82.34 sft (a) Materials:
1 x 18'-6" = 18.50 rft 2 x 1'-9" = 3.5 rft |
= 22.00 rft Add wastage 5%= 1.10 rft |
= 23.10 rft @ Tk. 197.00 per rft = Tk. 4,550.70
5 x 18'-6" = 92.50 rft 2 x 5 x 1'-9" = 17.50 rft |
= 110.00 rft Add wastage 5%= 5.50 rft |
= 115.50 rft @ Tk. 68.00 per rft = Tk. 7,854.00
5 x 1 x 3'-10" = 31.67 rft 1 x 18'-6" = 18.50 rft 2 x 1'-6" = 3.00 rft 5 x 2 x 3'-2" = 6.67 rft |
59.84 rft Add wastage 5%= 2.99 rft |
62.83 rft @ Tk. 60.00 rft = Tk. 3,769.80
welding, bending, making box 82.34 sft @ Tk. 500.00 sft = Tk. 41,170.00
|
Sub - Total = Tk. 65,050.78 Profit 10.00% = Tk. 6,505.08 Overhead 3.50% = Tk. 2,276.78 |
Total = Tk. 73,832.64 Add VAT with adjustment factor 1.06383 6.00% = Tk. 4,712.72 |
Grand Total = Tk. 78,545.36 Rate per sft = Tk. 953.91 Rate per sqm = Tk. 10,267.89 |
Say, Tk. 10,268 .00 per sqm |
|
Item No.- 20.7 |
Supplying, fitting and fixing 10mm thick tempered glass stair as per drawing, design and specification etc all complete in all respect accepted by Engineer in charge. Considering: 17'-0" x 3'-6" =59.50 sft (a) Cost related to SS part |
1. Cost of SS materials a) 62 mm dia SS pipe 1 x 17'-0" = 17.00 rft Add 5% wastage 0.85 rft |
= 17.85 rft @ Tk. 248.00 per rft = Tk. 4,426.80
holder 5 nos @ Tk. 150.00 each = Tk. 750.00
2 Fabrication and making post of railing support etc.
3 Scaffolding 100.00 sft @ Tk. 9.00 per sft = Tk. 900.00 4 Welding Rod(Electrode) 60.00 nos @ Tk. 10.00 each = Tk. 600.00 5 Argon gas, Filler rod, Tungsten rod Gardening disk electricity, woven mop 240 GRT etc LS = Tk. 3,500.00 |