Prev Next
īģŋ

09.1.4

1.

550 mm dia

Considering executing 550 mm /22 inch dia & 20 meter long 0.8 No pile in a day. Hire charge of rig set in/c fuel, lubricant, bentonite,

mobilization, demobilization, maintenance

 

 

 

 

 

and insurance coverage etc. 1 day @ Tk.

6,000.00 per day

=

Tk.

6,000.00

2

Foreman/supervisor 1 no @ Tk.

800.00 per day

=

Tk.

800.00

3

Skilled labour 3 nos @ Tk.

390.00 per day

=

Tk.

1,170.00

4

Ordinary labour 6 nos @ Tk.

320.00 per day

=

Tk.

1,920.00

5

Bentonite 30 kg/m3 @ Tk.

20.00 per kg

=

Tk.

2,850.00

5

power ,water, clean & sundry

LS

=

Tk.

250.00

 

 

Sub - Total

=

Tk.

12,990.00

 

Profit 10.00%

=

Tk.

1,299.00

 

 

Overhead

3.50%

=

Tk.

454.65

 

 

Total

=

Tk.

14,743.65

 

Add VAT with adjustment factor 1.06383

6.00%

=

Tk.

941.08

 

 

Grand Total

=

Tk.

15,684.73

 

 

Rate per meter

=

Tk.

980.30

 

Say, Tk.

980 .00 per meter

 

 

 

09.1.5

600 mm dia

 

 

 

 

 

Considering executing 6000 mm /24 inch dia & 20 meter long 0.7 No pile in a day.

 

 

 

 

1.

Hire charge of rig set in/c fuel, lubricant, bentonite, mobilization, demobilization, maintenance

 

 

 

 

 

and insurance coverage etc. 1 day @ Tk.

6,000.00 per day

=

Tk.

6,000.00

2

Foreman/supervisor 1 no @ Tk.

800.00 per day

=

Tk.

800.00

3

Skilled labour 3 nos @ Tk.

390.00 per day

=

Tk.

1,170.00

4

Ordinary labour 6 nos @ Tk.

320.00 per day

=

Tk.

1,920.00

5

Bentonite 30 kg/m3 @ Tk.

20.00 per kg

=

Tk.

3,390.00

6

power ,water, clean & sundry

LS

=

Tk.

250.00

 

 

Sub - Total

=

Tk.

13,530.00

 

Profit 10.00%

=

Tk.

1,353.00

 

 

Overhead

3.50%

=

Tk.

473.55

 

 

Total

=

Tk.

15,356.55

 

Add VAT with adjustment factor 1.06383

6.00%

=

Tk.

980.21

 

 

Grand Total

=

Tk.

16,336.76

 

 

Rate per meter

=

Tk.

1,166.91

 

Say, Tk.

1,167 .00 per meter

 

 

 

Item No.

- 09.2

 

 

 

 

Auger drilling /Rotary boring including equipment and labour for cast-in-situ piling

 

 

 

 

09.2.1

600 mm dia

 

 

 

 

 

Considering executing 600 mm /24 inch dia & 30 meter long 3.0 No pile in a day.

 

 

 

 

1)

Man-Power

 

 

 

 

  1.  

Field Engineer 1 no @ Tk.

1,800.00 per day

=

Tk.

1,800.00

  1.  

Skilled technician 1 no @ Tk.

1,000.00 per day

=

Tk.

1,000.00

  1.  

Foreman/supervisor 1 no @ Tk.

800.00 per day

=

Tk.

800.00

  1.  

Pile rig operator 2 nos @ Tk.

600.00 per day

=

Tk.

1,200.00

  1.  

Helper to pile rig operator 4 nos @ Tk.

390.00 per day

=

Tk.

1,560.00

  1.  

Electrician 1 no @ Tk.

600.00 per day

=

Tk.

600.00

  1.  

Skilled labour 10 nos @ Tk.

390.00 per day

=

Tk.

3,900.00

  1.  

Ordinary labour 15 nos @ Tk.

320.00 per day

=

Tk.

4,800.00

2)

Rent in/c mobilization, demobilization, maintenance, lubricants etc.

 

 

 

 

  1.  

Hire Charge of rig set 1 no @ Tk.

75,000.00 per day

=

Tk.

75,000.00

  1.  

Hire Charge of Crane 1 no @ Tk.

50,000.00 per day

=

Tk.

50,000.00

  1.  

Hire Charge of Air Compressor 1 no @ Tk.

5,000.00 per day

=

Tk.

5,000.00

  1.  

Hire Charge of Concreting Equipment 1 no @ Tk.

5,000.00 per day

=

Tk.

5,000.00

  1.  

Hire Charge of Generator 1 no @ Tk.

5,000.00 per day

=

Tk.

5,000.00

h)

Hire Charge of excavator 1 no @ Tk.

10,000.00 per day

=

Tk.

10,000.00

i)

Hire Charge of desander 1 no @ Tk.

6,000.00 per day

=

Tk.

6,000.00