Item No.- 15.16 |
|
|
|
|
|
Additional Rate for Plaster and Pointing work in additional floors |
|
|
|
|
|
15.16.1 Add for each addl. floor up to 5th floor (1/3 lab. per % sft) |
| per sqm | = | Tk. | 14.00 |
15.16.2 Add for each addl. from 6th floor to 9th floor (1/2 lab. per % sft) |
| per sqm | = | Tk. | 21.00 |
15.16.3 Add for each addl. floor above 9th floor (2/3 lab. per % sft) |
| per sqm | = | Tk. | 28.00 |
|
|
|
|
|
|
Item No.- 15.17 |
|
|
|
|
|
Precast ventilator with 1" thick cement mortar (1:2) including fitting fixing in position. |
|
|
|
|
|
Considering 6 sft of work
| 395.00 | per bag | = | Tk. | 98.75 |
| 1,400.00 | per % cft | = | Tk. | 21.00 |
| 17.55 | per sft | = | Tk. | 315.90 |
| 500.00 | per day | = | Tk. | 375.00 |
| 320.00 | per day | = | Tk. | 160.00 |
|
| Sub - Total | = | Tk. | 970.65 |
| Profit | 10.00% | = | Tk. | 97.07 |
| Overhead | 3.50% | = | Tk. | 33.97 |
|
| Total | = | Tk. | 1,101.69 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 70.32 |
|
| Grand Total | = | Tk. | 1,172.01 |
|
| Rate per sft | = | Tk. | 195.34 |
|
| Rate per sqm | = | Tk. | 2,102.64 |
Say, Tk. | 2,103 .00 per sqm |
|
|
| |
|
|
|
|
|
|
Item No.- 15.18 |
|
|
|
|
|
3" thick cornice of brick masonry (1:6) |
|
|
|
|
|
Considering 100 rft of work
& plastering 100 rft @ Tk.
and 1/2" thick cement plaster (1:6) 75 sft @ Tk. | 151.09 32.00 17.55 | per cft | = = = | Tk. | 944.31 3,200.00 1,316.25 |
|
| Sub - Total | = | Tk. | 5,460.56 |
| Profit | 10.00% | = | Tk. | 546.06 |
| Overhead | 3.50% | = | Tk. | 191.12 |
|
| Total | = | Tk. | 6,197.74 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 395.60 |
|
| Grand Total | = | Tk. | 6,593.34 |
|
| Rate per rft | = | Tk. | 65.93 |
|
| Rate per rm | = | Tk. | 216.32 |
Say, Tk. | 216 | .00 per meter |
|
|
|
|
|
|
|
|
|
Item No.- 15.19 |
|
|
|
|
|
Supplying & embedding of 19 to 32 mm height and 19 mm width broken glass placed @ app 25 mm c/c into plaster |
|
|
|
|
|
Considering 100 sft of work
(30% of cost of new glass) 95.00 sft |
|
|
|
|
|
Add 5% wastage= 4.75 sft | 12.00 | per sft | = | Tk. | 1,197.00 |
99.75 sft @ Tk. | |||||
| 500.00 | per day | = | Tk. | 250.00 |
| 390.00 | per day | = | Tk. | 195.00 |
|
| LS | = | Tk. | 75.00 |
|
| Sub - Total | = | Tk. | 1,717.00 |
| Profit | 10.00% | = | Tk. | 171.70 |
| Overhead | 3.50% | = | Tk. | 60.10 |
|
| Total | = | Tk. | 1,948.80 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 124.39 |
|
| Grand Total | = | Tk. | 2,073.19 |