Add VAT with adjustment factor 1.06383 (i) Ground floor | 6.00% | = | Tk. | 910.66 |
Grand Total Rate per sft Rate per sft Rate per sqm | = = = = | Tk. Tk. Tk. Tk. | 15,177.61 151.78 151.78 1,633.76 | |
Say, Tk. 1,634 | .00 per sqm |
| ||
|
|
|
|
|
Item No.- 04.20.1 |
|
|
|
|
Fancy screen work in wall with 4.5" x 4.5" x 4.5" design block in all floors (1:3). |
|
|
|
|
Considering 100 sft of work |
|
|
|
|
A. Materials: |
|
|
|
|
block in/c wastage 945 nos @ Tk. 28,000.00 | per % 0 nos | = | Tk. | 26,460.00 |
| per % cft | = | Tk. | 52.50 |
| per bag | = | Tk. | 395.00 |
| per Ib | = | Tk. | 70.00 |
B. Labour: |
|
|
|
|
| each | = | Tk. | 750.00 |
| each | = | Tk. | 1,375.00 |
| each | = | Tk. | 975.00 |
| each | = | Tk. | 320.00 |
cleaning blocks. 1 no @ Tk. 320.00 | each | = | Tk. | 320.00 |
@ 1/8 No. labour per day 0.875 no @ Tk. 320.00 | each | = | Tk. | 280.00 |
| per sft | = | Tk. | 225.00 |
| LS | = | Tk. | 160.00 |
| Sub - Total | = | Tk. | 31,382.50 |
Profit | 10.00% | = | Tk. | 3,138.25 |
Overhead | 3.50% | = | Tk. | 1,098.39 |
| Total |
| Tk. | 35,619.14 |
Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 2,273.56 |
| Grand Total | = | Tk. | 37,892.70 |
(i) Ground floor | Rate per sft | = | Tk. | 378.93 |
| Rate per sqm | = | Tk. | 4,078.80 |
Say, Tk. 4,079 | .00 per sqm |
|
|
|
|
|
|
|
|
Item No.- 04.20.2 |
|
|
|
|
Fancy screen work in wall with 5.5" x 5.5" x 4" design block in all floors (1:3) facing 5.5" x 4" |
|
|
|
|
Considering 100 sft of work |
|
|
|
|
A. Materials: |
|
|
|
|
block in/c wastage 510 nos @ Tk. 34,000.00 | per % 0 nos | = | Tk. | 17,340.00 |
| per % cft | = | Tk. | 52.50 |
| per bag | = | Tk. | 395.00 |
| per Ib | = | Tk. | 70.00 |
B. Labour: |
|
|
|
|
| per day | = | Tk. | 750.00 |
| per day | = | Tk. | 1,375.00 |
| per day | = | Tk. | 975.00 |
| per day | = | Tk. | 320.00 |
cleaning blocks 0.50 no @ Tk. 320.00 | per day | = | Tk. | 160.00 |
@ 1/8 No. labour per day 0.875 no @ Tk. 320.00 | per day | = | Tk. | 280.00 |
| per sft | = | Tk. | 225.00 |
| LS | = | Tk. | 160.00 |
| Sub - Total | = | Tk. | 22,102.50 |
Profit | 10.00% | = | Tk. | 2,210.25 |
Overhead | 3.50% | = | Tk. | 773.59 |