| Pump operator 1 no @ Helper 1 no @ Skilled labour for maintaining drainage 1 no @ Provide drainage facilities and connection to discharge system Tools and plant, sundries etc. | Tk. | 600.00 390.00 390.00 | per day LS LS | = = = = = | Tk. Tk. Tk. Tk. Tk. | 600.00 390.00 390.00 250.00 150.00 |
|
|
|
| Sub - Total | = | Tk. | 3,580.00 |
|
|
| Profit | 10.00% | = | Tk. | 358.00 |
|
|
| Overhead | 3.50% | = | Tk. | 125.30 |
|
|
|
| Total | = | Tk. | 4,063.30 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 243.80 |
|
|
|
| Grand Total | = | Tk. | 4,307.10 |
|
|
|
| Rate per hour | = | Tk. | 538.39 |
2.19.2 | Say, | Tk. | 538 | .00 per hour |
|
|
|
Bailing-out water using 1 cusec pump electricity operated pump set |
|
|
|
| |||
| Considering 1 day operation = 8 Hrs. |
|
|
|
|
|
|
Hire charge of pump including suction |
|
|
|
|
|
| |
| and delivery pipe, connection, switch 1 day @ | Tk. | 800.00 | per day | = | Tk. | 800.00 |
Electricity, lubricant, spares, maintenance etc. |
|
| LS | = | Tk. | 300.00 | |
Pump operator 1 no @ | Tk. | 600.00 | per day | = | Tk. | 600.00 | |
Helper 1 no @ | Tk. | 390.00 | per day | = | Tk. | 390.00 | |
Skilled labour for maintaining drainage 1 no @ | Tk. | 390.00 | per day | = | Tk. | 390.00 | |
Provide drainage facilities and connection to discharge facilities |
|
| LS | = | Tk. | 250.00 | |
(viii) | Tools and plant, sundries etc. |
|
| LS | = | Tk. | 150.00 |
|
|
|
| Sub - Total | = | Tk. | 2,880.00 |
|
|
| Profit | 10.00% | = | Tk. | 288.00 |
|
|
| Overhead | 3.50% | = | Tk. | 100.80 |
|
|
|
| Total | = | Tk. | 3,268.80 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 196.13 |
|
|
|
| Grand Total | = | Tk. | 3,464.93 |
|
|
|
| Rate per hour | = | Tk. | 433.12 |
| Say, | Tk. | 433 | .00 per hour |
|
|
|