Cement 0.1 bag Sand (F.M. 1.2) 0.5 cft Labour: Plumber 0.25 no Skilled labour 0.5 no Ordinary labour 0.5 no | @ @ @ @ @ | Tk. 395.00 Tk. 1,400.00 Tk. 600.00 Tk. 390.00 Tk. 320.00 Profit | per bag each | = = = = = | Tk. Tk. Tk. Tk. Tk. | 39.50 7.00 150.00 195.00 160.00 | |
Sub - Total 10.00% 3.50% | = = = | Tk. | 1,704.50 170.45 59.66 | ||||
Total | = | Tk. | 1,934.61 | ||||
| Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 123.49 | |
|
|
|
| Grand Total | = | Tk. | 2,058.10 |
|
|
|
| Rate per No. | = | Tk. | 2,058.10 |
|
| Say, | Tk. 2,058 .00 each |
|
|
| |
26.5.1.3 | Special coloured long pan with foot-rest 530x430x210 mm 12.5 | kg or equivalent |
|
|
|
| |
| Considering 1 No. of fixture |
|
|
|
| ||
1. | Special coloured long pan: 1 no | @ | Tk. 1,330.00 | each | = | Tk. | 1,330.00 |
2. | Fitting fixing materials: |
|
|
|
|
|
|
(a) | Cement mortar (1:4) |
|
|
|
|
|
|
Cement 0.1 bag | @ | Tk. 395.00 | per bag | = | Tk. | 39.50 | |
Sand (F.M. 1.2) 0.5 cft | @ | Tk. 1,400.00 | per % cft | = | Tk. | 7.00 | |
3. | Labour: |
|
|
|
|
|
|
Plumber 0.25 no | @ | Tk. 600.00 | each | = | Tk. | 150.00 | |
Skilled labour 0.5 no | @ | Tk. 390.00 | each | = | Tk. | 195.00 | |
Ordinary labour 0.5 no | @ | Tk. 320.00 | each | = | Tk. | 160.00 | |
|
|
|
| Sub - Total | = | Tk. | 1,881.50 |
|
|
| Profit | 10.00% | = | Tk. | 188.15 |
|
|
| Overhead | 3.50% | = | Tk. | 65.85 |
|
|
|
| Total | = | Tk. | 2,135.50 |
| Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 136.31 | |
|
|
|
| Grand Total | = | Tk. | 2,271.81 |
|
|
|
| Rate per No. | = | Tk. | 2,271.81 |
26.5.2.1 | White colour approx.530x450x290 mm 14.5 kg | Say, | Tk. 2,272 .00 each |
|
|
| |
|
|
|
| ||||
| Considering 1 No. of fixture |
|
|
|
|
|
|
1. | White long pan: 1 no | @ | Tk. 1,315.00 | each | = | Tk. | 1,315.00 |
2. | Fitting fixing materials: |
|
|
|
|
|
|
(a) | Cement mortar (1:4) |
|
|
|
|
|
|
Cement 0.1 bag | @ | Tk. 395.00 | per bag | = | Tk. | 39.50 | |
Sand (F.M. 1.2) 0.5 cft | @ | Tk. 1,400.00 | per % cft | = | Tk. | 7.00 | |
3. | Labour: |
|
|
|
|
|
|
Plumber 0.25 no | @ | Tk. 600.00 | each | = | Tk. | 150.00 | |
Skilled labour 0.5 no | @ | Tk. 390.00 | each | = | Tk. | 195.00 | |
Ordinary labour 0.5 no | @ | Tk. 320.00 | each | = | Tk. | 160.00 | |
|
|
|
| Sub - Total | = | Tk. | 1,866.50 |
|
|
| Profit | 10.00% | = | Tk. | 186.65 |
|
|
| Overhead | 3.50% | = | Tk. | 65.33 |
|
|
|
| Total | = | Tk. | 2,118.48 |
| Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 135.22 | |
|
|
|
| Grand Total | = | Tk. | 2,253.70 |
|
|
|
| Rate per No. | = | Tk. | 2,253.70 |
26.5.2.2 | Coloured 530x450x290 mm 14.5 kg | Say, | Tk. 2,254 .00 each |
|
|
| |
|
|
|
| ||||
| Considering 1 No. of fixture |
|
|
|
|
|
|
Coloured long pan: 1 no | @ | Tk. 1,643.00 | each | = | Tk. | 1,643.00 | |
Fitting fixing materials: |
|
|
|
|
|
| |
(a) | Cement mortar (1:4) |
|
|
|
|
|
|