|
|
| Profit | 10.00% 3.50% | = = | Tk. Tk. | 705.43 246.90 |
Total | = | Tk. | 8,006.58 | ||||
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 511.06 | |
|
|
|
| Grand Total | = | Tk. | 8,517.64 |
|
|
|
| Rate per sft | = | Tk. | 85.18 |
(i) Ground floor |
|
|
| Rate per sft | = | Tk. | 85.18 |
|
|
|
| Rate per sqm | = | Tk. | 916.88 |
| Say, | Tk. | 917 | .00 per sqm |
|
|
|
|
|
|
|
|
|
|
|
Item No.- 04.16 |
|
|
|
|
|
|
|
125 mm brick work with first class bricks (1:4) in superstructure |
|
|
|
|
|
|
|
Considering 100 sft work |
|
|
|
|
|
|
|
| @ | Tk. | 8,700.00 | per % 0 nos | = | Tk. | 4,176.00 |
| @ | Tk. | 1,400.00 | per % cft | = | Tk. | 238.00 |
| @ | Tk. | 395.00 | per bag | = | Tk. | 1,027.00 |
| @ | Tk. | 600.00 | per day | = | Tk. | 60.00 |
| @ | Tk. | 500.00 | per day | = | Tk. | 375.00 |
| @ | Tk. | 390.00 | per day | = | Tk. | 195.00 |
| @ | Tk. | 320.00 | per day | = | Tk. | 160.00 |
cleaning bricks 1 no | @ | Tk. | 320.00 | per day | = | Tk. | 320.00 |
washing sand 1/4 no | @ | Tk. | 320.00 | per day | = | Tk. | 80.00 |
@ 1/8 No. labour per day 0.875 no | @ | Tk. | 320.00 | per day | = | Tk. | 280.00 |
| @ | Tk. | 9.00 | per sft | = | Tk. | 225.00 |
|
|
|
| LS | = | Tk. | 160.00 |
|
|
|
| Sub - Total | = | Tk. | 7,296.00 |
|
|
| Profit | 10.00% | = | Tk. | 729.60 |
|
|
| Overhead | 3.50% | = | Tk. | 255.36 |
|
|
|
| Total | = | Tk. | 8,280.96 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 528.57 | |
|
|
|
| Grand Total | = | Tk. | 8,809.53 |
|
|
|
| Rate per sft | = | Tk. | 88.10 |
(i) Ground floor |
|
|
| Rate per sft | = | Tk. | 88.10 |
|
|
|
| Rate per sqm | = | Tk. | 948.31 |
| Say, | Tk. | 948 | .00 per sqm |
|
|
|
|
|
|
|
|
|
|
|
Item No.- 04.17 |
|
|
|
|
|
|
|
Exposed 125 mm pointing extra ordinary ornamental brick work (1:4) |
|
|
|
|
|
|
|
Considering 100 sft of work |
|
|
|
|
|
|
|
| @ | Tk. | 8,700.00 | per % 0 nos | = | Tk. | 4,176.00 |
Extra cost for special quality 1st class bricks in/c sorting out the bricks | @ |
| 20% |
| = | Tk. | 835.20 |
| @ | Tk. | 1,400.00 | per % cft | = | Tk. | 322.00 |
| @ | Tk. | 395.00 | per bag | = | Tk. | 1,185.00 |
| @ | Tk. | 600.00 | per day | = | Tk. | 60.00 |
| @ | Tk. | 500.00 | per day | = | Tk. | 500.00 |
| @ | Tk. | 390.00 | per day | = | Tk. | 195.00 |
| @ | Tk. | 320.00 | per day | = | Tk. | 160.00 |
cleaning bricks 1 no | @ | Tk. | 320.00 | per day | = | Tk. | 320.00 |
washing sand 0.25 no | @ | Tk. | 320.00 | per day | = | Tk. | 80.00 |
@ 1/4 labour per day 1.75 nos | @ | Tk. | 320.00 | per day | = | Tk. | 560.00 |
| @ | Tk. | 9.00 | per sft | = | Tk. | 225.00 |
|
|
|
| LS | = | Tk. | 266.67 |
|
|
|
| Sub - Total | = | Tk. | 8,884.87 |