12 x 40'-0" x 1'-0"= 480.00
in position as required 480.00
shutter water-proof. 480.00
| sft @ Tk. sft @ Tk. sft @ Tk. sft @ Tk. | 75.00 per sft | = | Tk. | 36,000.00 |
Total Using 16 times 10.00 per sft 1.25 per sft 2.67 per sft Total for 440 cft | = = = = = = | Tk. Tk. Tk. Tk. Tk. Tk. | 153,848.93 9,615.56 4,800.00 600.00 1,281.60 16,297.16 | ||
|
| Cost for 100 cft | = | Tk. | 3,703.90 |
D. Cost of bed preparation: |
|
|
|
|
|
Area of bed: 1 x 45'-0" x 15'-0"= 675.00 | sft |
|
|
|
|
neat cement finishing 675.00 | sft @ Tk. sft @ Tk. | 0.32 per sft 21.58 per sft | = = | Tk. Tk. | 216.00 14,566.50 |
|
| Total for 440 cft | = | Tk. | 14,782.50 |
|
| Cost for 100 cft of work | = | Tk. | 3,359.66 |
|
| Using 8 times | = | Tk. | 419.96 |
E. Polythene as separator between pile layers during casting concrete 675.00 | sft @ Tk. | 319.44 per % sft | = | Tk. | 2,156.22 |
|
| Cost for 100 cft of work | = | Tk. | 490.05 |
Abstract of cost for 100 cft of work |
|
|
| ||
|
|
| = | Tk. | 28,198.75 |
|
|
| = | Tk. | 1,199.80 |
|
|
| = | Tk. | 3,703.90 |
|
|
| = | Tk. | 419.96 |
|
|
| = | Tk. | 490.05 |
|
| Sub - Total | = | Tk. | 34,012.46 |
|
| Profit 10.00% | = | Tk. | 3,401.25 |
|
| Overhead 3.50% | = | Tk. | 1,190.44 |
|
| Total | = | Tk. | 38,604.15 |
Add VAT with adjustment factor | 1.06383 6.00% | = | Tk. | 2,464.10 | |
|
| Grand Total | = | Tk. | 41,068.25 |
|
| Rate per cft | = | Tk. | 410.68 |
|
| Rate per rft | = | Tk. | 410.68 |
|
| Rate per rm | = | Tk. | 1,347.44 |
| Say, Tk. | 1,347 .00 per meter |
|
|
|
|
|
|
|
|
|
Item No.- 09.10.3 |
|
|
|
|
|
14" x 14" Pre-cast pile with reinforced cement concrete (1 : 1.25 : 2.5) with stone chips. |
|
|
|
| |
Considering 50 rft long 14" x 14" size pile Also considering 73.5 rft long pile making work using 100 cft concrete |
|
|
|
| |
|
|
| = | Tk. | 28,198.75 |
|
|
| = | Tk. | 1,199.80 |
|
|
|
|
|
|
Volume of concrete: |
|
|
|
|
|
11 x 14" x 14" x 50'-0" = 748.61 cft (a) Cost of shuttering: |
|
|
|
|
|
|
|
|
|
|
|
Sides: 12 x 50'-0" x 1'-2"= 700.00 Add wastage 5%= 35.00 | sft sft |
|
|
|
|
= 735.00 | sft | ||||
@ 3.05 Ib per sft= 2241.75
| Ibs @ Tk. | 27.44 per Ib | = | Tk. | 61,513.62 |
Sides: 2 x 12 x 50'-0"= 1200.00 Supports: 12 x 51 x 1'-2"= 714.00 | rft rft |
|
|
|
|
= 1914.00 Add wastage 5%= 95.70 | rft rft | ||||
2009.70 | rft | ||||
@ 1.79 Ib per rft= 3597.36 | Ibs @ Tk. | 24.94 per Ib | = | Tk. | 89,718.16 |