Sub-total 'A' (b) Cost related to Tempered Glass part 1 (i) Cost of 10mm thick Tempered glass in/c. 10% wastage 65.45 sft @ Tk. 280.00 per sft | = = | Tk. Tk. | 20,052.80 18,326.00 |
ii) Glass hole 16 nos @ Tk. 25.00 each | = | Tk. | 400.00 |
(iii) Spider knob 16 nos @ Tk. 150.00 each | = | Tk. | 2,400.00 |
2 fitting Fixing of glass |
|
|
|
3 a) Skilled Technician 0.5 nos @ Tk. 1,000.00 per day | = | Tk. | 500.00 |
| = | Tk. | 300.00 |
| = | Tk. | 320.00 |
4 Polishing work 10% of 'A' | = | Tk. | 2,005.28 |
5 Carring of Materials from market to work shop and workshop to site LS | = | Tk. | 500.00 |
Sub-total 'B' | = | Tk. | 24,751.28 |
Sub-Total (A+B) | = | Tk. | 44,804.08 |
Profit 10.00% | = | Tk. | 4,480.41 |
Overhead 3.50% | = | Tk. | 1,568.14 |
Total | = | Tk. | 50,852.63 |
Add VAT with adjustment factor 1.0638 6.00% | = | Tk. | 3,245.82 |
Grand Total | = | Tk. | 54,098.45 |
Rate per sft | = | Tk. | 909.22 |
Rate per sqm | = | Tk. | 9,786.84 |
Say, Tk. 9,787 .00 per sqm |
|
|
|
|
|
|
|
Item No.- 20.8 |
|
|
|
Supplying, fitting and fixing 10mm thick Tempered glass Railing in verandah as per drawing, design and specification etc all complete in all respect accepted by Engineer in charge. |
|
|
|
Considering: 19'-0"x3'-6" =66.5 sft (a) Cost related to SS work Part |
|
|
|
1. Cost of pipe
|
|
|
|
1 x 20'-0" = 20.00 rft |
|
|
|
Add 5% wastage = 1.00 rft |
|
|
|
= 21.00 rft @ Tk. 248.00 per rft | = | Tk. | 5,208.00 |
| = | Tk. | 10,800.00 |
holder 10 nos @ Tk. 150.00 each
| = | Tk. | 1,500.00 |
| = | Tk. | 2,000.00 |
| = | Tk. | 2,000.00 |
2 Fabrication and making post of railing support etc.
| = | Tk. | 780.00 |
| = | Tk. | 1,014.00 |
| = | Tk. | 832.00 |
3 Scaffolding 100.00 sft @ Tk. 9.00 per sft | = | Tk. | 900.00 |
4 Welding Rod(Electrode) 60.00 nos @ Tk. 10.00 each | = | Tk. | 600.00 |
5 Argon gas, Filler rod, Tungsten rod Gardening disk electricity, woven mop 240 GRT etc LS |
| Tk. | 3,500.00 |
Sub-total 'A' (b) Cost related to glass work part | = | Tk. | 29,134.00 |
1 (i) Cost of 10mm thick Tempered glass in/c. 10% wastage 73.15 sft @ Tk. 280.00 per sft | = | Tk. | 20,482.00 |
ii) Glass hole 16 pcs @ Tk. 25.00 each | = | Tk. | 400.00 |
iii)Spider knob 36 pcs @ Tk. 150.00 each | = | Tk. | 5,400.00 |
2 fitting Fixing of glass |
|
|
|
3 a) Skilled Technician 0.5 No. @ Tk. 1,000.00 each | = | Tk. | 500.00 |
| = | Tk. | 300.00 |
| = | Tk. | 320.00 |
4 Polishing work 10% of 'A' on Tk. 26627.46 | = | Tk. | 2,913.40 |
5 Carring of Materials from market to work shop and workshop to site LS | = | Tk. | 500.00 |
Sub-total 'B' | = | Tk. | 30,815.40 |
Sub-Total (A+B) | = | Tk. | 59,949.40 |
Profit 10.00% | = | Tk. | 5,994.94 |
Overhead 3.50% | = | Tk. | 2,098.23 |