3 Sand (F.M. 2.2) 4 Cement 5 20 BWG galvanized wire mesh 2 mesh per 25mm 6 Wire Nail 7 24 No. G.I. wire 8 Head Mason 9 Mason 10 Skilled Labour 11 Ordinary Labour | 16.00 5.50 120.00 0.50 0.50 0.25 0.50 1.00 2.00 | cft bags sft kg kg no no no nos | @ @ @ @ @ @ @ @ @ | Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. | 4,500.00 415.00 25.00 90.00 120.00 600.00 500.00 390.00 320.00 | per % cft per bag per sft per kg per kg each each each each | = = = = = = = = = | Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. | 720.00 2,282.50 3,000.00 45.00 60.00 150.00 250.00 390.00 640.00 |
12 Ordinary Labour for 7 days curing & 1/8 labour par day | 0.88 | no | @ | Tk. | 320.00 | each | = | Tk. | 281.60 |
13 Local Carriage, Sundries, T & P, water etc. | 0.20 | no | @ | Tk. | 320.00 | each | = | Tk. | 64.00 |
|
|
|
|
|
| Sub - Total | = | Tk. | 9,740.10 |
|
|
|
|
| Profit | 10.00% | = | Tk. | 974.01 |
|
|
|
|
| Overhead | 3.50% | = | Tk. | 340.90 |
|
|
|
|
|
| Total | = | Tk. | 11,055.01 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 705.64 | |||
|
|
|
|
|
| Grand Total | = | Tk. | 11,760.65 |
|
|
|
|
|
| Rate per sft | = | Tk. | 117.61 |
|
|
|
|
|
| Rate per sqm | = | Tk. | 1,265.48 |
|
|
| Say, | Tk. | 1,265 .00 per sqm |
|
|
| |
|
|
|
|
|
|
|
|
|
|
Item No.17.5.2 |
|
|
|
|
|
|
|
| |
Ferrocement Treatment of Roof for Heat & Water Proofing |
|
|
|
|
|
|
|
| |
Considering 100 sft of work |
|
|
|
|
|
|
|
|
|
1 Stone chips (12mm down graded) | 11.00 | cft | @ | Tk. | 16,500.00 | per % cft | = |
| 1,815.00 |
2 Sand (F.M. 1.2) | 3.00 | cft | @ | Tk. | 1,400.00 | per % cft | = |
| 42.00 |
3 Sand (F.M. 2.2) | 19.00 | cft | @ | Tk. | 4,500.00 | per % cft | = |
| 855.00 |
4 Cement | 6.50 | bags | @ | Tk. | 415.00 | per bag | = |
| 2,697.50 |
5 EPS sheet (62mm thick) density 15 kg per | 20.00 | cft | @ | Tk. | 90.00 | per cft | = |
| 1,800.00 |
cum 6 20 BWG galvanized wire mesh 2 mesh per | 120.00 | sft | @ | Tk. | 25.00 | per sft | = |
| 3,000.00 |
25mm |
|
|
|
|
|
|
|
|
|
7 Wire Nail | 0.50 | kg | @ | Tk. | 90.00 | per kg | = |
| 45.00 |
8 24 No. G.I. wire | 0.50 | kg | @ | Tk. | 120.00 | per kg | = |
| 60.00 |
9 Head Mason | 0.25 | no | @ | Tk. | 600.00 | each | = |
| 150.00 |
10 Mason | 1.00 | no | @ | Tk. | 500.00 | each | = |
| 500.00 |
11 Skilled Labour | 1.00 | no | @ | Tk. | 390.00 | each | = |
| 390.00 |
12 Ordinary Labour | 2.00 | nos | @ | Tk. | 320.00 | each | = |
| 640.00 |
13 Ordinary Labour for 7 days curing & 1/8 labour par day | 0.875 | no | @ | Tk. | 320.00 | each | = |
| 280.00 |
14 Local Carriage, Sundries, T & P, water etc. | 0.20 | no | @ | Tk. | 320.00 | each | = |
| 64.00 |
|
|
|
|
|
| Sub - Total | = | Tk. | 12,338.50 |
|
|
|
|
| Profit | 10.00% | = | Tk. | 1,233.85 |
|
|
|
|
| Overhead | 3.50% | = | Tk. | 431.85 |
|
|
|
|
|
| Total | = | Tk. | 14,004.20 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 893.89 | |||
|
|
|
|
|
| Grand Total | = | Tk. | 14,898.09 |
|
|
|
|
|
| Rate per sft | = | Tk. | 148.98 |
|
|
|
|
|
| Rate per sqm | = | Tk. | 1,603.02 |
|
|
| Say, | Tk. | 1,603 .00 per sqm |
|
|
| |