Item No.- 15.3 |
|
|
|
| |
Minimum 1/2" thick cement plaster (1:4) with neat cement finishing to dado (average of 1/2" on one side and 3/4" on other side). For 3/4" thick plaster with neat cement finish on walls Considering 100 sft of work |
|
|
|
| |
(a) | Sand (F.M. 1.2) 7.5 cft | @ Tk. 1,400.00 per % cft | = | Tk. | 105.00 |
(b) | Cement 2 bags | @ Tk. 395.00 per bag | = | Tk. | 790.00 |
(c) | Labour |
| = |
|
|
Head mason 0.25 no | @ Tk. 600.00 per day | = | Tk. | 150.00 | |
Mason 1.25 nos | @ Tk. 500.00 per day | = | Tk. | 625.00 | |
Ordinary labour 1.25 nos | @ Tk. 320.00 per day | = | Tk. | 400.00 | |
(d) | Washing of sand, local carriage, curing, & sundries etc. | LS | = | Tk. | 320.00 |
|
| Sub - Total | = | Tk. | 2,390.00 |
|
| Profit 10.00% | = | Tk. | 239.00 |
|
| Overhead 3.50% | = | Tk. | 83.65 |
|
| Total | = | Tk. | 2,712.65 |
| Add VAT with adjustment | factor 1.06383 6.00% | = | Tk. | 173.15 |
|
| Grand Total | = | Tk. | 2,885.80 |
|
| Average of 1/2"[from item No. 15.2] and 3/4" | = | Tk. | 2,745.43 |
|
| Rate per sft | = | Tk. | 27.45 |
|
| Rate per sqm | = | Tk. | 295.47 |
(i) | Ground floor | Say, Tk. 295 .00 per sqm |
|
|
|
|
|
|
|
|
|
Item No.- 15.4 |
|
|
| ||
Min 1/2" thick cement plaster (1:6) to walls (average of 1/2" on one side and 3/4" on other side). |
|
|
| ||
Considering 100 sft of work |
|
|
| ||
A. For 1/2" thick cement plaster (1:6) to walls |
|
|
|
| |
(a) | Sand (F.M. 1.2) 6 cft | @ Tk. 1,400.00 per % cft | = | Tk. | 84.00 |
(b) | Cement 0.75 bag | @ Tk. 395.00 per bag | = | Tk. | 296.25 |
(c) | Labour |
|
|
|
|
Head mason 0.25 no | @ Tk. 600.00 per day | = | Tk. | 150.00 | |
Mason 1.00 no | @ Tk. 500.00 per day | = | Tk. | 500.00 | |
Ordinary labour 1.00 no | @ Tk. 320.00 per day | = | Tk. | 320.00 | |
(d) | Washing of sand, local carriage, scaffolding, curing, & sundries etc. | LS | = | Tk. | 320.00 |
|
| Sub - Total | = | Tk. | 1,670.25 |
|
| Profit 10.00% | = | Tk. | 167.03 |
|
| Overhead 3.50% | = | Tk. | 58.46 |
|
| Total | = | Tk. | 1,895.74 |
| Add VAT with adjustment | factor 1.06383 6.00% | = | Tk. | 121.00 |
|
| Grand Total | = | Tk. | 2,016.74 |
B. For 3/4" thick cement plaster (1:6) to walls |
|
|
|
| |
(a) | Sand (F.M. 1.2) 8.25 cft | @ Tk. 1,400.00 per % cft | = | Tk. | 115.50 |
(b) | Cement 1.1 bag | @ Tk. 395.00 per bag | = | Tk. | 434.50 |
(c) | Labour |
| = |
|
|
Head mason 0.25 no | @ Tk. 600.00 per day | = | Tk. | 150.00 | |
Mason 1.00 no | @ Tk. 500.00 per day | = | Tk. | 500.00 | |
Ordinary labour 1.00 no | @ Tk. 320.00 per day | = | Tk. | 320.00 | |
(d) | Washing of sand, local carriage, scaffolding, curing, & sundries etc. | LS | = | Tk. | 320.00 |
|
| Sub - Total | = | Tk. | 1,840.00 |
|
| Profit 10.00% | = | Tk. | 184.00 |
|
| Overhead 3.50% | = | Tk. | 64.40 |
|
| Total | = | Tk. | 2,088.40 |
| Add VAT with adjustment | factor 1.06383 6.00% | = | Tk. | 133.30 |
|
| Grand Total | = | Tk. | 2,221.70 |
|
| Average of A & B | = | Tk. | 2,119.22 |
(i) | Ground floor | Rate per sft | = | Tk. | 21.19 |
|
| Rate per sqm | = | Tk. | 228.09 |
|
| Say, Tk. 228 .00 per sqm |
|
|
|