Add VAT with adjustment (i) Ground floor | factor |
| 1.06383 | Total 6.00% | = = | Tk. Tk. | 17,053.94 1,088.55 | |
Grand Total Rate per sft Rate per sqm | = = = | Tk. | 18,142.49 181.42 1,952.80 | |||||
Say, | Tk. | 1,953 | .00 per sqm |
| ||||
|
|
|
|
|
|
|
|
|
Item No.- 04.20.5 |
|
|
|
|
|
|
|
|
Fancy Screen work with 8" x 4.75" x 4" design block in all floors (1:3) |
|
|
|
|
|
|
|
|
Considering 100 sft of work |
|
|
|
|
|
|
|
|
A. Materials: |
|
|
|
|
|
|
|
|
block in/c wastage 270 | nos | @ | Tk. | 47,000.00 | per % 0 nos | = | Tk. | 12,690.00 |
| cft | @ | Tk. | 1,400.00 | per % cft | = | Tk. | 28.00 |
| bag | @ | Tk. | 395.00 | per bag | = | Tk. | 197.50 |
| Ib | @ | Tk. | 70.00 | per Ib | = | Tk. | 35.00 |
B. Labour: |
|
|
|
|
|
|
|
|
| no | @ | Tk. | 600.00 | per day | = | Tk. | 600.00 |
| nos | @ | Tk. | 500.00 | per day | = | Tk. | 1,000.00 |
| nos | @ | Tk. | 390.00 | per day | = | Tk. | 975.00 |
| no | @ | Tk. | 320.00 | per day | = | Tk. | 320.00 |
cleaning blocks. 0.50 | no | @ | Tk. | 320.00 | per day | = | Tk. | 160.00 |
@ 1/8 No. labour per day 0.875 | no | @ | Tk. | 320.00 | per day | = | Tk. | 280.00 |
| sft | @ | Tk. | 9.00 | per sft | = | Tk. | 225.00 |
|
|
|
|
| LS | = | Tk. | 160.00 |
|
|
|
|
| Sub - Total | = | Tk. | 16,670.50 |
|
|
|
| Profit | 10.00% | = | Tk. | 1,667.05 |
|
|
|
| Overhead | 3.50% | = | Tk. | 583.47 |
|
|
|
|
| Total | = | Tk. | 18,921.02 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 1,207.72 | ||
|
|
|
|
| Grand Total | = | Tk. | 20,128.74 |
(i) Ground floor |
|
|
|
| Rate per sft | = | Tk. | 201.29 |
|
|
|
|
| Rate per sqm | = | Tk. | 2,166.69 |
|
| Say, | Tk. | 2,167 | .00 per sqm |
|
|
|
|
|
|
|
|
|
|
|
|
Item No.- 04.20.6 |
|
|
|
|
|
|
|
|
Fancy Screen work with 6" x 6" x 6"design block in all floors (1:3) |
|
|
|
|
|
|
|
|
Considering 100 sft of work |
|
|
|
|
|
|
|
|
A. Materials: |
|
|
|
|
|
|
|
|
block in/c wastage 420 | nos | @ | Tk. | 37,000.00 | per % 0 nos | = | Tk. | 15,540.00 |
| cft | @ | Tk. | 1,400.00 | per % cft | = | Tk. | 52.50 |
| bag | @ | Tk. | 395.00 | per bag | = | Tk. | 395.00 |
| Ib | @ | Tk. | 70.00 | per Ib | = | Tk. | 70.00 |
B. Labour: |
|
|
|
|
|
|
|
|
| nos | @ | Tk. | 600.00 | per day | = | Tk. | 750.00 |
| nos | @ | Tk. | 500.00 | per day | = | Tk. | 1,375.00 |
| nos | @ | Tk. | 390.00 | per day | = | Tk. | 975.00 |
| no | @ | Tk. | 320.00 | per day | = | Tk. | 320.00 |
cleaning blocks. 0.50 | no | @ | Tk. | 320.00 | per day | = | Tk. | 160.00 |
@ 1/8 No. labour per day 0.875 | no | @ | Tk. | 320.00 | per day | = | Tk. | 280.00 |
| sft | @ | Tk. | 9.00 | per sft | = | Tk. | 225.00 |
|
|
|
|
| LS | = | Tk. | 160.00 |
|
|
|
|
| Sub - Total | = | Tk. | 20,302.50 |
|
|
|
| Profit | 10.00% | = | Tk. | 2,030.25 |
|
|
|
| Overhead | 3.50% | = | Tk. | 710.59 |