Add VAT with adjustment factor (i) Ground floor |
| 1.06383 | Total 6.00% | = = | Tk. Tk. | 25,086.34 1,601.26 |
Grand Total Rate per sft Rate per sqm | = = = | Tk. | 26,687.60 266.88 2,872.70 | |||
Say, | Tk. | 2,873 | .00 per sqm |
| ||
|
|
|
|
|
|
|
Item No.- 04.20.3 |
|
|
|
|
|
|
Fancy Screen work with 6" x 6" x 4" or 6" x 6" x 4.5" design block in all floors (1:3) |
|
|
|
|
|
|
Considering 100 sft of work |
|
|
|
|
|
|
A. Materials: |
|
|
|
|
|
|
block in/c wastage 420 nos @ | Tk. | 37,000.00 | per % 0 nos | = | Tk. | 15,540.00 |
| Tk. | 1,400.00 | per % cft | = | Tk. | 52.50 |
| Tk. | 395.00 | per bag | = | Tk. | 395.00 |
| Tk. | 70.00 | per Ib | = | Tk. | 70.00 |
B. Labour: |
|
|
|
|
|
|
| Tk. | 600.00 | per day | = | Tk. | 750.00 |
| Tk. | 500.00 | per day | = | Tk. | 1,375.00 |
| Tk. | 390.00 | per day | = | Tk. | 975.00 |
| Tk. | 320.00 | per day | = | Tk. | 320.00 |
cleaning blocks. 0.50 no @ | Tk. | 320.00 | per day | = | Tk. | 160.00 |
@ 1/8 No. labour per day 0.875 no @ | Tk. | 320.00 | per day | = | Tk. | 280.00 |
| Tk. | 9.00 | per sft | = | Tk. | 225.00 |
|
|
| LS | = | Tk. | 160.00 |
|
|
| Sub - Total | = | Tk. | 20,302.50 |
|
| Profit | 10.00% | = | Tk. | 2,030.25 |
|
| Overhead | 3.50% | = | Tk. | 710.59 |
|
|
| Total | = | Tk. | 23,043.34 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 1,470.85 |
|
|
| Grand Total | = | Tk. | 24,514.19 |
(i) Ground floor |
|
| Rate per sft | = | Tk. | 245.14 |
|
|
| Rate per sqm | = | Tk. | 2,638.69 |
Say, | Tk. | 2,639 | .00 per sqm |
|
|
|
|
|
|
|
|
|
|
Item No.- 04.20.4 |
|
|
|
|
|
|
Fancy Screen work with 8" x 8" x 4.25" design block |
|
|
|
|
|
|
Considering 100 sft of work |
|
|
|
|
|
|
A. Materials: |
|
|
|
|
|
|
block in/c wastage 235 nos @ | Tk. | 47,000.00 | per % 0 nos | = | Tk. | 11,045.00 |
| Tk. | 1,400.00 | per % cft | = | Tk. | 28.00 |
| Tk. | 395.00 | per bag | = | Tk. | 197.50 |
| Tk. | 70.00 | per Ib | = | Tk. | 35.00 |
B. Labour: |
|
|
|
|
|
|
| Tk. | 600.00 | per day | = | Tk. | 600.00 |
| Tk. | 500.00 | per day | = | Tk. | 1,000.00 |
| Tk. | 390.00 | per day | = | Tk. | 975.00 |
| Tk. | 320.00 | per day | = | Tk. | 320.00 |
cleaning blocks. 0.50 no @ | Tk. | 320.00 | per day | = | Tk. | 160.00 |
@ 1/8 No. labour per day 0.875 no @ | Tk. | 320.00 | per day | = | Tk. | 280.00 |
| Tk. | 9.00 | per sft | = | Tk. | 225.00 |
|
|
| LS | = | Tk. | 160.00 |
|
|
| Sub - Total | = | Tk. | 15,025.50 |
|
| Profit | 10.00% | = | Tk. | 1,502.55 |
|
| Overhead | 3.50% | = | Tk. | 525.89 |