Prev Next


 

Item No.- 11.7.6

 

 

 

 

 

 

 

Supply and making hand rail for stair case including necessary moulding

 

 

 

 

 

 

 

 

Considering, 1 x 9'-6" x 2.75" x 6.25"= 1.134 cft of work

 

 

 

 

 

 

 

 

 

For Burma Teak wood

 

 

 

 

 

 

 

 

(a)

Cost of wood 1.1907

cft

@

Tk.

6,500.00

per cft

=

Tk.

7,739.55

(b)

Labour for making rails

 

 

 

 

 

 

 

 

  1.  

Carpenter 0.75

no

@

Tk.

600.00

per day

=

Tk.

450.00

  1.  

Carpenter helper 0.5

no

@

Tk.

390.00

per day

=

Tk.

195.00

(c)

Fitting, fixing in position in/c corner finishing

 

 

 

 

 

 

 

 

  1.  

Carpenter 0.5

no

@

Tk.

600.00

per day

=

Tk.

300.00

  1.  

Carpenter helper 0.5

no

@

Tk.

390.00

per day

=

Tk.

195.00

 

 

 

 

 

 

Sub - Total

=

Tk.

8,879.55

 

 

 

 

 

Profit

10.00%

=

Tk.

887.96

 

 

 

 

 

Overhead

3.50%

=

Tk.

310.78

 

 

 

 

 

 

Total

=

Tk.

10,078.29

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

643.30

 

 

 

 

 

 

Grand Total

=

Tk.

10,721.59

 

 

 

 

 

 

Rate per cft

=

Tk.

9,454.66

 

 

 

 

 

 

Rate per cum

=

Tk.

333,891.32

 

 

 

Say

Tk.

333,891

.00 per cum