09.2.3 1000 mm dia

Considering executing 1000 mm /40 inch dia & 30 meter long 1.8 No pile in a day.

1) Man-Power

  1. Field Engineer 1 no @ Tk. 1,800.00 per day = Tk. 1,800.00
  2. Skilled technician 1 no @ Tk. 1,000.00 per day = Tk. 1,000.00
  3. Foreman/supervisor 1 no @ Tk. 800.00 per day = Tk. 800.00
  4. Pile rig operator 2 nos @ Tk. 600.00 per day = Tk. 1,200.00
  5. Helper to pile rig operator 4 nos @ Tk. 390.00 per day = Tk. 1,560.00
  6. Electrician 1 no @ Tk. 600.00 per day = Tk. 600.00
  7. Skilled labour 10 nos @ Tk. 390.00 per day = Tk. 3,900.00
  8. Ordinary labour 15 nos @ Tk. 320.00 per day = Tk. 4,800.00

2) Rent in/c mobilization, demobilization,
maintenance, lubricants etc.

  1. Hire Charge of rig set 1 no @ Tk. 75,000.00 per day = Tk. 75,000.00
  2. Hire Charge of Crane 1 no @ Tk. 50,000.00 per day = Tk. 50,000.00
  3. Hire Charge of Air Compressor 1 no @ Tk. 5,000.00 per day = Tk. 5,000.00
  4. Hire Charge of Concreting Equipment 1 no @ Tk. 5,000.00 per day = Tk. 5,000.00
  5. Hire Charge of Generator 1 no @ Tk. 5,000.00 per day = Tk. 5,000.00

h) Hire Charge of excavator 1 no @ Tk. 10,000.00 per day = Tk. 10,000.00

  1. Hire Charge of desander 1 no @ Tk. 6,000.00 per day = Tk. 6,000.00
  2. Hire Charge of mud silo 1 no @ Tk. 1,000.00 per day = Tk. 1,000.00
  3. Hire Charge of dump truck 1 no @ Tk. 5,000.00 per day = Tk. 5,000.00
  4. Hire Charge of Water bowser 1 no @ Tk. 5,000.00 per day = Tk. 5,000.00

3) Fuel Consumption

a) Fuel Consumption for rig set LS = Tk. 10,000.00

a) Fuel Consumption for crane, air compressor, excavator LS = Tk. 20,000.00

c) Fuel Consumption for generator, Dump truck, wheel loader, wheel bowser LS = Tk. 20,000.00

4) Bentonite 39 kg/cum @ Tk. 20.00 per kg = Tk. 19,843.20

Sub - Total = Tk. 252,503.20

Profit 10.00% = Tk. 25,250.32

Overhead 3.50% = Tk. 8,837.61

Total = Tk. 286,591.13

Add VAT with adjustment factor 1.06383 6.00% = Tk. 18,293.05

Grand Total = Tk. 304,884.18

Rate per meter = Tk. 5,646.00

Say, Tk. 5,646 .00 per meter

 

Item No.- 09.3

Removal of spoils/ mud accumulated during boring of cast in situ pile by wash or percussion method of different dia. with the help of mud pump and container set by truck.

Considering 200cft of spoils/ mud removing work.

  1. Hire charge of 3HP mud pump 1/4 day @ Tk. 600.00 per day = Tk. 150.00
  2. Hire charge of MS steel tank 1 trip @ Tk. 350.00 per trip = Tk. 350.00

(6'-6" x 10'-0" x 4'-0" 1 trip @ Tk. 1,700.00 per trip = Tk. 1,700.00

  1. Hire charge of truck
  2. Pump operator 1/4 no @ Tk. 600.00 per nos = Tk. 150.00
  3. Ordinary labour 1/2 no @ Tk. 320.00 per nos = Tk. 160.00
  4. Sundries and incidental cost LS = Tk. 100.00

Total (A+B) = Tk. 2,610.00

Profit 10.00% = Tk. 261.00

Overhead 3.50% = Tk. 91.35

Total = Tk. 2,962.35

Add VAT with adjustment factor 1.06383 6.00% = Tk. 189.09

Grand Total = Tk. 3,151.44

Rate per cft = Tk. 15.76

Rate per cum = Tk. 556.56

Say, Tk. 557 .00 per cum