Prev Next
īģŋ

 

Item No.- 09.4

Casting of cast in situ bored pile with reinforced cement concrete works (1 : 1.5 : 3) with stone chips to give a minimum cylinder crushing strength of 21 Mpa.

Considering 16" dia, 65'-0" long 2 nos pile. = 181.54 cft concrete

A. Cost of Concrete

  1. Cost of Materials 181.54 cft @

Tk.

27,502.50

per % cft

=

Tk.

49,928.04

  1. Cost for Placing Concrete 181.54 cft @

Tk.

1,199.80

per % cft

=

Tk.

2,178.12

 

 

 

 

 

Tk.

52,106.16

  1. Add wastage, overflow & increase in diameter

 

 

10%

=

Tk.

5,210.62

 

 

 

Total (A)

=

Tk.

57,316.78

 

 

 

Total (A+B)

=

Tk.

57,316.78

 

 

Profit

10.00%

=

Tk.

5,731.68

 

 

Overhead

3.50%

=

Tk.

2,006.09

 

 

 

Total

=

Tk.

65,054.55

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

4,152.42

 

 

 

Grand Total

=

Tk.

69,206.97

 

 

 

Rate per cft

=

Tk.

381.22

 

 

 

Rate per cum

=

Tk.

13,462.78

Say,

Tk.

13,463

.00 per cum

 

 

 

 

 

 

 

 

 

 

Item No.- 09.5

 

 

 

 

 

 

Providing and making point welding

 

 

 

 

 

 

Considering 1 point welding

(a) Welding charge 1 Point @

Tk.

2.50

per point

=

Tk.

2.50

 

 

Profit

10.00%

=

Tk.

0.25

 

 

Overhead

3.50%

=

Tk.

0.09

 

 

 

Total

=

Tk.

2.84

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

0.18

 

 

 

Grand Total

=

Tk.

3.02

 

 

 

Rate per Point

=

Tk.

3.02

Say,

Tk.

3

.00 per point

 

 

 

Item No.- 09.6

 

 

 

 

 

 

Providing and making joint weldingof min. 300 mm length

Considering 1 inch of welding two faces 2 1

 

inch

 

 

 

 

(a) Welding charge 1x2 2 inch @

Tk.

6.00

per inch

=

Tk.

12.00

 

 

Profit

10.00%

=

Tk.

1.20

 

 

Overhead

3.50%

=

Tk.

0.42

 

 

 

Total

=

Tk.

13.62

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

0.87

 

 

 

Grand Total

=

Tk.

14.49

Tk. 570 .00 meter of weld Say,

Tk.

14.49 per inch of two face

 

 

 

 

 

 

 

 

Item No.- 09.7

 

 

 

 

 

 

Labour for breaking head of cast-in-situ bored pile/pre-cast driven pile

 

 

 

 

 

 

Considering 1 cum of work

  1. Skilled labour 7 nos @

Tk.

390.00

each

=

Tk.

2,730.00

  1. Ordinary labour 2 nos @

Tk.

320.00

each

=

Tk.

640.00

  1. Repairing of pile head in/c materials
  2. Straightening and bending of pile bars, tools & plant, sundries etc.

 

 

LS
LS

=

=

Tk. Tk.

250.00

250.00

 

 

 

Sub - Total

=

Tk.

3,870.00

 

 

Profit

10.00%

=

Tk.

387.00

 

 

Overhead

3.50%

=

Tk.

135.45

 

 

 

Total

=

Tk.

4,392.45

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

280.37

 

 

 

Grand Total

=

Tk.

4,672.82

Say,

Tk.

4,673

.00 per cum