Prev Next
īģŋ

 

Analysis of PWD SoR 2018 for Civil Works 170

 

DIVISION 07 : REINFORCED CEMENT CONCRETE (RCC) WORKS

 

 

Item No.- 07.1

R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication with brick chips

07.1.1

Cost of concrete for individual and combined footings, pile cap, raft/mat floor slab, foundation beam up to plinth level

 

Considering 100 cft

  1.  

Materials (From Secondary Input : Item B-3) = Tk. 16,628.00

  1.  

Laying/placing concrete (@ 1200 cft concreting using 1 mixer machine in one day) = Tk. 999.83

 

(From Secondary Input : Item A-1) Sub - Total = Tk. 17,627.83

 

Profit 10.00% = Tk. 1,762.78

 

Overhead 3.50% = Tk. 616.97

 

Total = Tk. 20,007.58

 

Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,277.08

 

Grand Total = Tk. 21,284.66

 

Rate per cft = Tk. 212.85

 

Rate per cum = Tk. 7,516.80

 

Say, Tk. 7,517 .00 per cum

07.1.2

Cost of concrete for padestals, column, column capitals, lift walls and walls upto ground floor

 

Considering 100 cft

  1.  

Materials (From Secondary Input : Item B-3) = Tk. 16,628.00

  1.  

Laying/placing concrete (@ 800 cft concreting using 1 mixer machine in one day) = Tk. 1,499.75

 

(From Secondary Input : Item A-3) Sub - Total = Tk. 18,127.75

 

Profit 10.00% = Tk. 1,812.78

 

Overhead 3.50% = Tk. 634.47

 

Total = Tk. 20,575.00

 

Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,313.30

 

Grand Total = Tk. 21,888.30

 

Rate per cft = Tk. 218.88

 

Rate per cum = Tk. 7,729.75

 

Say, Tk. 7,730 .00 per cum

07.1.3

Cost of concrete for floor / roof slab, tee beams, ell beams and rectangular beams, tie Beam, lintels, stair case slab and steps etc. upto ground floor

 

 

Considering 100 cft

  1.  

Materials (From Secondary Input : Item B-3) = Tk. 16,628.00

  1.  

Laying/placing concrete (@ 1000 cft concreting using 1 mixer machine in one day) = Tk. 1,199.80

 

(From Secondary Input : Item A-2) Sub - Total = Tk. 17,827.80

 

Profit 10.00% = Tk. 1,782.78

 

Overhead 3.50% = Tk. 623.97

 

Total = Tk. 20,234.55

 

Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,291.57

 

Grand Total = Tk. 21,526.12

 

Rate per cft = Tk. 215.26

 

Rate per cum = Tk. 7,601.91

 

Say, Tk. 7,602 .00 per cum

07.1.4

Cost of concrete for cornice, railing, drop walls, louver, fins, sunshade, false ceiling, waffle and ribbed floor slab etc. up to ground floor

 

 

Considering 100 cft

  1.  

Materials (From Secondary Input : Item B-3) = Tk. 16,628.00

  1.  

Laying/placing concrete (@ 600 cft concreting using 1 mixer machine in one day) = Tk. 1,999.67

 

(From Secondary Input : Item A-4) Sub - Total = Tk. 18,627.67

 

Profit 10.00% = Tk. 1,862.77

 

Overhead 3.50% = Tk. 651.97

 

Total = Tk. 21,142.41

 

Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,349.52

 

Grand Total = Tk. 22,491.93