(g) Hire charge of concrete mixer machine 0.10 no @ Tk. 1,200.00 each (h) Washing of sand, local carriage, scaffolding, curing, & sundries etc. LS | = = = = | Tk. Tk. Tk. Tk. | 550.00 352.00 120.00 320.00 |
Total | = | Tk. | 7,711.73 |
Profit 10.00% | = | Tk. | 771.17 |
Overhead 3.50% | = | Tk. | 269.91 |
| = | Tk. | 8,752.81 |
Add VAT with adjustment factor 1.06383 6.00% | = | Tk. | 558.69 |
Grand total | = | Tk. | 9,311.50 |
Rate per sft | = | Tk. | 93.12 |
Rate per sqm. | = | Tk. | 1,002.34 |
Say, Tk. 1,002 .00 per sqm |
|
|
|
|
|
|
|
Item No.- 17.4 |
|
|
|
Average 4" thick finished lime terracing with 3/4" down graded 1st class brick chips, surki and stone lime (7:2:2) |
|
|
|
Considering 100 cft of work (300 sft Area) |
|
|
|
(A) Cost of materials (i) 1st class bricks 820 nos @ Tk. 8,700.00 per % 0 nos | = | Tk. | 7,134.00 |
| = | Tk. | 8,629.28 |
| = | Tk. | 2,433.90 |
| = | Tk. | 916.47 |
(B) Labour cost
|
|
|
|
Total 25 nos @ Tk. 320.00 each | = | Tk. | 8,000.00 |
| = | Tk. | 600.00 |
| = | Tk. | 1,000.00 |
C. Miscellaneous
| = | Tk. | 400.00 |
| = | Tk. | 320.00 |
| = | Tk. | 640.00 |
| = | Tk. | 801.00 |
Sub - Total | = | Tk. | 30,874.65 |
Profit 10.00% | = | Tk. | 3,087.47 |
Overhead 3.50% | = | Tk. | 1,080.61 |
Total | = | Tk. | 35,042.73 |
Add VAT with adjustment factor 1.06383 6.00% | = | Tk. | 2,236.77 |
Grand Total | = | Tk. | 37,279.50 |
Rate per cft | = | Tk. | 372.80 |
Rate per cum | = | Tk. | 13,165.43 |
Say, Tk. 13,165 .00 per cum |
|
|
|
|
|
|
|
IItem No.- 17.4.1 |
|
|
|
Extra rate for lime terracing work in additional floor: |
|
|
|
17.4.1.1 Add for each addl. floor up to 5th floor: @ 0.75 nos lab per % cft per cum | = | Tk. | 102.00 |
17.4.1.2 Add for each addl. floor from 6th floor to 9th floor: @ 1 nos lab per % cft per cum | = | Tk. | 136.00 |
17.4.1.3 Add for each addl. floor for 10th floor & above: @ 1.25 nos lab. per % cft per cum | = | Tk. | 171.00 |
|
|
|
|
Item No.-17.5.1 |
|
|
|
Ferrocement Treatment of Roof for Water Proofing |
|
|
|
Considering 100 sft of work 1 Stone chips- 12mm down graded 11.00 cft @ Tk. 16,500.00 per % cft | = | Tk. | 1,815.00 |
2 Sand (F.M. 1.2) 3.00 cft @ Tk. 1,400.00 per % cft | = | Tk. | 42.00 |