Add VAT with adjustment factor 1.06383 6.00% = Tk. 6,251.79 |
Grand Total = Tk. 104,196.45 Rate per sft = Tk. 1,628.07 Rate per sqm = Tk. 17,524.55 |
Say, Tk. 17,525 .00 per sqm |
|
Item No.- 19.1.2 |
Manufacturing, supplying, fitting and fixing collapsible gate of any design and shape made of 20 x 20 x 3 mm S.S. angle placed @ 112 mm c/c vertically and connecting the same with each other by 20 x 3 mm S.S flat bar scissors Considering 1 No. collapsible gate Considering 8'-0" x 8'-0"= 64.00 sft in two parts a) Cost of materials
2 x 12 x 2 x 8'-6"= 384 rft Add wastage 5%= 19.2 rft |
= 403.2 rft @ Tk. 80.00 per Ib = Tk. 32,256.00
2 x 9 x 2 x 3 x 2'-0"= 216.00 rft 2 x 2 x 2 x 3 x 1'-9"= 42.00 rft |
= 258.00 rft Add wastage 5%= 12.90 rft |
= 270.90 rft @ Tk. 45.00 per rft = Tk. 12,190.50
4 x 8'-6"= 34 rft 2 x 2 x 0'-6"= 2 rft |
36 rft Add wastage 5%= 1.8 rft |
= 37.8 rft @ Tk. 200.00 per rft = Tk. 7,560.00 b) Hardwares, fittings and consumables:
v) Electrodes 70 pcs @ Tk. 10.00 per pc = Tk. 700.00
c) Making gate in work-shop
d) Carrying cost: materials & finished gate. LS = Tk. 150.00 |
Sub-total = Tk. 62,070.50 e) Workshop charge 10% = Tk. 6,207.05 |
Sub-Total = Tk. 68,277.55 f) Anciliary work for fitting-fixing the gate:
1 x 8'-0"= 8.00 rft @ Tk. 19.50 per rft = Tk. 156.00
14 x 6" x 4" x 4"= 1.00 cft (say) @ Tk. 17,763.63 per % cft = Tk. 177.64
3 x 8'-0" x 1'-0"= 24.00 sft @ Tk. 1,755.00 per % sft = Tk. 421.20
1 x 8'-0" x 1'-6"= 12.00 sft @ Tk. 2,158.00 per % sft = Tk. 258.96 g) Labour for fitting-fixing the gate: |