Item No.- 11.7.6 |
|
|
|
|
|
|
| ||
Supply and making hand rail for stair case including necessary moulding |
|
|
|
|
|
|
| ||
| Considering, 1 x 9'-6" x 2.75" x 6.25"= 1.134 cft of work |
|
|
|
|
|
|
|
|
| For Burma Teak wood |
|
|
|
|
|
|
|
|
(a) | Cost of wood 1.1907 | cft | @ | Tk. | 6,500.00 | per cft | = | Tk. | 7,739.55 |
(b) | Labour for making rails |
|
|
|
|
|
|
|
|
Carpenter 0.75 | no | @ | Tk. | 600.00 | per day | = | Tk. | 450.00 | |
Carpenter helper 0.5 | no | @ | Tk. | 390.00 | per day | = | Tk. | 195.00 | |
(c) | Fitting, fixing in position in/c corner finishing |
|
|
|
|
|
|
|
|
Carpenter 0.5 | no | @ | Tk. | 600.00 | per day | = | Tk. | 300.00 | |
Carpenter helper 0.5 | no | @ | Tk. | 390.00 | per day | = | Tk. | 195.00 | |
|
|
|
|
|
| Sub - Total | = | Tk. | 8,879.55 |
|
|
|
|
| Profit | 10.00% | = | Tk. | 887.96 |
|
|
|
|
| Overhead | 3.50% | = | Tk. | 310.78 |
|
|
|
|
|
| Total | = | Tk. | 10,078.29 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 643.30 | ||
|
|
|
|
|
| Grand Total | = | Tk. | 10,721.59 |
|
|
|
|
|
| Rate per cft | = | Tk. | 9,454.66 |
|
|
|
|
|
| Rate per cum | = | Tk. | 333,891.32 |
|
|
| Say | Tk. | 333,891 | .00 per cum |
|
|
|