Prev Next
īģŋ

Add VAT with adjustment

(i) Ground floor

factor

 

1.06383

Total

6.00%

=

=

Tk. Tk.

17,053.94

1,088.55

Grand Total Rate per sft Rate per sqm

=

=

=

Tk.
Tk.
Tk.

18,142.49

181.42

1,952.80

Say,

Tk.

1,953

.00 per sqm

 

 

 

 

 

 

 

 

 

 

Item No.- 04.20.5

 

 

 

 

 

 

 

 

Fancy Screen work with 8" x 4.75" x 4" design block in all floors (1:3)

 

 

 

 

 

 

 

 

Considering 100 sft of work

 

 

 

 

 

 

 

 

A. Materials:

 

 

 

 

 

 

 

 

  1. 8" x 4.75" x 4" design

block in/c wastage 270

nos

@

Tk.

47,000.00

per % 0 nos

=

Tk.

12,690.00

  1. Sand (F.M. 1.2) 2

cft

@

Tk.

1,400.00

per % cft

=

Tk.

28.00

  1. Cement 0.5

bag

@

Tk.

395.00

per bag

=

Tk.

197.50

  1. Colour pigment 0.5

Ib

@

Tk.

70.00

per Ib

=

Tk.

35.00

B. Labour:

 

 

 

 

 

 

 

 

  1. Head mason 1

no

@

Tk.

600.00

per day

=

Tk.

600.00

  1. Mason 2

nos

@

Tk.

500.00

per day

=

Tk.

1,000.00

  1. Skilled labour 2.5

nos

@

Tk.

390.00

per day

=

Tk.

975.00

  1. Ordinary labour 1

no

@

Tk.

320.00

per day

=

Tk.

320.00

  1. Labour for soaking &

cleaning blocks. 0.50

no

@

Tk.

320.00

per day

=

Tk.

160.00

  1. Labour for 7 days curing

@ 1/8 No. labour per day 0.875

no

@

Tk.

320.00

per day

=

Tk.

280.00

  1. Scaffolding 25

sft

@

Tk.

9.00

per sft

=

Tk.

225.00

  1. Washing of sand, local carriage & storage etc.

 

 

 

 

LS

=

Tk.

160.00

 

 

 

 

 

Sub - Total

=

Tk.

16,670.50

 

 

 

 

Profit

10.00%

=

Tk.

1,667.05

 

 

 

 

Overhead

3.50%

=

Tk.

583.47

 

 

 

 

 

Total

=

Tk.

18,921.02

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

1,207.72

 

 

 

 

 

Grand Total

=

Tk.

20,128.74

(i) Ground floor

 

 

 

 

Rate per sft

=

Tk.

201.29

 

 

 

 

 

Rate per sqm

=

Tk.

2,166.69

 

 

Say,

Tk.

2,167

.00 per sqm

 

 

 

 

 

 

 

 

 

 

 

 

Item No.- 04.20.6

 

 

 

 

 

 

 

 

Fancy Screen work with 6" x 6" x 6"design block in all floors (1:3)

 

 

 

 

 

 

 

 

Considering 100 sft of work

 

 

 

 

 

 

 

 

A. Materials:

 

 

 

 

 

 

 

 

  1. 6" x 6" x 6" design

block in/c wastage 420

nos

@

Tk.

37,000.00

per % 0 nos

=

Tk.

15,540.00

  1. Sand (F.M. 1.2) 3.75

cft

@

Tk.

1,400.00

per % cft

=

Tk.

52.50

  1. Cement 1

bag

@

Tk.

395.00

per bag

=

Tk.

395.00

  1. Colour pigment 1

Ib

@

Tk.

70.00

per Ib

=

Tk.

70.00

B. Labour:

 

 

 

 

 

 

 

 

  1. Head mason 1.25

nos

@

Tk.

600.00

per day

=

Tk.

750.00

  1. Mason 2.75

nos

@

Tk.

500.00

per day

=

Tk.

1,375.00

  1. Skilled labour 2.5

nos

@

Tk.

390.00

per day

=

Tk.

975.00

  1. Ordinary labour 1

no

@

Tk.

320.00

per day

=

Tk.

320.00

  1. Labour for soaking &

cleaning blocks. 0.50

no

@

Tk.

320.00

per day

=

Tk.

160.00

  1. Labour for 7 days curing

@ 1/8 No. labour per day 0.875

no

@

Tk.

320.00

per day

=

Tk.

280.00

  1. Scaffolding 25

sft

@

Tk.

9.00

per sft

=

Tk.

225.00

  1. Washing of sand, local carriage & storage etc.

 

 

 

 

LS

=

Tk.

160.00

 

 

 

 

 

Sub - Total

=

Tk.

20,302.50

 

 

 

 

Profit

10.00%

=

Tk.

2,030.25

 

 

 

 

Overhead

3.50%

=

Tk.

710.59