Prev Next
īģŋ

  1.  

1/2" thick plaster (1:4)

 

 

 

 

 

 

 

 

 

 

3 x 8'-0" x 1'-0"=

24.00

sft

@

Tk.

1,755.00

per % sft

=

Tk.

421.20

  1.  

Repairing floor and plaster with neat cement finish:

 

 

 

 

 

 

 

 

 

1 x 8'-0" x 1'-6"=

12.00

sft

@

Tk.

2,158.00

per % sft

=

Tk.

258.96

(g)

Labour for fitting-fixing the gate:

 

 

 

 

 

 

 

 

 

  1.  

Mason

0.5

no

@

Tk.

500.00

per day

=

Tk.

250.00

  1.  

Skilled labour

0.5

no

@

Tk.

390.00

per day

=

Tk.

195.00

 

 

 

 

 

 

 

Sub - Total

=

Tk.

26,095.21

 

 

 

 

 

 

Profit

10.00%

=

Tk.

2,609.52

 

 

 

 

 

 

Overhead

3.50%

=

Tk.

913.33

 

 

 

 

 

 

 

Total

=

Tk.

29,618.06

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

1,890.51

 

 

 

 

 

 

 

Grand Total

=

Tk.

31,508.57

 

 

 

 

 

 

 

Rate per sft

=

Tk.

492.32

 

 

 

 

 

 

 

Rate per sqm

=

Tk.

5,299.33

 

 

 

 

Say,

Tk.

5,299 .00 per sqm

 

 

 

 

 

 

 

 

Item No.- 19.1.4

 

 

 

Manufacturing, supplying, fitting and fixing of collapsible gate with 20x20x3 mm M.S. angle excluding cost of paint.

 

 

 

 

Considering 1 No. collapsible gate

 

 

 

 

 

 

 

 

 

 

Considering 8'-0" x 8'-0"= 64.00 sft in two parts

 

 

 

 

 

 

 

 

 

(a)

Cost of materials

 

 

 

 

 

 

 

 

 

  1.  

3/4" x 3/4" x 1/8" angle: @ 0.585 Ibs per rft

 

 

 

 

 

 

 

 

 

 

2 x 12 x 2 x 8'-6"=

384

rft

 

 

 

 

 

 

 

 

Add wastage 5%=

19.2

rft

 

 

 

 

 

 

 

 

=

403.2

rft

 

 

 

 

 

 

 

 

=

235.872

Ibs

@

Tk.

24.94

per Ib

=

Tk.

5,882.65

  1.  

3/4" x 1/8" M.S. flat bar diagonals at 3 levels of length

 

 

 

 

 

 

 

 

 

1'-0" to 2'-0": @ 0.32 Ibs per rft

 

 

 

 

 

 

 

 

 

2 x 9 x 2 x 3 x 2'-0"=

216.00

rft

 

 

 

 

 

 

 

 

2 x 2 x 2 x 3 x 1'-9"=

42.00

rft

 

 

 

 

 

 

 

 

=

258.00

rft

 

 

 

 

 

 

 

 

Add wastage 5%=

12.90

rft

 

 

 

 

 

 

 

 

=

270.90

rft

 

 

 

 

 

 

 

 

=

86.69

Ibs

@

Tk.

24.94

per Ib

=

Tk.

2,162.05

  1.  

2" x 1/4" F.I. bar to make Tee (top & bottom rail) and locking arrangement: @ 1.70 Ibs per rft

 

 

 

 

 

 

 

 

 

 

4 x 8'-6"=

34

rft

 

 

 

 

 

 

 

 

2 x 2 x 0'-6"=

2

rft

 

 

 

 

 

 

 

 

 

36

rft

 

 

 

 

 

 

 

 

Add wastage 5%=

1.8

rft

 

 

 

 

 

 

 

 

=

37.8

rft

 

 

 

 

 

 

 

 

=

64.26

Ibs

@

Tk.

24.94

per Ib

=

Tk.

1,602.64

(b)

Hardwares, fittings and consumables:

 

 

 

 

 

 

 

 

 

  1.  

Rivet and washer

2.50

kg

@

Tk.

90.00

per kg

=

Tk.

225.00

  1.  

1.5" dia M.S. wheel

6.00

nos

@

Tk.

28.00

each

=

Tk.

168.00

  1.  

M.S. clamp:

10

nos

@

Tk.

30.00

each

=

Tk.

300.00

  1.  

Locking arrangement

2

pairs

@

Tk.

275.00

each pair

=

Tk.

550.00

  1.  

Handle with 5/8" dia M.S rod

4

nos

@

Tk.

137.50

each

=

Tk.

550.00

  1.  

Electrodes

70

pcs

@

Tk.

10.00

per pc

=

Tk.

700.00

  1.  

Greese

0.5

Ib.

@

Tk.

56.00

per Ib

=

Tk.

28.00

(c)

Making gate in work-shop

 

 

 

 

 

 

 

 

 

  1.  

Welder/ fabricator

4.5

nos

@

Tk.

600.00

per day

=

Tk.

2,700.00

  1.  

Helper to welder

4.5

nos

@

Tk.

390.00

per day

=

Tk.

1,755.00

  1.  

Ordinary labour

4.5

nos

@

Tk.

320.00

per day

=

Tk.

1,440.00

(d)

Carrying cost: materials & finished gate.

 

 

 

 

 

LS

=

Tk.

480.00

 

 

 

 

 

 

 

Sub-total

=

Tk.

18,543.34

(e)

Workshop charge

 

 

 

 

 

10%

=

Tk.

1,854.33

 

 

 

 

 

 

 

Sub Total

=

Tk.

20,397.67

(f)

Anciliary work for fitting-fixing the gate: