Item No.- 09.8 |
|
|
|
| |||||
Conducting static load test for the cast in situ / precast pile providing required scaffolding. |
|
|
|
| |||||
09.8.1 | Mobilization and demobilization of testing |
|
|
|
|
|
|
|
|
(a) | |||||||||
| equipment (5 ton) by truck | 2 | trips | @ | Tk. 1,700.00 | per trip | = | Tk. | 3,400.00 |
|
|
|
|
| Profit | 10.00% | = | Tk. | 340.00 |
|
|
|
|
| Overhead | 3.50% | = | Tk. | 119.00 |
|
|
|
|
|
| Total | = | Tk. | 3,859.00 |
|
| Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 246.32 | ||
|
|
|
|
|
| Grand Total | = | Tk. | 4,105.32 |
|
|
|
| Say, | Tk. 4,105 .00 per set per site |
|
| ||
09.8.2 | Calibration of pressure gauge |
|
|
|
|
| = | Tk. | 5,400.00 |
(b) | |||||||||
|
|
|
|
| Profit | 10.00% | = | Tk. | 540.00 |
|
|
|
|
| Overhead | 3.50% | = | Tk. | 189.00 |
|
|
|
|
|
| Total | = | Tk. | 6,129.00 |
|
| Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 391.21 | ||
|
|
|
|
|
| Grand Total | = | Tk. | 6,520.21 |
|
|
|
| Say, | Tk. 6,520 .00 per set per site |
|
| ||
09.8.3 |
|
|
|
|
|
|
|
|
|
| For 50 tonne load for 1 test | 50 | 58 | Mton | (working volume) |
|
|
|
|
|
| Sand = | 1822.9 | bags |
| Wt of sand = | 35 |
| kg/bag |
(d) | Platform making: | crib wall | per ton |
| Tk. 275.00 |
|
| Tk. | 13,750.00 |
Foreman | 2 | nos | @ | Tk. 800.00 | each | = | Tk. | 1,600.00 | |
Skilled labour | 6 | nos | @ | Tk. 390.00 | each | = | Tk. | 2,340.00 | |
Ordinary labour | 10 | nos | @ | Tk. 320.00 | each | = | Tk. | 3,200.00 | |
(c) | Hire charge of load testing equipment (joist, jacks and other necessary devices in/c charges, hydraulic fluid etc.) | 1 | test | @ | Tk. 6,000.00 | per test | = | Tk. | 6,000.00 |
(d) | Cost of empty gunny bags |
|
|
|
|
|
|
|
|
| (taking 2 times use) | 911.45 | bags | @ | Tk. 5.00 | per bag | = | Tk. | 4,557.25 |
(e) | Cost of local sand as loading |
|
|
|
|
|
|
|
|
| materials (taking 2 times use) | 911.45 | cft | @ | Tk. 450.00 | per % cft | = | Tk. | 4,101.53 |
(f) | Labour for bag filling, stitching, loading & unloading: | 1822.90 | bags | @ | Tk. 10.00 | per bag | = | Tk. | 18,229.00 |
(h) | Preparation of test result in standard form in |
|
|
|
|
|
|
|
|
| triplicate | 1 | test | @ | Tk. 6,000.00 | per test | = | Tk. | 6,000.00 |
(i) | Other incidental charge |
|
|
|
| LS | = | Tk. | 960.00 |
|
|
|
|
|
| Sub - Total | = | Tk. | 60,737.78 |
|
|
|
|
| Profit | 10.00% | = | Tk. | 6,073.78 |
|
|
|
|
| Overhead | 3.50% | = | Tk. | 2,125.82 |
|
|
|
|
|
| Total | = | Tk. | 68,937.38 |
|
| Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 4,400.26 | ||
|
|
|
|
|
| Grand Total | = | Tk. | 73,337.64 |
|
|
|
| Say, | Tk. 73,338 .00 per test |
|
|
| |
| Tk. 1,466.76 per Mton test |
| |||||||
09.8.4 |
|
|
|
|
|
|
|
|
|
| For 100 ton load for 1 No. of test | 100 | 116 | Mton | (working volume) |
|
|
|
|
|
| sand = | 3645.7 | bags |
| Wt of sand = | 35 |
| kg/bag |
(b) | Platform making: | crib wall | per ton |
| Tk. 275.00 |
|
| Tk. | 27,500.00 |
(i) | Foreman | 2 | nos | @ | Tk. 800.00 | each | = | Tk. | 1,600.00 |
(ii) | Skilled labour | 6 | nos | @ | Tk. 390.00 | each | = | Tk. | 2,340.00 |
(iii) | Ordinary labour | 12 | nos | @ | Tk. 320.00 | each | = | Tk. | 3,840.00 |
(c) | Hire charge of load testing equipment (joist, jacks and other necessary devices in/c caliberation charges, hydraulic fluid etc.) | 1 | test | @ | Tk. 6,000.00 | per test | = | Tk. | 6,000.00 |
(d) | Cost of empty gunny bags |
|
|
|
|
|
|
|
|