Item No.- 09.1

 

 

 

 

Drilling /Boring by wash or percussion method including equipment and labour for cast-in-situ piling

 

 

 

 

09.1.1

400 mm dia

 

 

 

 

 

Considering executing 400 mm /16 inch dia & 20 meter long 1.4 No pile in a day.

 

 

 

 

  1.  

Hire charge of rig set in/c fuel, lubricant, mobilization, demobilization, maintenance

 

 

 

 

 

and insurance coverage etc. 1 day @ Tk. 6,000.00

per day

=

Tk.

6,000.00

  1.  

Foreman/supervisor 1 no @ Tk. 800.00

per day

=

Tk.

800.00

  1.  

Skilled labour 3 nos @ Tk. 390.00

per day

=

Tk.

1,170.00

  1.  

Ordinary labour 6 nos @ Tk. 320.00

per day

=

Tk.

1,920.00

  1.  

Bentonite 30 kg/m3 @ Tk. 20.00

per kg

=

Tk.

1,506.00

  1.  

power ,water, clean & sundry

LS

=

Tk.

250.00

 

 

Sub - Total

=

Tk.

11,646.00

 

Profit

10.00%

=

Tk.

1,164.60

 

Overhead

3.50%

=

Tk.

407.61

 

 

Total

=

Tk.

13,218.21

 

Add VAT with adjustment factor 1.06383

6.00%

=

Tk.

843.72

 

 

Grand Total

=

Tk.

14,061.93

 

 

Rate per meter

=

Tk.

502.21

 

Say, Tk. 502

.00 per meter

 

 

 

09.1.2

450 mm dia

 

 

 

 

 

Considering executing 450 mm /18 inch dia & 20 meter long 1.1 No pile in a day.

 

 

 

 

  1.  

Hire charge of rig set in/c fuel, lubricant, mobilization, demobilization, maintenance

 

 

 

 

 

and insurance coverage etc. 1 day @ Tk. 6,000.00

per day

=

Tk.

6,000.00

  1.  

Foreman/supervisor 1 no @ Tk. 800.00

per day

=

Tk.

800.00

  1.  

Skilled labour 3 nos @ Tk. 390.00

per day

=

Tk.

1,170.00

  1.  

Ordinary labour 6 nos @ Tk. 320.00

per day

=

Tk.

1,920.00

  1.  

Bentonite 30 kg/m3 @ Tk. 20.00

per kg

=

Tk.

1,908.00

  1.  

power ,water, clean & sundry

LS

=

Tk.

250.00

 

 

Sub - Total

=

Tk.

12,048.00

 

Profit

10.00%

=

Tk.

1,204.80

 

Overhead

3.50%

=

Tk.

421.68

 

 

Total

=

Tk.

13,674.48

 

Add VAT with adjustment factor 1.06383

6.00%

=

Tk.

872.84

 

 

Grand Total

=

Tk.

14,547.32

 

 

Rate per meter

=

Tk.

661.24

 

Say, Tk. 661

.00 per meter

 

 

 

09.1.3

500 mm dia

 

 

 

 

 

Considering executing 500 mm /20 inch dia & 20 meter long 0.95 No pile in a day.

 

 

 

 

  1.  

Hire charge of rig set in/c fuel, lubricant, mobilization, demobilization, maintenance

 

 

 

 

 

and insurance coverage etc. 1 day @ Tk. 6,000.00

per day

=

Tk.

6,000.00

  1.  

Foreman/supervisor 1 no @ Tk. 800.00

per day

=

Tk.

800.00

  1.  

Skilled labour 3 nos @ Tk. 390.00

per day

=

Tk.

1,170.00

  1.  

Ordinary labour 6 nos @ Tk. 320.00

per day

=

Tk.

1,920.00

  1.  

Bentonite 30 kg/m3 @ Tk. 20.00

per kg

=

Tk.

2,352.00

  1.  

power ,water, clean & sundry

LS

=

Tk.

250.00

 

 

Sub - Total

=

Tk.

12,492.00

 

Profit

10.00%

=

Tk.

1,249.20

 

Overhead

3.50%

=

Tk.

437.22

 

 

Total

=

Tk.

14,178.42

 

Add VAT with adjustment factor 1.06383

6.00%

=

Tk.

905.01

 

 

Grand Total

=

Tk.

15,083.43

 

 

Rate per meter

=

Tk.

793.86

 

Say, Tk. 794

.00 per meter