|
|
|
|
|
@ 1/8 labour per day 0.875 no @ Tk. 320.00 | per day | = | Tk. | 280.00 |
| per sft | = | Tk. | 225.00 |
| LS | = | Tk. | 320.00 |
| Sub - Total | = | Tk. | 19,892.25 |
Profit | 10.00% | = | Tk. | 1,989.23 |
Overhead | 3.50% | = | Tk. | 696.23 |
| Total | = | Tk. | 22,577.71 |
Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 1,441.13 |
| Grand Total | = | Tk. | 24,018.84 |
(i) Ground floor | Rate per sft | = | Tk. | 240.19 |
| Rate per sqm | = | Tk. | 2,585.41 |
Say, Tk. 2,585 | .00 per sqm |
|
|
|
|
|
|
|
|
Item No.- 04.14.5 |
|
|
|
|
Facing brick work with 242 x 70 x 12.7 mm clay wall tile (matt glazed textured) with 1:4 mortar with out side pointing. |
|
|
|
|
Considering 100 sft of work
in/c 5% wastage 540 nos @ Tk. 34,000.00 | per % 0 nos | = | Tk. | 18,360.00 |
| per % cft | = | Tk. | 196.00 |
| per bag | = | Tk. | 1,086.25 |
| per day | = | Tk. | 600.00 |
| per day | = | Tk. | 1,000.00 |
| per day | = | Tk. | 585.00 |
| per day | = | Tk. | 480.00 |
@ 1/8 labour per day 0.875 no @ Tk. 320.00 | per day | = | Tk. | 280.00 |
| per sft | = | Tk. | 225.00 |
| LS | = | Tk. | 320.00 |
| Sub - Total | = | Tk. | 23,132.25 |
Profit | 10.00% | = | Tk. | 2,313.23 |
Overhead | 3.50% | = | Tk. | 809.63 |
| Total | = | Tk. | 26,255.11 |
Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 1,675.86 |
| Grand Total | = | Tk. | 27,930.97 |
(i) Ground floor | Rate per sft | = | Tk. | 279.31 |
| Rate per sqm | = | Tk. | 3,006.49 |
Say, Tk. 3,006 | .00 per sqm |
|
|
|
|
|
|
|
|
Item No.- 04.15 |
|
|
|
|
125 mm brick work with first class bricks (1:6) in superstructure |
|
|
|
|
Considering 100 sft work
| per % 0 nos | = | Tk. | 4,176.00 |
| per % cft | = | Tk. | 252.00 |
| per bag | = | Tk. | 691.25 |
| per day | = | Tk. | 60.00 |
| per day | = | Tk. | 375.00 |
| per day | = | Tk. | 195.00 |
| per day | = | Tk. | 160.00 |
cleaning bricks 1 no @ Tk. 320.00 | per day | = | Tk. | 320.00 |
washing sand 1/2 no @ Tk. 320.00 | per day | = | Tk. | 160.00 |
@ 1/8 No. labour per day 0.875 no @ Tk. 320.00 | per day | = | Tk. | 280.00 |
| per sft | = | Tk. | 225.00 |
| LS | = | Tk. | 160.00 |
| Sub - Total | = | Tk. | 7,054.25 |