Item No.- 09.1 |
|
|
|
| |
Drilling /Boring by wash or percussion method including equipment and labour for cast-in-situ piling |
|
|
|
| |
09.1.1 | 400 mm dia |
|
|
|
|
| Considering executing 400 mm /16 inch dia & 20 meter long 1.4 No pile in a day. |
|
|
|
|
Hire charge of rig set in/c fuel, lubricant, mobilization, demobilization, maintenance |
|
|
|
| |
| and insurance coverage etc. 1 day @ Tk. 6,000.00 | per day | = | Tk. | 6,000.00 |
Foreman/supervisor 1 no @ Tk. 800.00 | per day | = | Tk. | 800.00 | |
Skilled labour 3 nos @ Tk. 390.00 | per day | = | Tk. | 1,170.00 | |
Ordinary labour 6 nos @ Tk. 320.00 | per day | = | Tk. | 1,920.00 | |
Bentonite 30 kg/m3 @ Tk. 20.00 | per kg | = | Tk. | 1,506.00 | |
power ,water, clean & sundry | LS | = | Tk. | 250.00 | |
|
| Sub - Total | = | Tk. | 11,646.00 |
| Profit | 10.00% | = | Tk. | 1,164.60 |
| Overhead | 3.50% | = | Tk. | 407.61 |
|
| Total | = | Tk. | 13,218.21 |
| Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 843.72 |
|
| Grand Total | = | Tk. | 14,061.93 |
|
| Rate per meter | = | Tk. | 502.21 |
| Say, Tk. 502 | .00 per meter |
|
|
|
09.1.2 | 450 mm dia |
|
|
|
|
| Considering executing 450 mm /18 inch dia & 20 meter long 1.1 No pile in a day. |
|
|
|
|
Hire charge of rig set in/c fuel, lubricant, mobilization, demobilization, maintenance |
|
|
|
| |
| and insurance coverage etc. 1 day @ Tk. 6,000.00 | per day | = | Tk. | 6,000.00 |
Foreman/supervisor 1 no @ Tk. 800.00 | per day | = | Tk. | 800.00 | |
Skilled labour 3 nos @ Tk. 390.00 | per day | = | Tk. | 1,170.00 | |
Ordinary labour 6 nos @ Tk. 320.00 | per day | = | Tk. | 1,920.00 | |
Bentonite 30 kg/m3 @ Tk. 20.00 | per kg | = | Tk. | 1,908.00 | |
power ,water, clean & sundry | LS | = | Tk. | 250.00 | |
|
| Sub - Total | = | Tk. | 12,048.00 |
| Profit | 10.00% | = | Tk. | 1,204.80 |
| Overhead | 3.50% | = | Tk. | 421.68 |
|
| Total | = | Tk. | 13,674.48 |
| Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 872.84 |
|
| Grand Total | = | Tk. | 14,547.32 |
|
| Rate per meter | = | Tk. | 661.24 |
| Say, Tk. 661 | .00 per meter |
|
|
|
09.1.3 | 500 mm dia |
|
|
|
|
| Considering executing 500 mm /20 inch dia & 20 meter long 0.95 No pile in a day. |
|
|
|
|
Hire charge of rig set in/c fuel, lubricant, mobilization, demobilization, maintenance |
|
|
|
| |
| and insurance coverage etc. 1 day @ Tk. 6,000.00 | per day | = | Tk. | 6,000.00 |
Foreman/supervisor 1 no @ Tk. 800.00 | per day | = | Tk. | 800.00 | |
Skilled labour 3 nos @ Tk. 390.00 | per day | = | Tk. | 1,170.00 | |
Ordinary labour 6 nos @ Tk. 320.00 | per day | = | Tk. | 1,920.00 | |
Bentonite 30 kg/m3 @ Tk. 20.00 | per kg | = | Tk. | 2,352.00 | |
power ,water, clean & sundry | LS | = | Tk. | 250.00 | |
|
| Sub - Total | = | Tk. | 12,492.00 |
| Profit | 10.00% | = | Tk. | 1,249.20 |
| Overhead | 3.50% | = | Tk. | 437.22 |
|
| Total | = | Tk. | 14,178.42 |
| Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 905.01 |
|
| Grand Total | = | Tk. | 15,083.43 |
|
| Rate per meter | = | Tk. | 793.86 |
| Say, Tk. 794 | .00 per meter |
|
|
|