Prev Next
īģŋ

E. Polythene as separator between pile layers

 

 

 

 

 

during casting concrete 897.75 sft @ Tk.

319.44

per % sft

=

Tk.

2,867.77

 

Cost for 100 cft of work

=

Tk.

655.22

Abstract of cost for 100 cft of work

 

 

=

Tk.

28,198.75

  1. Cost of concrete
  1. Labour, machinery, fuel and lubricants for casting

 

 

=

Tk.

1,999.67

  1. Cost of shuttering

 

 

=

Tk.

4,975.94

  1. Cost of bed preparation

 

 

=

Tk.

561.50

  1. Cost of polythene

 

 

=

Tk.

655.22

 

 

Sub - Total

=

Tk.

36,391.08

 

Profit

10.00%

=

Tk.

3,639.11

 

Overhead

3.50%

=

Tk.

1,273.69

 

 

Total

=

Tk.

41,303.88

Add VAT with adjustment factor

1.06383

6.00%

=

Tk.

2,636.42

 

 

Grand Total

=

Tk.

43,940.30

 

 

Rate per cft

=

Tk.

439.40

 

 

Rate per rft

=

Tk.

193.34

 

 

Rate per rm

=

Tk.

634.35

Say, Tk.

634

.00 per meter

 

 

 

 

 

 

 

 

 

Item No.- 09.22.3

 

 

 

 

 

Driving of 7" x 7" x 25'-0" Pre-cast Pile (micro-pile)

 

 

 

 

 

Considering 25 rft long 8 nos pile

  1. Hire charge of driving equipment in/c cost of

fuel and lubricant etc. 1 day @ Tk.

  1. Labour charge for pile carrying, lifting, shifting and driving etc. complete:

4,000.00

Per day

=

Tk.

4,000.00

  1. Rig operator 1.00 no @ Tk.

600.00

each

=

Tk.

600.00

  1. Skilled labour 3 nos @ Tk.

390.00

each

=

Tk.

1,170.00

  1. Ordinary labour 7.00 nos @ Tk.

320.00

each

=

Tk.

2,240.00

 

 

Sub - Total

=

Tk.

8,010.00

 

Profit

10.00%

=

Tk.

801.00

 

Overhead

3.50%

=

Tk.

280.35

 

 

Total

=

Tk.

9,091.35

Add VAT with adjustment factor

1.06383

6.00%

=

Tk.

580.30

 

 

Grand Total

=

Tk.

9,671.65

 

 

Rate per pile

=

Tk.

1,208.96

 

 

Rate per rft

=

Tk.

48.36

 

 

Rate per rm

=

Tk.

158.67

Say, Tk.

159

.00 per meter

 

 

 

 

 

 

 

 

 

Item No.- 09.22.4

 

 

 

 

 

Driving of 7" x 7" x 25'-0" Pre-cast Pile (micro-pile)

 

 

 

 

 

Considering 25 rft long 7 nos pile

  1. Hire charge of driving equipment in/c cost of

fuel and lubricant etc. 1 day @ Tk.

  1. Labour charge for pile carrying, lifting, shifting and driving etc. complete:

4,000.00

Per day

=

Tk.

4,000.00

  1. Rig operator 1.00 no @ Tk.

600.00

each

=

Tk.

600.00

  1. Skilled labour 3 nos @ Tk.

390.00

each

=

Tk.

1,170.00

  1. Ordinary labour 8.00 nos @ Tk.

320.00

each

=

Tk.

2,560.00

 

 

Sub - Total

=

Tk.

8,330.00

 

Profit

10.00%

=

Tk.

833.00

 

Overhead

3.50%

=

Tk.

291.55

 

 

Total

=

Tk.

9,454.55

Add VAT with adjustment factor

1.06383

6.00%

=

Tk.

603.48

 

 

Grand Total

=

Tk.

10,058.03

 

 

Rate per pile

=

Tk.

1,436.86

 

 

Rate per rft

=

Tk.

57.47

 

 

Rate per rm

=

Tk.

188.56

Say, Tk.

189

.00 per meter