Prev Next
īģŋ

 

  1. Mason 0.5
  2. Skilled labour 0.5

no
no

@

@

Tk. 500.00

Tk. 390.00

Contractor's profit Overhead expenses

per day
per day

=

=

Tk. Tk.

250.00

195.00

Sub - Total

10.00%

3.50%

=

=

=

Tk.
Tk.
Tk.

70,009.35

7,000.94

2,450.33

Total

=

Tk.

79,460.62

 

add VAT with adjustment factor

 

1.06383

 

6.00%

=

Tk.

5,071.96

 

 

 

 

 

 

Grand Total

=

Tk.

84,532.58

 

 

 

 

 

 

Rate per sft

=

Tk.

1,320.82

 

 

 

 

 

 

Rate per sqm

=

Tk.

14,217.31

 

 

 

Say, Tk.

14,217 .00 per sqm

 

 

 

 

 

 

 

 

Item No.- 19.1.3

 

 

 

Manufacturing, supplying, fitting and fixing of collapsible gate with 25 x 25 x 3 mm M.S. angle excluding cost of paint.

 

 

 

 

Considering 1 No. collapsible gate

 

 

 

 

 

 

 

 

 

Considering 8'-0" x 8'-0"= 64.00 sft in two parts

 

 

 

 

 

 

 

 

(a)

Cost of materials

 

 

 

 

 

 

 

 

(i)

1" x 1" x 1/8" angle: @ 0.8 Ibs per rft

2 x 12 x 2 x 8'-6"= 384

Add wastage 5%= 19.2

rft
rft

 

 

 

 

 

 

 

= 403.2

rft

 

= 322.56

Ibs

@

Tk.

24.94

per Ib

=

Tk.

8,044.65

(ii)

1" x 1/8" M.S. flat bar diagonals at 3 levels of length

 

 

 

 

 

 

 

 

 

1'-0" to 2'-0": @ 0.43 Ibs per rft

2 x 9 x 2 x 3 x 2'-0"= 216.00

2 x 2 x 2 x 3 x 1'-9"= 42.00

rft
rft

 

 

 

 

 

 

 

= 258.00

Add wastage 5%= 12.90

rft
rft

= 270.90

rft

 

= 116.49

Ibs

@

Tk.

24.94

per Ib

=

Tk.

2,905.26

(iii)

2" x 1/4" F.I. bar to make Tee (top & bottom rail) and locking arrangement: @ 1.70 Ibs per rft

4 x 8'-6"= 34

2 x 2 x 0'-6"= 2

rft
rft

 

 

 

 

 

 

 

36

Add wastage 5%= 1.8

rft
rft

= 37.8

rft

 

= 64.26

Ibs

@

Tk.

24.94

per Ib

=

Tk.

1,602.64

(b)

Hardwares, fittings and consumables:

 

 

 

 

 

 

 

 

  1.  

Rivet and washer 3.00

kg

@

Tk.

90.00

per kg

=

Tk.

270.00

  1.  

1.5" dia M.S. wheel 6.00

nos

@

Tk.

28.00

each

=

Tk.

168.00

  1.  

M.S. clamp: 10

nos

@

Tk.

30.00

each

=

Tk.

300.00

  1.  

Locking arrangement 2

pairs

@

Tk.

275.00

each pair

=

Tk.

550.00

  1.  

Handle with 5/8" dia M.S rod 4

nos

@

Tk.

137.50

each

=

Tk.

550.00

  1.  

Electrodes 70

pcs

@

Tk.

10.00

per pc

=

Tk.

700.00

  1.  

Greese 0.5

Ibs

@

Tk.

56.00

per Ib

=

Tk.

28.00

(c)

Making gate in work-shop

 

 

 

 

 

 

 

 

  1.  

Welder/ fabricator 5

nos

@

Tk.

600.00

per day

=

Tk.

3,000.00

  1.  

Helper to welder 5

nos

@

Tk.

390.00

per day

=

Tk.

1,950.00

  1.  

Ordinary labour 5

nos

@

Tk.

320.00

per day

=

Tk.

1,600.00

(d)

Carrying cost: materials & finished gate.

 

 

 

 

LS

=

Tk.

480.00

 

 

 

 

 

 

Sub-total

=

Tk.

22,148.55

(e)

Workshop charge

 

 

 

 

10%

=

Tk.

2,214.86

 

 

 

 

 

 

Total

=

Tk.

24,363.41

(f)

Anciliary work for fitting-fixing the gate:

 

 

 

 

 

 

 

 

  1.  

Making holes 14.00

nos

@

Tk.

19.50

each

=

Tk.

273.00

  1.  

Making groove (channel) on floor:

 

 

 

 

 

 

 

 

 

1 x 8'-0"= 8.00

rft

@

Tk.

19.50

per rft

=

Tk.

156.00

  1.  

Cost of CC (1:2:4):

 

 

 

 

 

 

 

 

 

14 x 6" x 4" x 4"= 1.00

cft (say)

@

Tk.

17,763.63

per % cft

=

Tk.

177.64