Prev Next
īģŋ

 

Item No.- 09.8

 

 

 

 

Conducting static load test for the cast in situ / precast pile providing required scaffolding.

 

 

 

 

09.8.1

Mobilization and demobilization of testing

 

 

 

 

 

 

 

 

(a)

 

equipment (5 ton) by truck

2

trips

@

Tk. 1,700.00

per trip

=

Tk.

3,400.00

 

 

 

 

 

Profit

10.00%

=

Tk.

340.00

 

 

 

 

 

Overhead

3.50%

=

Tk.

119.00

 

 

 

 

 

 

Total

=

Tk.

3,859.00

 

 

Add VAT with adjustment factor

1.06383

6.00%

=

Tk.

246.32

 

 

 

 

 

 

Grand Total

=

Tk.

4,105.32

 

 

 

 

Say,

Tk. 4,105 .00 per set per site

 

 

09.8.2

Calibration of pressure gauge

 

 

 

 

 

=

Tk.

5,400.00

(b)

 

 

 

 

 

Profit

10.00%

=

Tk.

540.00

 

 

 

 

 

Overhead

3.50%

=

Tk.

189.00

 

 

 

 

 

 

Total

=

Tk.

6,129.00

 

 

Add VAT with adjustment factor

1.06383

6.00%

=

Tk.

391.21

 

 

 

 

 

 

Grand Total

=

Tk.

6,520.21

 

 

 

 

Say,

Tk. 6,520 .00 per set per site

 

 

09.8.3

 

 

 

 

 

 

 

 

 

 

For 50 tonne load for 1 test

50

58

Mton

(working volume)

 

 

 

 

 

 

Sand =

1822.9

bags

 

Wt of sand =

35

 

kg/bag

(d)

Platform making:

crib wall

per ton

 

Tk. 275.00

 

 

Tk.

13,750.00

  1.  

Foreman

2

nos

@

Tk. 800.00

each

=

Tk.

1,600.00

  1.  

Skilled labour

6

nos

@

Tk. 390.00

each

=

Tk.

2,340.00

  1.  

Ordinary labour

10

nos

@

Tk. 320.00

each

=

Tk.

3,200.00

(c)

Hire charge of load testing equipment (joist, jacks and other necessary devices in/c charges, hydraulic fluid etc.)

1

test

@

Tk. 6,000.00

per test

=

Tk.

6,000.00

(d)

Cost of empty gunny bags

 

 

 

 

 

 

 

 

 

(taking 2 times use)

911.45

bags

@

Tk. 5.00

per bag

=

Tk.

4,557.25

(e)

Cost of local sand as loading

 

 

 

 

 

 

 

 

 

materials (taking 2 times use)

911.45

cft

@

Tk. 450.00

per % cft

=

Tk.

4,101.53

(f)

Labour for bag filling,

stitching, loading & unloading:

1822.90

bags

@

Tk. 10.00

per bag

=

Tk.

18,229.00

(h)

Preparation of test result in standard form in

 

 

 

 

 

 

 

 

 

triplicate

1

test

@

Tk. 6,000.00

per test

=

Tk.

6,000.00

(i)

Other incidental charge

 

 

 

 

LS

=

Tk.

960.00

 

 

 

 

 

 

Sub - Total

=

Tk.

60,737.78

 

 

 

 

 

Profit

10.00%

=

Tk.

6,073.78

 

 

 

 

 

Overhead

3.50%

=

Tk.

2,125.82

 

 

 

 

 

 

Total

=

Tk.

68,937.38

 

 

Add VAT with adjustment factor

1.06383

6.00%

=

Tk.

4,400.26

 

 

 

 

 

 

Grand Total

=

Tk.

73,337.64

 

 

 

 

Say,

Tk. 73,338 .00 per test

 

 

 

 

Tk. 1,466.76 per Mton test

 

09.8.4

 

 

 

 

 

 

 

 

 

 

For 100 ton load for 1 No. of test

100

116

Mton

(working volume)

 

 

 

 

 

 

sand =

3645.7

bags

 

Wt of sand =

35

 

kg/bag

(b)

Platform making:

crib wall

per ton

 

Tk. 275.00

 

 

Tk.

27,500.00

(i)

Foreman

2

nos

@

Tk. 800.00

each

=

Tk.

1,600.00

(ii)

Skilled labour

6

nos

@

Tk. 390.00

each

=

Tk.

2,340.00

(iii)

Ordinary labour

12

nos

@

Tk. 320.00

each

=

Tk.

3,840.00

(c)

Hire charge of load testing equipment (joist, jacks and other necessary devices in/c caliberation charges, hydraulic fluid etc.)

1

test

@

Tk. 6,000.00

per test

=

Tk.

6,000.00

(d)

Cost of empty gunny bags