Prev Next
īģŋ

Item No.- 09.22.5

 

 

 

 

 

 

 

 

 

 

180 mm x 180 mm Pre-stressed Pre-cast Pile with ColdConsidering 7.62 rm long 178mmx178mm size pile

-Drawn wire concrete (1:1.5:3) with Stone chips

 

 

 

 

1

Stone Chips (12mm down Graded)

 

7.56

cft

@

Tk.

165.00

per cft

=

Tk.

1,247.40

2

Sand (F.M. 2.2)

 

5.50

cft

@

Tk.

45.00

per cft

=

Tk.

247.50

3

Cement

 

2.00

bag

@

Tk.

415.00

per bag

=

Tk.

830.00

4

MS Rod (fy = 400 Mpa, Cold-Drawn Wire)

 

23.60

kg

@

Tk.

60.50

per kg

=

Tk.

1,427.80

5

20 BWG (M.S. Sheet) Pile Shoe

 

1.00

no

@

Tk.

122.24

per no

=

Tk.

122.24

6

24 No. G.I. wire

 

0.50

Kg

@

Tk.

120.00

per kg

=

Tk.

60.00

7

Steel Shuttering and Tensioning

 

29.00

sft

@

Tk.

4.11

per sft

=

Tk.

119.19

 

  1. Fromwork/Shuttering

 

 

 

 

 

 

LS

 

Tk.

350.00

 

  1. Mechnical Vibration and Tensioning

 

 

 

 

 

 

LS

 

Tk.

200.00

8

Hire charge of mixture machine including oil

 

0.12

no

@

Tk.

2,004.00

per day

=

Tk.

240.48

 

& operator

 

 

 

 

 

 

 

 

 

 

9

Hire charge of Vibrator table including Oil &

 

0.12

no

@

Tk.

996.00

per day

=

Tk.

119.52

 

Operator

 

 

 

 

 

 

 

 

 

 

10

Head Mason

 

0.08

no

@

Tk.

600.00

each

=

Tk.

48.00

11

Mason

 

0.17

no

@

Tk.

500.00

each

=

Tk.

85.00

12

Rod binder

 

0.17

no

@

Tk.

500.00

each

=

Tk.

85.00

13

Skilled Labour

 

1.00

no

@

Tk.

390.00

each

=

Tk.

390.00

14

Ordinary Labour

 

0.50

no

@

Tk.

320.00

each

=

Tk.

160.00

15

Ordinary Labour for 7 days curing & 1/8 labour par day

 

0.875

no

@

Tk.

320.00

each

=

Tk.

280.00

16

Local Carriage, Sundries, T & P, water etc.

 

1.00

no

@

Tk.

320.00

each

=

Tk.

320.00

 

 

 

 

 

 

 

 

Sub - Total

=

Tk.

6,332.13

 

 

 

 

 

 

 

Profit

10.00%

=

Tk.

633.21

 

 

 

 

 

 

 

Overhead

3.50%

=

Tk.

221.62

 

 

 

 

 

 

 

 

Total

=

Tk.

7,186.96

 

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

458.74

 

 

 

 

 

 

 

 

Grand Total

=

Tk.

7,645.70

 

 

 

 

 

 

 

 

Rate per pile

=

Tk.

305.83

 

 

 

 

 

 

 

 

Rate per rft

=

Tk.

1,003.12

 

 

 

 

 

 

 

 

Rate per rm

=

Tk.

1,003.00

 

 

 

 

 

Say,

Tk.

1,003

.00 per meter

 

 

 

 

 

 

 

 

Item No.- 09.23.1

 

 

 

 

 

 

 

 

 

 

PIT : Pile Integrity Test

 

 

 

 

 

 

 

 

 

 

 

Mobilization & demobilization

 

in/c

1st

12

piles

Tk.

20,000.00

per 100km

=

Tk.

20,000.00

 

 

 

 

 

 

 

 

Sub - Total

=

Tk.

20,000.00

 

 

 

 

 

 

 

Profit

10.00%

=

Tk.

2,000.00

 

 

 

 

 

 

 

Overhead

3.50%

=

Tk.

700.00

 

 

 

 

 

 

 

 

Total

=

Tk.

22,700.00

 

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

1,448.94

 

 

 

 

 

 

 

 

Grand Total

=

Tk.

24,148.94

 

 

 

 

 

Say,

Tk.

24,149 .00 up to 1st 12 piles

 

 

 

 

 

 

 

 

Item No.- 09.23.2

 

 

 

 

 

 

 

 

 

 

 

PIT on piles beyond

 

12

piles

 

Tk.

1,000.00

each

=

Tk.

1,000.00

 

 

 

 

 

 

 

 

Sub - Total

=

Tk.

1,000.00

 

 

 

 

 

 

 

Profit

10.00%

=

Tk.

100.00

 

 

 

 

 

 

 

Overhead

3.50%

=

Tk.

35.00

 

 

 

 

 

 

 

 

Total

=

Tk.

1,135.00

 

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

72.45

 

 

 

 

 

 

 

 

Grand Total

=

Tk.

1,207.45

 

 

 

 

 

Say,

Tk.

1,207

.00 per pile