Add VAT with adjustment factor 1.06383 6.00%

= Tk. 9,875.07

= Tk. 630.32

Grand Total Rate per No.

= Tk. 10,505.39

= Tk. 10,505.39

Say, Tk. 10,505 .00 each

 

26.3.1.3

Special coloured combicloset Special coloured (Deep Blue/ Ruby/ Rain Forest/ Green), 670 x 365 x 755 mm,31.0 kg or equivalent or equivalent

 

 

Considering 1 No. of fixture

1.

Special coloured combicloset: 1 no @ Tk. 9,060.00 each

= Tk. 9,060.00

2

Fitting fixing materials:

 

(a)

Cement mortar (1:4)

 

  1.  

Cement 0.1 bag @ Tk. 395.00 per bag

= Tk. 39.50

  1.  

Sand (F.M. 1.2) 0.5 cft @ Tk. 1,400.00 per % cft

= Tk. 7.00

(b)

Nuts with washer 4 nos @ Tk. 26.00 each

= Tk. 104.00

4.

Labour:

 

  1.  

Plumber 0.25 no @ Tk. 600.00 each

= Tk. 150.00

  1.  

Skilled labour 1 no @ Tk. 390.00 each

= Tk. 390.00

  1.  

Ordinary labour 0.5 no @ Tk. 320.00 each

= Tk. 160.00

 

Sub - Total

= Tk. 9,910.50

 

Profit 10.00%

= Tk. 991.05

 

Overhead 3.50%

= Tk. 346.87

 

Total

= Tk. 11,248.42

 

Add VAT with adjustment factor 1.06383 6.00%

= Tk. 717.98

 

Grand Total

= Tk. 11,966.40

 

Rate per No.

= Tk. 11,966.40

 

Say, Tk. 11,966 .00 each

 

26.3.2.1

Light colour (Ivory/ Alpine White/ Grey/ Pink/ Blue/ Aqua Verde), 700x370x795mm, 32.5kg or Equivalent

 

 

Considering 1 No. of fixture

 

1.

White Combicloset 1 no @ Tk. 7,130.00 each

= Tk. 7,130.00

2

Fitting fixing materials:

 

(a)

Cement mortar (1:4)

 

  1.  

Cement 0.1 bag @ Tk. 395.00 per bag

= Tk. 39.50

  1.  

Sand (F.M. 1.2) 0.5 cft @ Tk. 1,400.00 per % cft

= Tk. 7.00

(b)

Nuts with washer 4 nos @ Tk. 26.00 each

= Tk. 104.00

4.

Labour:

 

  1.  

Plumber 0.25 no @ Tk. 600.00 each

= Tk. 150.00

  1.  

Skilled labour 1 no @ Tk. 390.00 each

= Tk. 390.00

  1.  

Ordinary labour 0.5 no @ Tk. 320.00 each

= Tk. 160.00

 

Sub - Total

= Tk. 7,980.50

 

Profit 10.00%

= Tk. 798.05

 

Overhead 3.50%

= Tk. 279.32

 

Total

= Tk. 9,057.87

 

Add VAT with adjustment factor 1.06383 6.00%

= Tk. 578.16

 

Grand Total

= Tk. 9,636.03

 

Rate per No.

= Tk. 9,636.03

 

Say, Tk. 9,636 .00 each

 

26.3.2.2

Coloured (Marble Shaded) 700x370x795mm , 32.5kg or Equivalent

 

 

Considering 1 No. of fixture

 

1.

White Combicloset 1 no @ Tk. 9,270.00 each

= Tk. 9,270.00

3.

Fitting fixing materials:

 

(a)

Cement mortar (1:4)

 

  1.  

Cement 0.1 bag @ Tk. 395.00 per bag

= Tk. 39.50

  1.  

Sand (F.M. 1.2) 0.5 cft @ Tk. 1,400.00 per % cft

= Tk. 7.00

(b)

Nuts with washer 4 nos @ Tk. 26.00 each

= Tk. 104.00

4.

Labour: