Item No.- 15.3

 

 

 

 

Minimum 1/2" thick cement plaster (1:4) with neat cement finishing to dado (average of 1/2" on one side and 3/4" on other side).

For 3/4" thick plaster with neat cement finish on walls Considering 100 sft of work

 

 

 

 

(a)

Sand (F.M. 1.2) 7.5 cft

@ Tk. 1,400.00 per % cft

=

Tk.

105.00

(b)

Cement 2 bags

@ Tk. 395.00 per bag

=

Tk.

790.00

(c)

Labour

 

=

 

 

  1.  

Head mason 0.25 no

@ Tk. 600.00 per day

=

Tk.

150.00

  1.  

Mason 1.25 nos

@ Tk. 500.00 per day

=

Tk.

625.00

  1.  

Ordinary labour 1.25 nos

@ Tk. 320.00 per day

=

Tk.

400.00

(d)

Washing of sand, local carriage, curing, & sundries etc.

LS

=

Tk.

320.00

 

 

Sub - Total

=

Tk.

2,390.00

 

 

Profit 10.00%

=

Tk.

239.00

 

 

Overhead 3.50%

=

Tk.

83.65

 

 

Total

=

Tk.

2,712.65

 

Add VAT with adjustment

factor 1.06383 6.00%

=

Tk.

173.15

 

 

Grand Total

=

Tk.

2,885.80

 

 

Average of 1/2"[from item No. 15.2] and 3/4"

=

Tk.

2,745.43

 

 

Rate per sft

=

Tk.

27.45

 

 

Rate per sqm

=

Tk.

295.47

(i)

Ground floor

Say, Tk. 295 .00 per sqm

 

 

 

 

 

 

 

 

 

Item No.- 15.4

 

 

 

Min 1/2" thick cement plaster (1:6) to walls (average of 1/2" on one side and 3/4" on other side).

 

 

 

Considering 100 sft of work

 

 

 

A. For 1/2" thick cement plaster (1:6) to walls

 

 

 

 

(a)

Sand (F.M. 1.2) 6 cft

@ Tk. 1,400.00 per % cft

=

Tk.

84.00

(b)

Cement 0.75 bag

@ Tk. 395.00 per bag

=

Tk.

296.25

(c)

Labour

 

 

 

 

  1.  

Head mason 0.25 no

@ Tk. 600.00 per day

=

Tk.

150.00

  1.  

Mason 1.00 no

@ Tk. 500.00 per day

=

Tk.

500.00

  1.  

Ordinary labour 1.00 no

@ Tk. 320.00 per day

=

Tk.

320.00

(d)

Washing of sand, local carriage, scaffolding, curing, & sundries etc.

LS

=

Tk.

320.00

 

 

Sub - Total

=

Tk.

1,670.25

 

 

Profit 10.00%

=

Tk.

167.03

 

 

Overhead 3.50%

=

Tk.

58.46

 

 

Total

=

Tk.

1,895.74

 

Add VAT with adjustment

factor 1.06383 6.00%

=

Tk.

121.00

 

 

Grand Total

=

Tk.

2,016.74

B. For 3/4" thick cement plaster (1:6) to walls

 

 

 

 

(a)

Sand (F.M. 1.2) 8.25 cft

@ Tk. 1,400.00 per % cft

=

Tk.

115.50

(b)

Cement 1.1 bag

@ Tk. 395.00 per bag

=

Tk.

434.50

(c)

Labour

 

=

 

 

  1.  

Head mason 0.25 no

@ Tk. 600.00 per day

=

Tk.

150.00

  1.  

Mason 1.00 no

@ Tk. 500.00 per day

=

Tk.

500.00

  1.  

Ordinary labour 1.00 no

@ Tk. 320.00 per day

=

Tk.

320.00

(d)

Washing of sand, local carriage, scaffolding, curing, & sundries etc.

LS

=

Tk.

320.00

 

 

Sub - Total

=

Tk.

1,840.00

 

 

Profit 10.00%

=

Tk.

184.00

 

 

Overhead 3.50%

=

Tk.

64.40

 

 

Total

=

Tk.

2,088.40

 

Add VAT with adjustment

factor 1.06383 6.00%

=

Tk.

133.30

 

 

Grand Total

=

Tk.

2,221.70

 

 

Average of A & B

=

Tk.

2,119.22

(i)

Ground floor

Rate per sft

=

Tk.

21.19

 

 

Rate per sqm

=

Tk.

228.09

 

 

Say, Tk. 228 .00 per sqm