labour 3/4 no @ | Tk. | 320.00 | per day | = | Tk. | 240.00 |
|
|
| Profit | 10.00% | = | Tk. | 24.00 |
|
|
| Overhead | 3.50% | = | Tk. | 8.40 |
|
|
|
| Total | = | Tk. | 272.40 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 17.39 |
|
|
|
| Grand Total | = | Tk. | 289.79 |
|
|
|
| Rate per cft | = | Tk. | 0.29 |
|
|
|
| Rate per cum | = | Tk. | 10.24 |
| Say | Tk. | 10 | .00 per cum |
|
|
|
2.18.4 | For each additional lift of one foot beyond 15'-0" and upto 20'-0" |
|
|
|
|
|
|
| Considering 1000 cft of excavation work |
|
|
|
|
|
|
(i) | Extra labour 1 no @ | Tk. | 320.00 | per day | = | Tk. | 320.00 |
|
|
| Profit | 10.00% | = | Tk. | 32.00 |
|
|
| Overhead | 3.50% | = | Tk. | 11.20 |
|
|
|
| Total | = | Tk. | 363.20 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 23.18 |
|
|
|
| Grand Total | = | Tk. | 386.38 |
|
|
|
| Rate per cft | = | Tk. | 0.39 |
|
|
|
| Rate per cum | = | Tk. | 13.77 |
2.18.5 | Say, | Tk. | 14 | .00 per cum |
|
|
|
Extra each additional lead of 100'-0" |
|
|
|
| |||
| Considering 1000 cft of excavation work |
|
|
|
|
|
|
(i) | Extra labour 2 nos @ | Tk. | 320.00 | per day | = | Tk. | 640.00 |
|
|
| Profit | 10.00% | = | Tk. | 64.00 |
|
|
| Overhead | 3.50% | = | Tk. | 22.40 |
|
|
|
| Total | = | Tk. | 726.40 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 46.37 |
|
|
|
| Grand Total | = | Tk. | 772.77 |
|
|
|
| Rate per cft | = | Tk. | 0.77 |
|
|
|
| Rate per cum | = | Tk. | 27.19 |
| Say | Tk. | 27 | .00 per cum |
|
|
|
2.19.1 | Bailing-out water using 1 cusec diesel operated pump set |
|
|
|
|
|
|
| Considering 1 day operation = 8 Hrs. |
|
|
|
|
|
|
Hire charge of pump including suction |
|
|
|
|
|
| |
| and delivery pipe, connection, switch 1 day @ | Tk. | 1,200.00 | per day | = | Tk. | 1,200.00 |
Fuel, lubricant, spares, maintenance etc. |
|
| LS | = | Tk. | 600.00 |