Add VAT with adjustment factor (i) Ground floor | 1.06383 | 6.00% | = | Tk. | 709.14 |
Grand Total Rate per sft Rate per sqm | = = = | Tk. | 11,818.98 118.19 1,272.20 | ||
Say, Tk. | 1,272 .00 per sqm |
| |||
|
|
|
|
|
|
Item No.- 05.1.5 |
|
|
|
|
|
10 mm thick (finished) mosaic in floor with Indian chips without glass strip using |
|
|
|
|
|
100% grey cement in/c 25 mm thick patent stone (1:2:4) with brick chips |
|
|
|
|
|
Considering 100 sft of work |
|
|
|
|
|
A. Materials: |
|
|
|
|
|
| 395.00 | per bag | = | Tk. | 948.00 |
| 18.00 | per kg | = | Tk. | 2,250.00 |
| 420.00 | each | = | Tk. | 140.00 |
neat finish and 1/4 No. mason 100 sft @ Tk. | 2,543.41 | per % sft | = | Tk. | 2,543.41 |
B. Labour: |
|
|
|
|
|
Same as 05.1.1 100 sft @ Tk. | 4,232.50 | per % sft | = | Tk. | 4,232.50 |
|
| Sub - Total | = | Tk. | 10,113.91 |
| Profit | 10.00% | = | Tk. | 1,011.39 |
| Overhead | 3.50% | = | Tk. | 353.99 |
|
| Total | = | Tk. | 11,479.29 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 732.72 |
|
| Grand Total | = | Tk. | 12,212.01 |
(i) Ground floor |
| Rate per sft | = | Tk. | 122.12 |
|
| Rate per sqm | = | Tk. | 1,314.50 |
Say, Tk. | 1,315 .00 per sqm |
|
|
| |
|
|
|
|
|
|
Item No.- 05.1.6 |
|
|
|
|
|
10 mm thick (finished) mosaic in floor with Pakistani chips & without glass strip using |
|
|
|
|
|
100% white cement in/c 25 mm thick patent stone with brick chips |
|
|
|
|
|
Considering 100 sft of work |
|
|
|
|
|
A. Materials
| 26.00 | per kg | = | Tk. | 3,250.00 |
| 20.00 | per kg | = | Tk. | 2,500.00 |
| 420.00 | each | = | Tk. | 140.00 |
neat finish and 1/4 No. mason. 100 sft @ Tk. | 2,543.41 | per % sft | = | Tk. | 2,543.41 |
|
| Sub-Total (a) | = | Tk. | 8,433.41 |
B. Labour: |
|
|
|
|
|
For mixing, laying, compacting and curing: |
|
|
|
|
|
| 600.00 | per day | = | Tk. | 450.00 |
| 390.00 | per day | = | Tk. | 292.50 |
| 320.00 | per day | = | Tk. | 320.00 |
Hire charge of mosaic cutting machine and operation: |
|
|
|
|
|
| 400.00 | per day | = | Tk. | 400.00 |
| 600.00 | per day | = | Tk. | 600.00 |
| 390.00 | per day | = | Tk. | 390.00 |
| 320.00 | per day | = | Tk. | 320.00 |
| 175.00 | each | = | Tk. | 525.00 |
Pumic stone oxalic acid and washing: |
|
|
|
|
|
Ordinary labour 1 no @ Tk. | 320.00 | per day | = | Tk. | 320.00 |
|
| Sub-Total (b) | = | Tk. | 3,617.50 |
| Sub-Total (a+b) | = | Tk. | 12,050.91 | |
| Profit | 10.00% | = | Tk. | 1,205.09 |
| Overhead | 3.50% | = | Tk. | 421.78 |
|
| Total | = | Tk. | 13,677.78 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 873.05 |