E. Polythene as separator between pile layers |
|
|
|
|
|
during casting concrete 897.75 sft @ Tk. | 319.44 | per % sft | = | Tk. | 2,867.77 |
| Cost for 100 cft of work | = | Tk. | 655.22 | |
Abstract of cost for 100 cft of work |
|
| = | Tk. | 28,198.75 |
| |||||
|
|
| = | Tk. | 1,999.67 |
|
|
| = | Tk. | 4,975.94 |
|
|
| = | Tk. | 561.50 |
|
|
| = | Tk. | 655.22 |
|
| Sub - Total | = | Tk. | 36,391.08 |
| Profit | 10.00% | = | Tk. | 3,639.11 |
| Overhead | 3.50% | = | Tk. | 1,273.69 |
|
| Total | = | Tk. | 41,303.88 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 2,636.42 |
|
| Grand Total | = | Tk. | 43,940.30 |
|
| Rate per cft | = | Tk. | 439.40 |
|
| Rate per rft | = | Tk. | 193.34 |
|
| Rate per rm | = | Tk. | 634.35 |
Say, Tk. | 634 | .00 per meter |
|
|
|
|
|
|
|
|
|
Item No.- 09.22.3 |
|
|
|
|
|
Driving of 7" x 7" x 25'-0" Pre-cast Pile (micro-pile) |
|
|
|
|
|
Considering 25 rft long 8 nos pile
fuel and lubricant etc. 1 day @ Tk.
| 4,000.00 | Per day | = | Tk. | 4,000.00 |
| 600.00 | each | = | Tk. | 600.00 |
| 390.00 | each | = | Tk. | 1,170.00 |
| 320.00 | each | = | Tk. | 2,240.00 |
|
| Sub - Total | = | Tk. | 8,010.00 |
| Profit | 10.00% | = | Tk. | 801.00 |
| Overhead | 3.50% | = | Tk. | 280.35 |
|
| Total | = | Tk. | 9,091.35 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 580.30 |
|
| Grand Total | = | Tk. | 9,671.65 |
|
| Rate per pile | = | Tk. | 1,208.96 |
|
| Rate per rft | = | Tk. | 48.36 |
|
| Rate per rm | = | Tk. | 158.67 |
Say, Tk. | 159 | .00 per meter |
|
|
|
|
|
|
|
|
|
Item No.- 09.22.4 |
|
|
|
|
|
Driving of 7" x 7" x 25'-0" Pre-cast Pile (micro-pile) |
|
|
|
|
|
Considering 25 rft long 7 nos pile
fuel and lubricant etc. 1 day @ Tk.
| 4,000.00 | Per day | = | Tk. | 4,000.00 |
| 600.00 | each | = | Tk. | 600.00 |
| 390.00 | each | = | Tk. | 1,170.00 |
| 320.00 | each | = | Tk. | 2,560.00 |
|
| Sub - Total | = | Tk. | 8,330.00 |
| Profit | 10.00% | = | Tk. | 833.00 |
| Overhead | 3.50% | = | Tk. | 291.55 |
|
| Total | = | Tk. | 9,454.55 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 603.48 |
|
| Grand Total | = | Tk. | 10,058.03 |
|
| Rate per pile | = | Tk. | 1,436.86 |
|
| Rate per rft | = | Tk. | 57.47 |
|
| Rate per rm | = | Tk. | 188.56 |
Say, Tk. | 189 | .00 per meter |
|
|
|