Prev Next
īģŋ

  1. Mason 1.10 no @ Tk. 500.00 each
  2. Ordinary labour 1.10 no @ Tk. 320.00 each

(g) Hire charge of concrete mixer machine 0.10 no @ Tk. 1,200.00 each

(h) Washing of sand, local carriage, scaffolding, curing, & sundries etc. LS

= = = =

Tk. Tk. Tk. Tk.

550.00 352.00 120.00 320.00

Total

=

Tk.

7,711.73

Profit 10.00%

=

Tk.

771.17

Overhead 3.50%

=

Tk.

269.91

 

=

Tk.

8,752.81

Add VAT with adjustment factor 1.06383 6.00%

=

Tk.

558.69

Grand total

=

Tk.

9,311.50

Rate per sft

=

Tk.

93.12

Rate per sqm.

=

Tk.

1,002.34

Say, Tk. 1,002 .00 per sqm

 

 

 

 

 

 

 

Item No.- 17.4

 

 

 

Average 4" thick finished lime terracing with 3/4" down graded 1st class brick chips, surki and stone lime (7:2:2)

 

 

 

Considering 100 cft of work (300 sft Area)

 

 

 

(A) Cost of materials

(i) 1st class bricks 820 nos @ Tk. 8,700.00 per % 0 nos

=

Tk.

7,134.00

  1. Stone lime 539.33 kg @ Tk. 16.00 per kg

=

Tk.

8,629.28

  1. 1st class surki 34.77 cft @ Tk. 70.00 per cft

=

Tk.

2,433.90

  1. Cost for breaking chips 96.47 cft @ Tk. 950.00 per % cft

=

Tk.

916.47

(B) Labour cost

  1. Labour for slacking lime 1 no
  2. Labour for dry mixing 2 nos
  3. Labour for wet mixing 6 nos
  4. Labour for lifting and casting 3 nos
  5. Labour for beating 12 nos
  6. Labour for finishing 1 no

 

 

 

Total 25 nos @ Tk. 320.00 each

=

Tk.

8,000.00

  1. Head Mason 1 no @ Tk. 600.00 each

=

Tk.

600.00

  1. Mason for finishing (300 sft) 2 nos @ Tk. 500.00 each

=

Tk.

1,000.00

C. Miscellaneous

  1. Expenditure for making platform: soling excluding cost of bricks LS

=

Tk.

400.00

  1. Expenditure for providing polythene cover LS

=

Tk.

320.00

  1. Local carriage, storage, tools & plants, gumboot, koppa etc. LS

=

Tk.

640.00

  1. Curing 300 sft @ Tk. 2.67 LS

=

Tk.

801.00

Sub - Total

=

Tk.

30,874.65

Profit 10.00%

=

Tk.

3,087.47

Overhead 3.50%

=

Tk.

1,080.61

Total

=

Tk.

35,042.73

Add VAT with adjustment factor 1.06383 6.00%

=

Tk.

2,236.77

Grand Total

=

Tk.

37,279.50

Rate per cft

=

Tk.

372.80

Rate per cum

=

Tk.

13,165.43

Say, Tk. 13,165 .00 per cum

 

 

 

 

 

 

 

IItem No.- 17.4.1

 

 

 

Extra rate for lime terracing work in additional floor:

 

 

 

17.4.1.1 Add for each addl. floor up to 5th floor: @ 0.75 nos lab per % cft per cum

=

Tk.

102.00

17.4.1.2 Add for each addl. floor from 6th floor to 9th floor: @ 1 nos lab per % cft per cum

=

Tk.

136.00

17.4.1.3 Add for each addl. floor for 10th floor & above: @ 1.25 nos lab. per % cft per cum

=

Tk.

171.00

 

 

 

 

Item No.-17.5.1

 

 

 

Ferrocement Treatment of Roof for Water Proofing

 

 

 

Considering 100 sft of work

1 Stone chips- 12mm down graded 11.00 cft @ Tk. 16,500.00 per % cft

=

Tk.

1,815.00

2 Sand (F.M. 1.2) 3.00 cft @ Tk. 1,400.00 per % cft

=

Tk.

42.00