Item No.- 15.5 |
|
|
|
|
|
|
|
|
1/4" thick cement plaster (1:4) to ceiling, column, beams etc. and all other RCC surfaces Considering 100 sft of work |
|
|
|
| ||||
| 2.5 | cft | @ | Tk. | 1,400.00 per % cft | = | Tk. | 35.00 |
| 0.5 | bag | @ | Tk. | 395.00 per bag | = | Tk. | 197.50 |
| 0.125 0.25 | bag | @ @ | Tk. Tk. | 395.00 per bag 600.00 per day | = = | Tk. Tk. | 49.38 150.00 |
| 1.00 | no | @ | Tk. | 500.00 per day | = | Tk. | 500.00 |
| 1.00 | no | @ | Tk. | 320.00 per day | = | Tk. | 320.00 |
| 0.50 | no | @ | Tk. | 320.00 per day | = | Tk. | 160.00 |
|
|
| LS | = | Tk. | 320.00 | ||
|
|
|
|
| Sub - Total | = | Tk. | 1,731.88 |
|
|
|
|
| Profit 10.00% | = | Tk. | 173.19 |
|
|
|
|
| Overhead 3.50% | = | Tk. | 60.62 |
|
|
|
|
| Total | = | Tk. | 1,965.69 |
| Add VAT with adjustment factor |
| 1.06383 6.00% | = | Tk. | 125.47 | ||
|
|
|
|
| Grand Total | = | Tk. | 2,091.16 |
|
|
|
|
| Rate per sft | = | Tk. | 20.91 |
i) For ground floor |
|
|
|
| Rate per sqm | = | Tk. | 225.08 |
Say, | Tk. | 225 .00 per sqm |
| |||||
|
|
|
|
|
|
|
|
|
Item No.- 15.6 |
|
|
|
|
|
|
|
|
Min 1/4" thick cement plaster (1:3) to walls |
|
|
|
|
|
|
|
|
Considering 100 sft of work |
|
|
|
|
|
|
|
|
A. For 1/2" thick cement plaster (1:3) to walls (a) Sand (F.M. 1.2) | 4.7 | cft | @ | Tk. | 1,400.00 per % cft | = | Tk. | 65.80 |
(b) Cement (c) Labour
| 1.25 0.25 | bag | @ @ | Tk. Tk. | 395.00 per bag 600.00 per day | = = | Tk. Tk. | 493.75 150.00 |
| 1.00 | no | @ | Tk. | 500.00 per day | = | Tk. | 500.00 |
| 1.00 | no | @ | Tk. | 320.00 per day | = | Tk. | 320.00 |
(d) Washing of sand, local carriage, scaffolding, curing, & sundries etc. |
|
| LS | = | Tk. | 320.00 | ||
|
|
|
|
| Sub - Total | = | Tk. | 1,849.55 |
|
|
|
|
| Profit 10.00% | = | Tk. | 184.96 |
|
|
|
|
| Overhead 3.50% | = | Tk. | 64.73 |
|
|
|
|
| Total | = | Tk. | 2,099.24 |
| Add VAT with adjustment factor |
| 1.06383 6.00% | = | Tk. | 133.99 | ||
|
|
|
|
| Grand Total | = | Tk. | 2,233.23 |
B. For 1/4" thick cement plaster (1:3) to walls (a) Sand (F.M. 1.2) | 2.35 | cft | @ | Tk. | 1,400.00 per % cft | = | Tk. | 32.90 |
(b) Cement (c) Labour
| 0.625 1/4 | bag | @ @ | Tk. Tk. | 395.00 per bag 600.00 per day | = = | Tk. Tk. | 246.88 150.00 |
| 1.00 | no | @ | Tk. | 500.00 per day | = | Tk. | 500.00 |
| 1.00 | no | @ | Tk. | 320.00 per day | = | Tk. | 320.00 |
(d) Washing of sand, local carriage, scaffolding, curing, & sundries etc. |
|
| LS | = | Tk. | 320.00 | ||
|
|
|
|
| Sub - Total | = | Tk. | 1,569.78 |
|
|
|
|
| Profit 10.00% | = | Tk. | 156.98 |
|
|
|
|
| Overhead 3.50% | = | Tk. | 54.94 |
|
|
|
|
| Total | = | Tk. | 1,781.70 |
| Add VAT with adjustment factor |
| 1.06383 6.00% | = | Tk. | 113.73 | ||
|
|
|
|
| Grand Total | = | Tk. | 1,895.43 |
|
|
|
|
| Average of A & B | = | Tk. | 2,064.33 |
(i) Ground floor |
|
|
|
| Rate per sft | = | Tk. | 20.64 |
|
|
|
|
| Rate per sqm | = | Tk. | 222.17 |
|
|
| Say, | Tk. | 222 .00 per sqm |
|
|
|